Topic:"Confidentiality" in M12696

Matter: NSP Maritime Link Inc. (NSPML) - Application to Review the Holdback Mechanism
13 passages 11 documents

Confidentiality across all matters →

N-2(C)NSPML (BW) RIRs 1-22 - Confidential 1 passage
Section 1 p. p. 0
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Certain files are accepted as confidential because they are protected by privacy law, or contain sensitive information that, if disclosed, could...

AI summary The document is a confidentiality notice for a Nova Scotia regulatory proceeding, explaining that access requires a Confidentiality Agreement. It outlines contact methods for the Clerk of the Board (phone, email) and provides the document number 320036. The notice emphasizes privacy protections and sensitive information disclosure risks.

N-3(C)NSPML (CA) RIRs 1-4 - Confidential 1 passage
Section 1 p. p. 0
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Certain files are accepted as confidential because they are protected by privacy law, or contain sensitive information that, if disclosed, could...

AI summary This confidentiality notice indicates the document contains sensitive information protected by privacy laws. Access requires a Confidentiality Agreement, and contact details for the Clerk of the Board are provided for access requests. Document number 320036 is referenced.

N-4NSPML (IG) RIRs 1-26 - Redacted 2 passages
Article 22. Confidentiality p. pp. 145-148
Article 22. Confidentiality 22.1 Confidentiality. Confidential Information shall include, without limitation, all information relating to a Party's technology, research and development, business affairs, and pricing, and any information su...

AI summary Article 22 defines Confidential Information as data related to technology, business affairs, or pricing, designated as confidential in writing or orally. Parties must provide written justification for confidentiality claims upon request, with each party covering their own costs for confidential treatment.

Article 25. Information Access and Audit Rights p. pp. 151-152
Article 25. Information Access and Audit Rights 25.1 Information Access. Each Party (the "disclosing Party") shall make available to the other Party information that is in the possession of the disclosing Party and is necessary in order fo...

AI summary Article 25 outlines information access and audit rights under the Large Generator Interconnection Agreement (LGIA). Parties must disclose necessary information to verify costs and obligations, report non-force majeure events with details, and allow audits of accounts and records during normal business hours, subject to confidentiality constraints.

N-4(C)NSPML (IG) RIRs 1-26 - Confidential 1 passage
Section 1 p. p. 0
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Certain files are accepted as confidential because they are protected by privacy law, or contain sensitive information that, if disclosed, could...

AI summary The document is marked confidential due to privacy laws or sensitive information. Access requires a Confidentiality Agreement. A public redacted version may be available. Contact details for the Clerk of the Board are provided, along with instructions to request access to the document.

N-5(C)NSPML (NSEB) RIRs 1-19 - Confidential 1 passage
Section 1 p. p. 0
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Certain files are accepted as confidential because they are protected by privacy law, or contain sensitive information that, if disclosed, could...

AI summary The document is marked confidential due to privacy or sensitive information. Access requires a Confidentiality Agreement, and a redacted public version may be available. Contact details for the Clerk of the Board are provided for access requests.

N-6(C)NSPML (SBA) RIRs 1-6 - Confidential 1 passage
Section 1 p. p. 0
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Certain files are accepted as confidential because they are protected by privacy law, or contain sensitive information that, if disclosed, could...

AI summary The document is marked confidential under Board rules, with access restricted to protect sensitive information. A public redacted version may be available, and access requests must be directed to the Clerk of the Board via phone, toll-free, or email. Document number 320036 is referenced.

N-7Evidence - BW 1 passage
Section 246 p. p. 18
- NS Block, measured in MWh (excluding Make-up Energy), is received during each of 12 - consecutive months."[41](#page-18-1) In introducing this requirement, the Board also stated: - NSPML/NS Power may apply to the Board for relief if it c...

AI summary The requirement mandates NSPML to receive twelve consecutive months of NS Block volumes (excluding Make-up Energy) at least 90% of the total monthly volumes called for under the Energy and Capacity Agreement. This prevents over-reliance on Make-up volumes and ensures consistency and predictability in volume delivery.

101313IG (NSPML) IR 1 to 26 - Confidential 1 passage
Section 1 p. p. 0
CONFIDENTIALITY NOTICE The document you are attempting to access has been filed in confidence. Some exhibits, noted as confidential, contain information which if released might cause financial or other harm to the party filing it, or which...

AI summary The document is marked confidential, with access restricted to protect sensitive information. It directs users to contact the Nova Scotia Energy Board's Clerk for access via a Confidentiality Agreement. Contact details and document number (320036) are provided.

101387Email to NSPML requesting further jusification for extension request 1 passage
Statement of Confidentiality p. p. 0
Statement of Confidentiality This message (including any attachments) may contain private or protected information meant for a specific person or organization. If you received this by mistake, please let the sender know, do not communicate...

AI summary The email from Sharleen Nielsen (Emera) to Crystal Henwood (Nova Scotia) discusses NSP Maritime Link Inc.'s (NSPML) application to review the holdback mechanism and propose changes to filing dates. The message emphasizes confidentiality and includes numerous recipients from various organizations involved in the regulatory process.

101681Confidential Undertaking 1 passage
Schedule "A"
Schedule "A" - 1. NSP Maritime Link Inc. ("NSPML") will provide Designated Confidential Information, as defined herein, to the Designated Recipients as defined below. - 2. Designated Confidential Information shall consist of material, whet...

AI summary Schedule 'A' outlines conditions for NSP Maritime Link Inc. (NSPML) to provide Designated Confidential Information to specified recipients. Access is restricted to signatories of the attached undertaking, with prohibitions on sharing information beyond designated recipients. The Nova Scotia Energy Board is referenced as the authority confirming confidential information designations.

101682Letter from NSPML re: RIRs / confidentiality 2 passages
Section 1 p. p. 0
April 21, 2026 [[email protected]](mailto:[email protected]) Ms. Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, Nova Scotia B3J 3P6 Dear Ms. Henwood: RE: M126...

AI summary NSP Maritime Link Inc. (NSPML) submitted responses to information requests in M12696, seeking confidential treatment for documents containing commercially sensitive data, third-party information, and performance data from Newfoundland and Labrador Hydro (NLH). The request emphasizes protecting negotiation capabilities and adhering to third-party distribution restrictions.

Section 2 p. p. 0
ins performance data related to the Labrador Island Link that was provided by Newfoundland and Labrador Hydro (NLH). NLH considers this data to be sensitive and requested it not be disclosed publicly. 4. In respect of IG IR-07, NSPML seeks...

AI summary The document discusses requests for confidential treatment of sensitive data related to the Labrador Island Link by Newfoundland and Labrador Hydro (NLH) and maintenance schedules by NSP Maritime Link Inc. (NSPML). NSPML also removed redactions in IG IR-12 after determining they did not require confidentiality.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →