Matter: CI# 38943 - P-128.10 - NSPI WO - LIN1 Boiler Refurbishment - $1,653,592
1 passage 1 document

Cost Considerations across all matters →

N-1Redacted Work Order 1 passage
LIN1-Boiler Refurbishment Summary of Alternatives p. p. 8
LIN1-Boiler Refurbishment Summary of Alternatives Budget Year: 20101 Date: 19-Jul-10 Division: Power Production CI Number: 38943 Department: Lingan Project No. : 1 Originator: 1 Alternative After T~x WACC PV of EVA / NPV Rank IRR Disc Pay...

AI summary The document presents a summary of alternatives for boiler refurbishment at the Lingan Power Plant. It evaluates the financial and operational impacts of refurbishing the boiler versus doing nothing, highlighting costs, net present value, internal rate of return, and potential unscheduled outages due to tube leaks.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →