Matter: Nova Scotia Power Inc. CI C0044172 – L7005 Canso Crossing Vibration Mitigation - $2,431,095 (P&A)2026 Q1 Capital Reports
6 passages 3 documents

Cost Considerations across all matters →

N-1CI C0044172 – L7005 Canso Crossing Vibration Mitigation - $2,431,095 - Redacted 4 passages
Why do this project this way? p. p. 8
Why do this project this way? Installation of the new dampening system provides a long-term solution to conductor vibration compared with further interventions using the originally installed dampening system which is now at end-of-life. In...

AI summary Installing a new dampening system is more cost-effective than replacing the entire conductor section, which would cost around $2.5 million, and offers a long-term solution to vibration issues.

Contingency Statement p. p. 8
Contingency Statement This project is complete; as such, no contingency has been included in the detailed cost estimate.

AI summary The project is declared complete, resulting in no contingency being included in the detailed cost estimate provided.

Execution Year: 2023-2025 p. p. 8
Execution Year: 2023-2025 Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour Engineering - Design PD 49 $ 452 $ 21,979 Project Management PD 52 $ 452 $ 23,591 Tec...

AI summary The document presents a detailed cost estimate for a project spanning 2023-2025, including labor, materials, and other expenses. It outlines various categories of costs, such as regular and term labor, overtime, materials, and contracts, with specific dollar amounts and quantities. The total estimated cost, including administrative overhead and capitalized interest, is provided.

Document No: XXX-XX-XXXX-XXXX p. p. 8
Document No: XXX-XX-XXXX-XXXX Required fields: Started or Preliminary Defined or Complete Defined (D) Defined (D) Defined (D) Defined (D) Defined (D) Defined (D) Defined (D) Defined (D) Defined (D) Defined (D) Defined (D) Defined (D) Defin...

AI summary The document contains a table outlining a Project Cost Estimate Input Checklist and Maturity Matrix with various classifications and requirements. It includes fields such as 'Required fields', 'Estimate Classification', and 'Class' with percentages and statuses like 'Defined (D)', 'Not Applicable (NA)', and 'Complete (C)'.

N-2CI C0044172 REFILE - Redacted 1 passage
Execution Year: 2023-2025 p. p. 7
Execution Year: 2023-2025 Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour Engineering - Design PD 49 $ 452 $ 21,979 Project Management PD 52 $ 452 $ 23,591 Tec...

AI summary The document presents a detailed cost estimate for a project spanning 2023-2025, including labor, materials, contracts, and overhead costs. It outlines various categories such as regular and term labor, overtime, travel, meals, materials, and capitalization of interest, with a total estimate of $2,431,095 when including administrative overhead and AFUDC.

102450Letter NSPI re: Confidentiality 1 passage
Commercial Sensitivity p. p. 0
Commercial Sensitivity Consistent with the May 4, 2026 filing, certain information within Attachment 1 reflects internal analyses, cost considerations, and project-specific approaches that are commercially sensitive to NS Power. Disclosure...

AI summary NS Power has marked certain information in Attachment 1 as commercially sensitive, indicating that disclosure could harm its competitive position in future procurement processes or negotiations. This aligns with a prior filing from May 4, 2026.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →