CI C0052654 IR-7 Attachment 1 Page 1 of 1 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Cost Element ACE ATO Variance Variance Explanation Steel Towers 113,880 990,177 876,297 Original estimate for foundations was underestimated as NS Power...
AI summary The document presents a cost comparison between the ACE and ATO projects, highlighting significant variances due to underestimated initial costs, increased labor and contract expenses, and the need for additional contingency planning. The request also asks for project numbers, cost comparisons, and explanations of cost allocation and project impacts.
NON-CONFIDENTIAL 1 (iii) Total savings anticipated for NS Power are approximately $700K for the L-5541 2 Crossing ($1.6M – ($1.8M / 2)). 3 4 In summary: 5 Relevant Scope ( civil, steel towers supply, installation, and framing) Forecast Cos...
AI summary The document outlines potential cost savings for the L-5541 project, estimating $700K from shared infrastructure with the L-6554 project. Both projects share costs for civil work and steel structures over the Mersey River, with remaining costs assigned individually. The wind farm project's schedule is not expected to impact this project's execution.