Contingency Statement Contingency for this project has been determined using a combination of internal subject matter expert judgment (professional engineers and field personnel) based on previous line replacement and upgrade experience an...
AI summary The project's contingency is set at 15% based on internal expertise and nonbinding guidelines, classified as Class 3. Risks include overtime due to shortened outages, material cost increases, remote access challenges, and unexpected asset replacements.
Execution Year: 2026-2027 Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour T&D Labour - Site Supervision Design - Engineering PD PD 60 220 $ $ 461 452 $ $ 27,79...
AI summary The document outlines a cost estimate for a project spanning 2026-2027, including labor, materials, contracts, and overhead costs. It breaks down expenses into categories such as regular labor, materials, contracts, and administrative overhead, with a total estimated cost of $3,603,351.