Topic/Matter Intersection

Topic:"Corporate Adjustments" in M12394

Matter: NSP Maritime Link Inc. -  2026 Assessment Application - NSPML
5 passages 3 documents

Corporate Adjustments across all matters →

N-8NSPML (NSEB) RIR 1 to 44 - Redacted 3 passages
NON-CONFIDENTIAL p. p. 1
NON-CONFIDENTIAL Title Proposed FTEs in 2025; Actual in 2024 Position Description Reliability/Planning Engineer (now Sr. Electrical Engineer) 1.00 Provides planning support for the Engineering and technical teams. Senior Corporate Accounta...

AI summary The document outlines proposed full-time equivalents (FTEs) and roles for various positions within NSPML in 2025, including roles related to reliability, planning, finance, asset management, and environmental affairs, with a total complement of 29.5 FTEs.

9.10 Corporate Policies p. p. 124
9.10 Corporate Policies It is understood and agreed that the Manager may provide the coverage referenced in this Agreement through policies covering other assets and/or operations operated by the Manager.

AI summary The Manager is permitted to provide coverage through policies that apply to other assets and operations under their management, as outlined in the agreement.

12.3 Own Property Damage p. pp. 128-129
12.3 Own Property Damage For the avoidance of doubt, it is the Parties' intent that, subject to any right a Party may have to seek compensation from a third party who caused the Loss or from insurance, each Party shall be responsible for a...

AI summary The Parties agree that each is responsible for Losses to its own property, including facilities, equipment, and materials on the site of Defined Assets, regardless of the cause, including O&M Activities or the actions of the other Party or its affiliates. This applies unless compensation from a third party or insurance is available.

N-18British Columbia Utilities Commission Decision and Order G-236-23 1 passage
T. A. Loski, Commissioner p. p. 0
T. A. Loski, Commissioner EXECU JTIVE SU UMMARY i 1.0 INTRODUCTION 1.1 Background 1 1.2 Purpose and Scope of the Generic Cost of Capital Proceeding 1 1.3 Regulatory Process 2.0 KEY P KEY PRINCIPLES AND DECISION FRAMEWORK 2.1 Legislative Re...

AI summary This document outlines the structure and key considerations of a generic cost of capital proceeding, including legislative requirements, peer data analysis, credit ratings, financial models, and determinations on capital structure and return on equity. It discusses the use of various financial models like CAPM and DCF, as well as considerations related to business risk and flotation costs.

99012IG (NSPML) IR 1 to 22 1 passage
29
29 1 (a) Please confirm whether the change in the capital structure was initially 2 recommended by Concentric or suggested to Concentric by NSPML? - 3 (b) If this was initially requested by NSPML, how did NSPML initially come up 4 with the...

AI summary The text presents a regulatory inquiry regarding a change in capital structure, specifically asking whether the change was recommended by Concentric or suggested by NSPML and how NSPML arrived at the proposed 40% equity thickness.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →