Topic/Matter Intersection

Topic:"Cost Considerations" in M12455

Matter: Nova Scotia Power Inc. - CI C0059783 – HYD Upper Lake Falls 2 Overhaul – $1,582,014
1 passage 1 document

Cost Considerations across all matters →

N-1Application 1 passage
Preamble p. p. 5
This project is being submitted as an AACE Class 3 estimate. The defined deliverables of this project indicate that 73% of the Class 3 deliverables have been completed. AACE recommends applying between 10% to 30% contingency to estimates i...

AI summary The project is submitted as an AACE Class 3 estimate with 73% of deliverables completed. A 15% contingency is applied to account for risks such as water management and potential refurbishment needs. The maturity level reflects the completion status of deliverables, with descriptors indicating progress from 'Not Required' to 'Complete'.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →