HomeConfidentialityM11307Evidence
Topic/Matter Intersection

Topic:"Confidentiality" in M11307

Matter: P-884 - Nova Scotia Power Inc. - 2023 Evergreen  Integrated Resource Plan (IRP) -  Action Plan and Roadmap
2 passages 2 documents

Confidentiality across all matters →

N-5Reply Submission - NSPI 1 passage
The study should also ask whether energy to meet those peak demands should be stored in a batery, a tank, a lake or in a regionally linked, diversified e p. p. 11
that correctly iden�fying the need for capacity is paramount for all subsequent IRP runs. The study should also ask whether energy to meet those peak demands should be stored in a batery, a tank, a lake or in a regionally linked, diversifi...

AI summary The text discusses the importance of correctly identifying capacity needs for Integrated Resource Plan (IRP) runs and the need for clear standards to make trade-offs among different energy storage options. It also addresses concerns around the sharing of commercially sensitive information during negotiations and its potential impact on achieving favorable commercial terms.

91361Submission - NRR 1 passage
Commercial Sensitivity
Commercial Sensitivity NSP has made the IRP process more opaque than necessary by shielding numbers used in assumptions on the grounds of commercial sensitivity. As this is not a UARB proceeding, stakeholders have no way to contest this la...

AI summary NSP is criticized for making the IRP process opaque by withholding numbers due to commercial sensitivity, limiting stakeholder scrutiny. NRR acknowledges UARB's confidentiality measures but highlights the absence of Quebec negotiation details as undermining process confidence.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →