Topic/Matter Intersection

Topic:"Cost Considerations" in M12870

Matter: Wasoqonatl Transmission Incorporated (WTI) – Q1 2026 Independent Engineer Reporting: NS-NB Reliability Intertie Tie Project
1 passage 1 document

Cost Considerations across all matters →

W-1Report - Redacted 1 passage
4.8 DISALLOWED COSTS p. p. 11
4.8 DISALLOWED COSTS BTY is not aware of any disallowed costs as of the date of issuance of this report. 127 John Street, Toronto, ON, M5V 2E2 416 596 9339 This Report has been prepared at the request of The Project Lenders on behalf of Wa...

AI summary BTY Consultancy Group Inc. states it is not aware of any disallowed costs as of the report's issuance date. The report, prepared for The Project Lenders on behalf of Wasoqonatl Transmission Incorporated, is confidential and proprietary.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →