Please refer to the variance sheet for more information. C0061550 - L5031 Replacements and Upgrades - Hubbards to East Chester - ATO Term Labour-Overtime - 873 873 Travel Expense - 5,981 5,981 Travel required for field supervisors not capt...
AI summary The document outlines cost variances for a project involving replacements and upgrades from Hubbards to East Chester. Key increases include materials, contracts, and rock-breaking costs due to granite in the Chester area, as well as additional labor and travel expenses not captured in the original estimate.