DATE FILED: April 8, 2026 Page 4 of 19 1 2.0 RESPONSE TO CA (WILSON) EVIDENCE 22 projects, for example). For repetitive work that has consistent, well understood risks, the 23 contingency percentage applied should solely be based on the le...
AI summary The document discusses NS Power's disagreement with a recommendation to file a risk matrix for projects with contingency over 10%, arguing that such matrices are unnecessary for well-understood risks and that they are already accounted for in project management practices.