Topic/Matter Intersection

Topic:"Cost Considerations" in M12536

Matter: NSPI General Complaint - Overhead Wires - Tye Laframboise
2 passages 2 documents

Cost Considerations across all matters →

L-3NSPI (NSEB) RIR-1 to RIR-6 (redacted) 1 passage
1 Request IR-2: p. p. 3
1 Request IR-2: 2 3 Please provide a cost table with itemised work details for the underground service upgrade, 4 which includes: 5 6 (a) A clear itemisation of all costs involved in upgrading the underground service to 200 7 amps. 8 9 (b)...

AI summary The request asks for a detailed cost table for an underground service upgrade to 200 amps, including cost breakdowns and responsibilities. NS Power explains that they cannot provide detailed estimates due to undefined work scope and that utility-side upgrades up to the URD box are their responsibility, while homeowner-owned infrastructure is the customer's responsibility.

100868NSEB (NSPI) IR-1 to IR-6 (redacted) 1 passage
Request IR-2:
Request IR-2: - Please provide a cost table with itemised work details for the underground service upgrade, which includes: - a) A clear itemisation of all costs involved in upgrading the underground service to 200 amps. - b) Specify the c...

AI summary Request IR-2 asks for a detailed cost table for an underground service upgrade to 200 amps, specifying the cost breakdown and responsibilities of NS Power and the homeowner.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →