N-1Redacted Work Order 9/8/2010
2 passages
Why do this project this way? The need for repair is based on OEM recommendations. These repairs have been successfully completed on similar units. By performing the work in 2010 during the commissioning of TUC#6, replacement energy costs...
AI summary The project's repair is based on OEM recommendations, with similar units successfully repaired. Performing the work in 2010 during TUC#6 commissioning minimized replacement energy costs.
LM6000 - Overhaul Tuft's Cove #5 EngineD Summary of Alternatives Budget Year: Division: Department: Originator: 2010 Po ower Proc uction Waj Cor nbus toin Turbin es 178 100000 Date: CI Number: Project No. : 23-Aug-10 • 28752 1 tbd Alternat...
AI summary The document presents an analysis of alternatives for the overhaul of the LM6000 engine at Tuft's Cove #5. It outlines the costs and benefits of performing the overhaul in 2010, with a focus on avoiding higher costs due to potential downtime and derating of the engine. The analysis assumes a conservative overhaul life of 3 years and estimates the avoided costs for 2010 and 2011.
Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →