Topic:"Cost Considerations" in M12842

Matter: Nova Scotia Power Inc. - CI C0083591 – IR746 Petpeswick Community Solar - $0 (U&U)2026 Q1 Capital Reports
2 passages 2 documents

Cost Considerations across all matters →

N-1CI C0083591 – IR746 Petpeswick Community Solar - $0 - Redacted 1 passage
Execution Year: 2026-2027 p. p. 2
Execution Year: 2026-2027 Cost Support Completed Similar Description Unit Quantity Unit Estimate Total Estimate Reference Projects (FP#'s) Regular Labour Electrician PD 750 $ 403 $ 302,461 Engineering PD 51 $ 452 $ 22,844 Sub-Total $ 325,3...

AI summary The document outlines a cost breakdown for a project with execution years 2026-2027, including labor, travel, materials, and overhead costs. It provides estimates for various components such as electrician labor, engineering, travel expenses, and materials like metering racks and communication modems. The table also includes capital contributions and administrative overhead.

N-2NSPI (NSEB) RIR 1 to 7 - Redacted 1 passage
16 p. p. 8
16 Provision PDF Page # Article 5. Cost Responsibility, Milestones, Billing and Payment: Section 5.1.1 Cost Estimates 20 Article 5. Cost Responsibility, Milestones, Billing and Payment: Section 5.1.2 Interconnection Facilities 20 Article 5...

AI summary The text outlines sections of Article 5, focusing on cost responsibility, milestones, billing, and payment, specifically addressing cost estimates, interconnection facilities, and distribution upgrades. These sections are referenced on page 20 of the PDF.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →