CI 38856 - L7011 Deteriorated Replacements (NSUARB P-128.10) NSPI Responses to UARB Information Requests REDACTED 1 Request IR-5: 2 3 Based on Attachment 1 of NSPI's response to IR-T1, filed in support of the 2010 ACE Plan 4 approval reque...
AI summary NSPI responds to UARB's information request regarding discrepancies in hourly rates and estimated hours for a transmission project. NSPI clarifies that the rate on Page 7 was incorrect and explains that the correct rate applies to distribution work, not transmission. The estimated hours for the project are approximately 7,965 Standard Work Unit Hours.