Matter: Nova Scotia Power Inc. - CI C0070486 – HYD Lower Great Brook Stoplog Replacement – $3,593,884
2 passages 2 documents

Confidentiality across all matters →

100738Board Decision Letter 1 passage
Section 1 p. p. 0
January 27, 2026 [[email protected]](mailto:[email protected]) Lana Myatt Senior Regulatory Analyst Nova Scotia Power Inc. PO Box 910 1223 Lower Water Street Halifax, NS B3J 3S8 Dear Ms. Myatt: M12590 – Nova Scotia Power Inc. – CI...

AI summary Nova Scotia Power Inc. has requested approval for a capital expenditure of $3,593,884 to replace all 120 stoplogs at the Lower Great Brook Generating Station. The Board has reviewed the application and approved the request for confidentiality under Rule 12 of the Board Regulatory Rules.

100738Board Decision Letter 1 passage
Section 1 p. p. 0
January 27, 2026 [[email protected]](mailto:[email protected]) Lana Myatt Senior Regulatory Analyst Nova Scotia Power Inc. PO Box 910 1223 Lower Water Street Halifax, NS B3J 3S8 Dear Ms. Myatt: M12590 – Nova Scotia Power Inc. – CI...

AI summary Nova Scotia Power Inc. has requested approval for a capital expenditure of $3,593,884 to replace all 120 stoplogs at the Lower Great Brook Generating Station. The Board has reviewed the application, received responses to information requests, and approved the request for confidentiality.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →