Topic/Matter Intersection

Topic:"Cost Considerations" in M03511

Matter: CI# 38856 - P-128.10 - NSPI WO - L7011 Deteriorated Replacements - $2,055,736
2 passages 2 documents

Cost Considerations across all matters →

N-2Redacted Responses to Information Requests 1 passage
of Units Unit cost Total
CI 38856 - L7011 Deteriorated Replacements (NSUARB P-128.10) NSPI Responses to UARB Information Requests REDACTED 1 Request IR-5: 2 3 Based on Attachment 1 of NSPI's response to IR-T1, filed in support of the 2010 ACE Plan 4 approval reque...

AI summary NSPI responds to UARB's information request regarding discrepancies in hourly rates and estimated hours for a transmission project. NSPI clarifies that the rate on Page 7 was incorrect and explains that the correct rate applies to distribution work, not transmission. The estimated hours for the project are approximately 7,965 Standard Work Unit Hours.

05649Information Requests 11/2/2010 1 passage
Section 1
MaHing address Nova Scotia Utility and Review Board Office PO Box 1692, Unit "M" 3rd Floor Halifax, Nova Scotia 1601 Lower Water Street B3J 353 Halifax, Nova Scotia 83J 3P6 uarb,board@gov,ns,ca 902424-4448 t Web www.nsuarb.ca 902 424-3919...

AI summary Nova Scotia Utility and Review Board has requested additional information regarding a capital item in NSPI's 2010 ACE Plan Work Order, including activation and completion dates, cost support for materials, and clarification on the increase in costs due to contract changes.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →