E-12027-2031 DSM Plan Application
8 passages
DSM is a long-term investment with lasting benefits and considerable lifetime savings, yet the Preferred Plan also contributes to short-term and immediate ratepayer benefits. In the short-term, the Preferred Plan will achieve 435.4 GWh of...
AI summary The Preferred Plan for DSM is highlighted as a long-term investment with immediate and lasting benefits. It will achieve significant energy savings and cost avoidance, with the investment being fully recouped by 2032. The payback analysis shows that the plan is in the best interests of ratepayers due to lower current investment costs and inflation mitigation.
2 6.1 OVERVIEW - 3 The Preferred Plan represents a comprehensive suite of programs and service offerings which will deliver - 4 approximately 435.4 GWh of affordable, incremental net energy savings, 85.0 MW of cumulative system- - 5 peak d...
AI summary The Preferred Plan outlines a comprehensive suite of energy efficiency programs and service offerings that aim to deliver significant energy savings and demand reductions over the 2027–2031 period. It emphasizes affordability, long-term ratepayer benefits, and cost-effectiveness, with a focus on achieving energy efficiency at a lower lifetime unit cost compared to fuel costs.
Table 7: 2027–2031 Plan - Portfolio Level Insights Insights 2027–2031 Energy Efficiency Energy Savings as % of NS Power Load 0.8% Energy Savings (EE) Split (RES/BNI) 29/71 Demand Savings (EE) Split (RES/BNI) 44/56 Dedicated Low-Income & Eq...
AI summary Table 7 provides insights into the 2027–2031 plan, highlighting energy efficiency savings, demand response capacity, solar-PV generation, and associated costs and benefits. It includes metrics such as energy savings percentages, unit costs, and CO₂e savings across residential and BNI (Business and Non-Industrial) sectors.
2.2.6 UNIT COST RESULTS Unit cost data is a calculation output reflecting E1's investment and energy savings over a defined time period. Actual results for the 2023–2025 period show a portfolio-level unit cost of $0.37/kWh, slightly lower...
AI summary The 2023–2025 unit cost for E1's energy efficiency programs was slightly lower than the approved plan, but residential unit costs have risen due to the pause of the Residential Behaviour program and changes in program components. These trends are expected to continue into 2026 and influence the development of the 2027–2031 DSM Preferred Plan.
ecting the mix of program components and the projected costs and savings associated - with these program components. By comparison, the portfolio unit cost for the 2026 DSM Extension was - $0.49/kWh. - The increase in portfolio unit cost o...
AI summary The document discusses the increase in portfolio unit cost for the 2027–2031 energy efficiency programs, driven by changes in product mix and savings. The shift from low-cost lighting measures to more complex upgrades and the reduction in savings from heat pumps are key factors.
3 [Table 47](#page-169-0) provides the program performance indicators. 5 Table 47: 2027–2031 Demand Response Performance Indicators Year Investment ($ million) Available Capacity (MW) Participation (devices) Participation (participants) Le...
AI summary Table 47 outlines the 2027–2031 Demand Response (DR) performance indicators, including investment, available capacity, participation numbers, and the Program Administrator Cost (PAC) test. The table shows a steady increase in investment and available capacity over the years, with participation numbers remaining relatively stable. The PAC test is defined as a benefit/cost ratio comparing lifetime benefits to DR investment, with levelized costs calculated over a ten-year period.
17 Table 1: 2027–2031 Alternate Scenario Portfolio Level Insights Insights 2027–2031 Energy Efficiency Energy Savings as % of NS Power Load 0.8% Energy Savings (EE) Split (RES/BNI) 29/71 Demand Savings (EE) Split (RES/BNI) 44/56 Dedicated...
AI summary This table provides insights into the 2027–2031 alternate scenario portfolio, including energy efficiency savings, demand response capacity, solar-PV generation, and overall benefits of the alternative plan, such as energy savings, investment, and CO₂e reductions.
1 Table 6: 2029 Alternate Scenario Savings and Investment by Program Component 2029 Investment ($ million) Lifetime Benefits ($ million) First Year Energy Savings (GWh) Lifetime Energy Savings (GWh) Peak Demand Savings (MW) Available Deman...
AI summary Table 6 presents the 2029 Alternate Scenario Savings and Investment by Program Component, focusing on Affordable Multifamily Housing. The data includes investment, lifetime benefits, energy savings, and other metrics, highlighting the financial and energy impact of this program.
E-9E1 (IG) RIRs 1-29
11 passages
Industrial customers are allocated any portion of the Enabling Strategies budget for electrification research. If so, please provide the dollar amounts allocated to each class over the plan period. (d) If, during the 2027–2031 plan period,...
AI summary The response outlines how industrial customers are allocated portions of the Enabling Strategies budget for electrification research and discusses the process for introducing electrification measures if they become cost-effective under the modified-PAC test, including cost allocation and potential Board approval.
dentified. (b) Please provide the methodology and all assumptions underlying the lifetime unit cost calculation, including assumed savings lifetimes, discount rate, and realization rates by measure. (c) Please provide the comparable first-...
AI summary E1 responds to requests for methodology details on unit cost calculations for the DSM Plan, noting program support cost allocations, timing constraints affecting 2026 updates, and references to Attachment 1 for cost comparisons between 2026 and 2027–2031 plans. It also mentions administration cost allocations and the incorporation of 2025 evaluation adjustments in the 2027–2031 plan.
- 4 Attachment 2 to this IR response. Residential Instant Savings - Cost and Energy Savings Analysis Administrative / Overhead Cost Reduction (0.17) 2027-2031 Unit Cost $ 2.67 Change in Costs (0.99) 2027-2031 Average Cost 4.86 Energy Savin...
AI summary The document provides cost and energy savings analyses for residential and efficient product installation programs, including administrative costs, changes in costs, and energy savings projections from 2026 to 2031. It outlines unit costs, savings from various initiatives like heat pumps and building envelope improvements, and the impact of participation changes on overall savings.
To: Gina Thompson, Kate McDonald EfficiencyOne From: Michael Goldman, Matt Nelson, Jodi Hanover, Apex Analytics LLC Subject: Review of EfficiencyOne First-Year Costs and Unit Cost Reasonableness Date: May 22, 2026 EfficiencyOne's (E1) firs...
AI summary EfficiencyOne's first-year energy efficiency program costs for the 2027–2031 DSM Plan are deemed reasonable and prudent by Apex Analytics, based on a jurisdictional comparison with six similar regions. The analysis considers factors like program maturity and savings attribution, reinforcing the conclusion that E1's costs align with industry norms and cost-effectiveness criteria.
Residential Programs Within the residential sector, unit costs increase between 2025 and the 2027–2031 period, with variation by program type. Residential Instant Savings shows an increase in unit cost in 2026 relative to 2025, followed by...
AI summary The residential programs section discusses changes in unit costs across various initiatives from 2025 to 2031. Unit costs for programs like Residential Instant Savings and Home Energy Assessments increase initially before fluctuating. Efficient Product Installation and Affordable Housing programs also show rising costs due to factors like reduced participation, measure mix changes, and increased incentives.
Conclusions When evaluated in the context of other jurisdictions, E1's submitted first-year energy efficiency costs for the 2027-2031 Plan are reasonable, prudent, and consistent with industry norms. It should be expected that there will b...
AI summary E1's 2027-2031 DSM Plan first-year energy efficiency costs are deemed reasonable and prudent, consistent with industry norms. The increase in \/kWh costs is attributed to factors like the phase-out of low-cost measures and increased investment in equity and electrification programs. These trends are consistent with regulatory findings in other jurisdictions.
avings for each affected customer class. (b) Please explain the allocation methodology used to allocate each category of expenditure to each customer class (and/or program/measure). Response IR-12:
AI summary The response IR-12 is requested to explain the allocation methodology for expenditures to customer classes and programs. The request focuses on how costs are distributed across different categories and customer segments.
Date Filed: May 28, 2026 IG IR-12, Attachment 1, Page 1 of 1 DSM Statement of Operations ($ millions) Incentives $ 44.53 $ 4.13 $ 1.72 $ 8.31 $ 7.04 $ 4.67 $ - $ 0.89 $ 1.60 $ 7.04 $ 0.75 $ 0.55 $ 2.85 $ 0.03 $ 0.57 $ - $ - $ 4.37 Evaluati...
AI summary The document presents a detailed breakdown of the DSM Statement of Operations, highlighting various financial categories such as incentives, program support, and administrative costs. It includes figures related to evaluation, verification, amortization, and other operational expenses.
Response IR-13: (a) Enabling Strategies costs for the Development and Research and Other Enabling Strategies categories were allocated to the rate classes according to the percentage of total program costs each rate class represents. Indus...
AI summary Enabling Strategies costs are allocated to rate classes based on the percentage of total program costs each class represents. Industrial rate classes are excluded from Education and Outreach costs, while Market Transformation costs are fully allocated to the Residential rate class.
Request IR-16: Reference: Exhibit E-1, Application, Appendix A, Section 4.7, pages 40–42/112; Exhibit E- 1, Appendix B, Attachment 2. Preamble: E1 states that the rate-class allocation of expenditures was developed using three years of his...
AI summary The request seeks detailed information on the rate-class allocation methodology used by E1, including its full methodology, historical data, reconciliation with the 2027–2031 Preferred Plan, and confirmation of programs requiring bespoke assumptions. It also asks for confirmation on mid-course adjustments affecting spending allocations.
- (d) The following IR response was provided by Elenchus. - Large Industrial customers have rate increases over the DSM plan period for Demand Response because the impact of reallocating demand-related costs to the Large Industrial class e...
AI summary Large Industrial customers face rate increases during the DSM plan period due to reallocating demand-related costs, as their peak demand reduction is lower than the overall system reduction. This leads to a higher allocation of energy-related costs to the Large Industrial class.
E-12E1 (NSEB) RIRs 1-66 - Redacted
22 passages
Following its jurisdictional comparison analysis, Apex then considered the unique circumstances for Nova Scotia based on its historical electricity demand, climate goals, and needs as a province. Apex examined Nova Scotia's priorities and...
AI summary Apex analyzed Nova Scotia's energy efficiency programs, considering historical demand, climate goals, and E1's capacity. Despite increased costs due to inflation and reduced savings from some measures, energy efficiency remains cost-effective. Reducing program goals could disrupt the market, leading to higher costs and reduced service. Apex supports maintaining current savings targets.
13 Table 1: Demand Response Non-Incentive Cost Considerations Cost Category E1 Cost Considerations Program Administration Annual costs associated with program management, including E1 staffing, overhead, and evaluation activities. Updated...
AI summary The table outlines non-incentive cost considerations for demand response programs, including program administration, delivery, marketing, and technology enablement. It highlights updated assumptions and cost-sharing opportunities, informed by current contracts and future cost changes.
E1 Responses to Nova Scotia Energy Board (NSEB) Information Requests NON-CONFIDENTIAL Cost Category E1 Cost Considerations Program Development One-time program start-up costs. Applied only to the 2023–2025 DSM Plan and are not included in...
AI summary This document provides E1's responses to Nova Scotia Energy Board (NSEB) information requests, focusing on cost considerations for the 2023–2025 DSM Plan, including one-time program start-up costs and detailed input assumptions for cost categories.
9 DSM Salary costs are projected to increase between 3.6% - 4.2% over the 2027–2031 10 Plan period related to anticipated performance increases and inflation.
AI summary DSM salary costs are expected to rise by 3.6% to 4.2% from 2027 to 2031 due to anticipated performance increases and inflation.
In thousands of dollars 2026 2027 2028 2029 2030 2031 DSM Benefit Costs $ 1,759 $ 1,747 $ 1,815 $ 1,880 $ 1,955 $ 2,038 11
AI summary The table presents the projected DSM Benefit Costs from 2026 to 2031, showing a steady increase in costs over the years.
PRICE SETTING Price setting is the process of coming up with the cost of a good or service for a consumer. With price setting, there are two influences: - 1. The value a consumer is willing to pay (participant perceived value) - 2. The pro...
AI summary Price setting involves balancing consumer perceived value and production/distribution costs plus return on investment. Perceived value is difficult to quantify and varies by individual, while return on investment can be calculated. Strategies like consumer surveys, competitive research, and historical data are used to estimate perceived value curves, which often follow a sigmoid relationship based on price elasticity of demand.
Table 2: Incremental Equipment Cost Scenarios Scenario General Description New Purchase/Installation A customer may decide to make a new purchase for a technology or service. There is not a current technology or service in use. For example...
AI summary This table outlines the 'New Purchase/Installation' scenario, where a customer purchases a new technology or service without existing infrastructure. It defines the standard technology as the most popular or commonly used option, or non-existent in some cases. Incremental Equipment Costs are calculated as the difference between the efficient option and the base case.
Participant Cost Test In evaluating a participant's purchase decision from a financial perspective, the PC test is a useful analysis to deploy. It assesses all of the direct financial considerations that a participant faces in making a pur...
AI summary The Participant Cost (PC) test evaluates whether the financial benefits of a technology or service outweigh the financial costs from the participant's perspective. Benefits include incentives, tax credits, and utility bill savings, while costs include purchase, installation, and maintenance expenses, excluding utility bill savings to avoid double-counting.
Measure Project Cost ($) Simple Project Payback Current Cost to Customer Cost to Customer Threshold Custom Project Retrofit Track $96,424 4 years 25% 50% 2 years Table 33: Cost to Customer Incentive Level Threshold for Average Project in C...
AI summary Table 33 outlines the cost to customer incentive level threshold for an average project in a custom retrofit, showing a project cost of $96,424, a simple project payback of 4 years, and a current cost to customer of 25% with a threshold of 50%.
Figure 23: Union Gas Targets & Performance Metric[s](#page-37-0) 4 Resource Acquisition Scorecard Large Volume Large Volume Large Volume - Revised Large Volume Overhead - Revised Evaluation - Revised Evaluation - Revised Large Volume Total...
AI summary The document presents a detailed budget and performance metrics table for Union Gas, including various program costs, overheads, and inflation adjustments. It outlines different categories of expenses such as market transformation, administrative costs, and program-level overheads, along with their respective financial figures and sections referenced.
- 4. Net Levelized cost ($/kWh)1 = PV (costs all benefits except for electric energy benefits) / PV (energy savings) Benefits Costs Avoided electric energy costs Avoided electric capacity costs Avoided non-electric fuel costs Customer non-...
AI summary The document outlines the net levelized cost calculation for energy programs, highlighting benefits such as avoided electric energy and capacity costs, and non-electric fuel savings, while considering various costs including utility program costs, overhead, and customer expenses.
Please see Table below which details what factors are taken into account when examining each avoided cost component in California: Component Basis of Annual Forecast Basis of Hourly Shape Generation Energy Forward market prices and the $/k...
AI summary The table outlines factors considered in examining avoided cost components in California, including generation energy, capacity, ancillary services, T&D capacity, environment, and avoided RPS, with details on their annual forecast and hourly shape bases.
2013-2015 Total Portfolio $/kWh 2013 2014 2015 Gross Savings (kWh) 828,999,924 845,181,086 769,529,791 Spending $ 317,221,372 $ 365,056,021 $ 385,199,846 $/kWh $ 0.38 $ 0.43 $ 0.50 Excludes C&S,EM&V and On-Bill Financing expenses reported...
AI summary The table presents the 2013-2015 Total Portfolio \/kWh data, showing gross savings, spending, and \/kWh costs. It also includes PG&E's incentive-to-administrative spending ratios for the same period. The data is budgeted, not actual, and excludes certain expenses.
2013 2014 2015 2016 Incentive Costs $85,792,815 $87,475,385 $81,650,474 $90,618,627 Administration $68,482,871 $71,734,454 $72,025,504 $77,017,143 Incentive-to Administration Ratio 56:44 55:45 53:47 65:35 2015-2019 STRATEGIC PLAN 13
AI summary The table presents incentive costs and administration costs for the years 2013 to 2016, along with the ratio of incentive-to-administration costs. The 2015-2019 Strategic Plan is referenced as a key document in the context.
Costs The OPUC has defined that the following elements be considered when determining the costs from the societal perspective 15 (i.e., Total Resource Cost): - 1. Total cost of efficiency measures and actions 16 , including costs to the En...
AI summary The OPUC outlines the elements to consider when determining societal costs, including total efficiency measure costs, Energy Trust administrative and program management costs. It clarifies that utility system tests include only Energy Trust incentives and associated administrative costs, while excluding tax credits and certain program costs paid by federal or state agencies.
Benefits (Avoided Costs) In the societal test, the Energy Trust will include the following benefits: - 1. The value of the electrical and/or gas energy saved based on the avoided cost forecasts of the utilities whose customers are served b...
AI summary The Energy Trust includes benefits such as avoided energy costs, non-energy benefits, line losses, and natural gas capacity benefits in its societal test. These are based on forecasts from utilities and PUC approvals, with specific considerations for environmental and efficiency-related factors.
Avoided Supply Costs in TRC Calculation The benefits calculated in the TRC are the avoided supply costs. The avoided supply costs include the reduction in costs of electric energy, natural gas, generation and transmission, and distribution...
AI summary The TRC calculation considers avoided supply costs, which include reductions in electric energy, natural gas, generation, transmission, and distribution capacity costs, valued at marginal cost during periods of load reduction.
Inputs - Avoided Supply Costs (energy and capacity); - Local Avoided Supply Costs (energy and capacity); - Fixed Program Administration Costs; - Year of Implementation; - Measure Participation; - Variable Costs; - Annual Operating Costs (F...
AI summary The text lists various cost and efficiency-related factors and metrics used in energy programs, including avoided supply costs, program administration costs, energy savings, and financial parameters such as discount and inflation rates.
E1 Responses to Nova Scotia Energy Board (NSEB) Information Requests NON-CONFIDENTIAL Request IR-21: Evidence – Exhibit E-1, pp.1-71 (pdf pp. 8-78) - Pdf pg. 55 states that when E1 created its Preferred Plan, it took cost-efficiencies into...
AI summary EfficiencyOne (E1) responded to a request regarding cost-efficiencies in its 2027–2031 Preferred Plan. E1 reduced FTE staffing, spending on Enabling Strategies, and focused on cost-effective program delivery through measures such as streamlining workflows, enhancing digital delivery, and consolidating contracts. E1 did not pursue cost-efficiencies that would limit investment in IT and cybersecurity.
3.1.5 INCREMENTAL COST - Value: $382,537.50 (in $2025) - Unit: per GWh saved - Source: Refer to CUS_IND_001 - Details: The incremental cost for this measure is assumed to be consistent with CUS_IND_001.
AI summary The incremental cost for the measure is valued at $382,537.50 per GWh saved, based on the assumptions from CUS_IND_001, which is referenced as the source.
E1 Responses to Nova Scotia Energy Board (NSEB) Information Requests NON-CONFIDENTIAL 1 Request IR-45: 2 3 Appendix A - Preferred Plan pp. 1-112 (Attach. 1-5) 4 5 Exhibit E-1, Appendix A, page 108 of 112 (pdf pg. 196): 6 7 E1 discusses fur...
AI summary Nova Scotia Power (E1) responds to information requests from the Nova Scotia Energy Board (NSEB) regarding mid-course adjustments to demand-side management plans and cost assumptions in the General Rate Application. E1 references prior responses and states it is not aware of required updates to avoided costs.
E1 Responses to Nova Scotia Energy Board (NSEB) Information Requests NON-CONFIDENTIAL 1 • Adjustments to true-up differences between NS Power collections and the amount 2 that was intended to be collected by rate class through the Program...
AI summary E1 responds to Nova Scotia Energy Board information requests regarding adjustments to true-up differences in collections and surplus from the implementation of the DSM Plan. The response notes that DSM-related costs are apportioned to rate classes based on the '25/75 rule', with 75% allocated to rate classes and 25% to the system.
E-16E1 (Synapse) RIRs 1-90
6 passages
Table 9: Scenario 1DR-Base – Round 1 Modelling Results TRC & PAC NS Cost Test Available Total Program Scenario 1DR-Base Investment1 Lifetime Lifetime Capacity2 Resource Cost Administrator NS Cost Test (2027-2031) ($ million) Benefits Benef...
AI summary Table 9 presents the results of the Scenario 1DR-Base – Round 1 Modelling, detailing various demand response and energy efficiency programs, their investments, benefits, and costs. The table includes data for residential demand response, smart thermostats, water heaters, battery control, EV charging control, and BNI programs, with total investments and cost test figures provided.
Table 12: Scenario 1Solar-PV-Base - Round 1 Modelling Results Scenario 1Solar-PV - Base (2027-2031) Investment ($ million) Lifetime TRC & PAC Benefits ($ million) NS Cost Test Lifetime Benefits ($ million) Estimated Generation (GWh) Lifeti...
AI summary Table 12 presents the results of the Solar-PV-Base scenario modeling for the years 2027-2031. It includes investment costs, benefits, generation estimates, and cost tests for residential and business programs. The data highlights the financial and operational impacts of solar photovoltaic initiatives.
Q2 2025 compared to Q2 2024 Q2 2025 net income decreased by $12 million compared to Q2 2024. The decrease is due to higher OM&G expenses, and higher depreciation and amortization due to increased PP&E in service. OM&G expenses increased du...
AI summary Q2 2025 net income decreased by $12 million compared to Q2 2024 due to higher OM&G expenses and depreciation and amortization. The request IR-21 asks for detailed data on lighting measures in the Instant Savings and Efficiency Product Installation program components, including number of measures, investment, energy savings, costs, and benefits, categorized by measure type and plan year.
f energy savings as a percentage of load at 0.8 percent and the recommendation of the energy savings split between residential and business programs. (b) Please refer to part (a) of this IR response. Request IR-23: Page 48 of the Evidence...
AI summary The text discusses EfficiencyOne's (E1) cost management strategies, including competitive procurement practices and multi-year procurement arrangements used in its 2027-2031 DSM Plan to achieve best value and reduce transaction costs. It also requests detailed information on contracts up for competitive procurement and existing and new multi-year procurement arrangements.
tion where BNI DR can provide value and where customers with curtailable load are within those areas. i) Please refer to part (d) of this IR response. ii) Please refer to part (d) of this IR response. Request IR-62: Please refer to Table 4...
AI summary The response explains that the lower PAC for 2028 is due to significantly lower avoided costs in 2028 compared to other years, particularly the avoided cost of generation capacity being less than half of the 2027 value. Avoided cost of capacity is the main factor influencing PAC results for demand response programs.
12 Process Timeframe filing of the Annual Progress Report and Evaluation Report. Additional meetings scheduled throughout the year as required. 1 Request IR-90: 2 3 Please refer to Appendix A - Attachment 4, Sheet 21 (Annual Cost Category)...
AI summary The document outlines a request for detailed information on demand response enrollments, program costs, and energy savings across various years and customer segments. It also asks for a description of cost categories and a breakdown of costs related to a cybersecurity incident.
E-23Evidence - Synapse
5 passages
- NSEB should direct E1 to pursue an amount of electrification in its Proposed Plan that does not increase electricity costs at the portfolio level. This could take the form of the strategic electrification resources that E1 included in it...
AI summary The NSEB provides guidance to E1 on electrification strategies, demand response program improvements, and budget adjustments. It emphasizes cost control, performance evaluation, and the need for mid-cycle adjustments if program budgets change significantly.
$ / kW Capacity 2026 2027 % Change Benefits per kW 363 507 39% Costs per kW 1,283 563 -56% BCR 2026 2027 PAC 0.28 0.90 Source: Synapse Analysis of: 2026 Extension filing, Appendix A, Attachment 4, pg. 4, 19c; E1, 2027-2031 Plan, Appendix A...
AI summary The table compares benefits and costs per kW for capacity in 2026 and 2027, showing a significant increase in benefits and a decrease in costs, resulting in a higher BCR and PAC in 2027. The data is sourced from Synapse Analysis and filings by E1.
Q. In which budget categories does E1 plan to realize cost savings per kW of capacity? A. E1 plans to cut residential thermostat and water heater demand response budgets per kW of capacity across all budget categories. As shown in [Table 1...
AI summary E1 plans to reduce residential thermostat and water heater demand response budgets per kW of capacity across all budget categories, with the majority of cost savings coming from reductions in technology enablement costs.
Q. What is E1's approach to managing program delivery costs? A. On the overall DSM plan, E1 states that it has "heard some concerns from stakeholders that program delivery costs have increased unreasonably since the last plan. However, E1...
AI summary E1 explains that program delivery costs have increased due to factors like reduced government funding and market changes, but claims it has taken steps to manage and contain costs. Customer incentives make up 71% of the Preferred Plan's costs, and E1 plans to use benchmarking, competitive procurement, and third-party audits to improve cost-effectiveness.
1 2 Q. Does E1 address the high program delivery costs for the residential demand response program specifically? 3 A. No. E1 does not address the high delivery costs of the residential demand 4 response program specifically. According to t...
AI summary E1 does not specifically address the high delivery costs of the residential demand response program. The response notes that while E1 reviewed DR incentives and program delivery costs, it did not evaluate delivery costs for demand response programs. E1's spending on incentives is much lower compared to similar programs in other regions, with a significant portion allocated to program delivery. Recommendations include conducting a process evaluation and reviewing the competitive procurement process for delivery services.
E-41Rebuttal Evidence - E1
7 passages
2.2.2 RESIDENTIAL DEMAND RESPONSE DELIVERY COSTS Second, Ms. Napoleon makes recommendations regarding residential demand response costs. At page 6, lines 7 – 13, Ms. Napoleon recommends: Regarding residential demand response, E1 should see...
AI summary Ms. Napoleon recommends that E1 reduce residential demand response costs per kW by enrolling new participants in low-cost pathways, conduct a process evaluation of the program's delivery, and review its competitive procurement process for residential demand response services.
Q. How do E1's Residential program delivery costs compare to other jurisdictions? A. E1's proposed residential demand response delivery costs as a share of total budgets appear substantially higher than similar programs in other jurisdicti...
AI summary E1's proposed residential demand response delivery costs are significantly higher compared to similar programs in Rhode Island Energy and National Grid (Massachusetts), raising concerns about cost-effectiveness and the reasonableness of the proposed budget.
E1 Rebuttal Evidence E1 acknowledges that the delivery-cost share of its residential demand response budget is higher than that of the Rhode Island Energy and National Grid (Massachusetts) programs cited by Ms. Napoleon, but submits that t...
AI summary E1 argues that comparing its residential demand response budget to programs in Rhode Island and Massachusetts is not valid due to differences in program maturity, market conditions, and delivery models. E1 highlights that its program is at an earlier stage and that cost categorization differs between programs, making a direct comparison inappropriate.
At PDF page 17, Brattle states: First, current PAC test results assumes that program costs are appropriate, but residential DR program costs are much higher compared to DR programs from other utilities, shown in Figure 3. These high costs...
AI summary Brattle highlights that E1's residential demand response (DR) programs have significantly higher costs compared to other utilities and E1's own BNI programs. The high costs are attributed to the use of smaller customer-side devices, which increase delivery costs. Brattle suggests that E1 could reduce costs by learning from other utilities and improving program administration.
E1 Rebuttal Evidence With respect to Brattle's observation that residential Demand Response program costs are high relative to other utilities and to E1's own BNI programs, E1 notes that Brattle acknowledges the structural reason for the d...
AI summary E1 responds to Brattle's observation that residential Demand Response (DR) program costs are higher compared to other utilities and E1's BNI programs. E1 explains that the higher costs are due to the program's delivery through many small customer-side devices and its early development stage. E1 acknowledges the need to improve costs but argues that current costs are not imprudent and that efforts are underway to enhance cost-effectiveness before scaling.
Q. Has Apex observed rising costs in other mature jurisdictions? A. Yes. As shown in E1's response to IG IR-10, Attachment 2, Massachusetts, which has long standing programs with robust budgets, removed its behavioral and lighting programs...
AI summary Apex has observed rising costs in mature jurisdictions, citing examples from Massachusetts and Efficiency Maine. Program administration and marketing costs have increased significantly over time, reflecting market realities rather than inefficiencies. These trends are influenced by program maturity, equity priorities, and global economics.
Q. What other market and program forces help explain E1's rising unit costs? A. Measurement & Verification updates and net savings adjustments have a significant impact on claimable savings. As programs mature, evaluations often reduce net...
AI summary E1's rising unit costs are influenced by factors such as measurement and verification updates, net savings adjustments, market transformation, and increased program delivery costs. As programs mature, savings claims decrease, and more complex and expensive opportunities arise, leading to higher spending on customer incentives and program delivery.
102579Letter NSPI re: requests that its third-party experts, Sanem Sergici and/or Sai Shetty of The Brattle Group, participate virtually
4 passages
l to assess the prudence of an electric utility's power procurement strategy in comparison to several other alternative options. As a result of this model, she assessed whether it is prudent to recover the congestion and loss costs associa...
AI summary The text outlines work related to assessing the prudence of power procurement strategies, marginal cost studies, and integrated resource planning for electric utilities. It discusses evaluating congestion and loss costs, incremental costs of serving demand, and designing future scenarios based on external factors such as fuel prices and environmental regulations.
SENIOR ENERGY ASSOCIATE Chicago +1.872.302.6115 [email protected] Mr. Shetty has worked with electric utilities on issues related to regulatory retail ratemaking, rate design, load forecasting, utility program screening and transmissi...
AI summary Sai Shetty is a Senior Energy Associate with experience in regulatory retail ratemaking, rate design, load forecasting, and utility program screening. He has worked on modernizing electric rate design and conducting embedded and marginal cost of service studies. His work also includes performance-based regulation, benefit-cost analysis for DERs and DSM, and analysis of the Value of Lost Load and Net Energy Metering.
er's self-generation profiles against utility-owned generation and understanding marginal costs incurred by the utility to serve an additional customer. - Rate Modernization for Interstate Power and Light (IPL). For IPL in Iowa, Mr. Shetty...
AI summary The text outlines Sai P. Shetty's consulting experience with various utilities, including work on rate modernization for IPL and innovative rate pilots for EPE. It highlights activities such as embedded cost of service studies, marginal cost of service studies, and the design of new rate structures.
EXPERT EVIDENCE AND REGULATORY FILINGS - Before the New Brunswick Energy and Utilities Board, "Review of NB Power Cost Allocation Methods for Production Plant", report filed on behalf of New Brunswick Power, Matter EL-002-2026, May 2026 (w...
AI summary The text lists various regulatory filings and expert evidence reports submitted by utility companies and organizations across different jurisdictions, including New Brunswick, Texas, New Mexico, Maryland, and Quebec. These reports cover topics such as cost allocation methods, time-varying rate pilots, and performance incentive mechanisms.