5.0 Budget Pricing Pricing in this proposal has been based on the scope of work as outlined in this document. The prices presented below for the Siemens staff and services, trades, subcontractors and other services that may be utilized dur...
AI summary The document outlines the budget pricing for the Trenton 2010 Turbine Outage, based on a time & material (T&M) basis. It specifies that final pricing will be governed by Siemens Terms & Conditions and that any additional costs due to delays or changes not caused by Siemens or its subcontractors will be the responsibility of NSPI.
REDACTED 1 Response IR-GI2: (cont'd) 2 3 b) The breakdown of the estimated project cost is as follows: 4 5 i) Regular Labour: $184,000 6 7 ii) Term Labour: _ 8 9 iii) Power Production Contracts: _ 10 11 iv) Materials: _ 12 13 v) Interest a...
AI summary The response outlines the estimated project costs, including regular and term labour, power production contracts, materials, and interest and asset retirement obligations. It emphasizes the need to keep certain costs confidential to prevent suppliers from gaining competitive advantages and increasing costs for customers.