This project is being submitted as a Class 3 estimate. The defined deliverables of this project indicate that 88% of the Class 3 deliverables have been completed. A contingency value of 20% was selected to account for specific risks such a...
AI summary The project is submitted as a Class 3 estimate with 88% of deliverables completed. A 20% contingency is included to address risks like deteriorated copper in rotor windings, asbestos, and unforeseen overtime or material cost increases.
T O T O CUSTOMER PO # RFQ/RFP # Customer WO # ON SITE AND TRAVEL DT MON REP TWO HOURS PER DAY TRAVEL WHILE ON SITE DUE TO ACCOMIDATION AVABILITY. 26 HOURS TOTAL MN1008 COMPLETE SERVICE REPORT INCLUDING DWG FILE OF WINDING DIAGRAM HOUR 6.00...
AI summary The text outlines various costs associated with on-site work and travel, including flight, hotel, per diem, mileage, and shop supplies. It includes estimated expenses and quantities for each item, providing a detailed breakdown of the associated costs.