N-1Redacted Work Order 5/4/2010 2 passages
Cost Centre 800 - 800-Services - Admin. Budget Version 2010 ACE Plan (New AFUDC) p. p. 1
Cost Centre 800 - 800-Services - Admin. Budget Version 2010 ACE Plan (New AFUDC) Capital Item Accounts Acct Actv Account Activity Forecast Amount Amount Variance 094 094 - Interest Capitalizeq 7,386 0 7,386 013 002 013 - COPS Contracts 002...

AI summary The document presents a budget forecast for Cost Centre 800, focusing on administrative expenses related to the 2010 ACE Plan and the introduction of a new AFUDC. It includes detailed line items with forecasted amounts, actual amounts, and variances for various capital and operational activities.

Why do this project this way? p. p. 1
Why do this project this way? Alternatives to extending this feeder include building a 138kV transmission line and a new substation in Eastern Passage. This item was investigated in th\'l Distribution Planning Study . "Dartmouth 25kV Syste...

AI summary The document outlines alternatives to extending a feeder, including a 138kV transmission line and substation in Eastern Passage, referencing a 2008 Distribution Planning Study. The current approach is deemed the most cost-effective, executed by NSPI and an affiliate under ACE 2010 guidelines.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →