Matter: Nova Scotia Power Inc. - CI C0061552 – L6043 Replacements and Upgrades- $3,603,3512026 Q1 Capital Reports
2 passages 1 document

Confidentiality across all matters →

101860Letter NSPI re:First Quarter 2026 Capital Items 2 passages
Request for Confidentiality p. p. 0
Request for Confidentiality Pursuant to Rule 12 of the Board Regulatory Rules, NS Power requests confidential treatment of certain portions of the material filed in support of the following Capital Work Orders: - (1) CI C0044172 L7005 Cans...

AI summary NS Power requests confidential treatment for specific Capital Work Orders under Rule 12 of the Board Regulatory Rules, citing sensitive information in the supporting materials. The request includes six projects related to infrastructure and solar energy initiatives.

Commercial Information p. p. 0
Commercial Information Items 1, 2, 3 and 4: Partial confidentiality was applied to costs associated with materials, contracts, freight, consulting, licensing and software details provided in the capital work orders. To protect value for cu...

AI summary NS Power applies partial confidentiality to capital work order costs and vendor information to protect customer interests, prevent competitive disadvantages, and maintain system security. Confidentiality preserves competitive pricing, avoids higher customer costs, and safeguards distribution system reliability.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →