Preamble
NOVA SCOTIA POWEll An Emera Company November 16,2010 Ms. Nancy McNeil Regulatory Affairs Officer/Clerk Nova Scotia Utility and Review Board 3rd Floor, 1601 Lower Water Street P.O. Box 1692, Unit "M" Halifax, NS B3J 3S3 Re: CI 38856 - L7011...

AI summary NSPI provided responses to information requests regarding a capital item, explaining that project dates were determined by line availability and that the cost estimate included replacements for defective components. The response also highlighted the confidentiality of contract costs to protect competitive pricing.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →