Matter: Nova Scotia Power Inc. - CI C0030984 – IT - Cisco UCS Lifecycle - $2,088,998 (FIN)
1 passage 1 document

Cost Considerations across all matters →

99039Board Decision Letter 1 passage
Section 3 p. pp. 0-1
The scope of the project involved replacing the end-of-life B200 M4 blades and 6200 Series Fabric Interconnect assets in NS Power's current Cisco Unified Computing System (UCS) computer environment. The project was underspent primarily due...

AI summary The project involved replacing outdated IT assets in NS Power's Cisco UCS environment and was underspent due to unused contingency and lower internal labor costs. The Board approved the final cost of $2,088,998 but noted the delay in submitting the final cost report and reminded NS Power to submit FINs within six months of project completion.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →