Matter: Nova Scotia Power Inc. - Commercial Net Metering Program - 2025 Annual Report �
2 passages 1 document

Confidentiality across all matters →

N-3NSPI (IG) RIR 1 to 4 2 passages
Section 4 p. p. 2
(c) Not confirmed. The cost allocation and refund methodology described in NS Power's Annual Interconnection Processes Proceeding Report (M12778) reflects the cost allocation straw proposal for distribution network upgrades that was provid...

AI summary NS Power's cost allocation and refund methodology for distribution network upgrades has not been accepted by the Board and is not currently under approval by NSEB. NS Power has not filed revisions to Regulation 2.12 and considers it premature to discuss recommendations related to distribution network upgrades, citing confidentiality under the SSGIA.

Section 5 p. p. 2
connection customer network upgrade costs and refunds are confidential to the interconnection customer under the SSGIA and so limited information would be publicly available in any case.[1](#page-2-0) (e) NS Power is not in a position to p...

AI summary The document discusses confidentiality of connection customer network upgrade costs and refunds under the SSGIA, and notes that NS Power cannot provide a timeline for filing amendments to certain regulations due to ongoing evaluations.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →