Topic:"Cost Considerations" in M12960

Matter: Nova Scotia Power Inc. - CI C0052654 – L5541 Water Crossing Upgrades - $2,265,295 (ATO)
3 passages 2 documents

Cost Considerations across all matters →

N-2NSPI (NSEB) RIR 1 to 10 - Redacted 2 passages
CI C0052654 IR-7 Attachment 1 Page 1 of 1 REDACTED (CONFIDENTIAL INFORMATION REMOVED)
CI C0052654 IR-7 Attachment 1 Page 1 of 1 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Cost Element ACE ATO Variance Variance Explanation Steel Towers 113,880 990,177 876,297 Original estimate for foundations was underestimated as NS Power...

AI summary The document presents a cost comparison between the ACE and ATO projects, highlighting significant variances due to underestimated initial costs, increased labor and contract expenses, and the need for additional contingency planning. The request also asks for project numbers, cost comparisons, and explanations of cost allocation and project impacts.

NON-CONFIDENTIAL
NON-CONFIDENTIAL 1 (iii) Total savings anticipated for NS Power are approximately $700K for the L-5541 2 Crossing ($1.6M – ($1.8M / 2)). 3 4 In summary: 5 Relevant Scope ( civil, steel towers supply, installation, and framing) Forecast Cos...

AI summary The document outlines potential cost savings for the L-5541 project, estimating $700K from shared infrastructure with the L-6554 project. Both projects share costs for civil work and steel structures over the Mersey River, with remaining costs assigned individually. The wind farm project's schedule is not expected to impact this project's execution.

103491NSEB (NSPI) IR-1 to IR-10 1 passage
Request IR-8:
Request IR-8: - a) Please provide the project number for the Mersey Wind Interconnection project. - b) Please provide a cost comparison showing: - a. The forecast cost of separate L-5541 and L-6554 crossings; - b. The total cost of the sha...

AI summary Request IR-8 seeks information on the Mersey Wind Interconnection project, including its project number, cost comparisons between separate and shared crossing designs, potential impacts of delays or additional costs, and how costs will be allocated.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →