M-4TOMB (NSEB) RIR 22 to 33
5 passages
2. Please identify the cost to provide the underground service. $130,546. II. Please identify the estimated costs to provide the Civic Number with overhead service. Overhead service was not practical for these three locations, per the abov...
AI summary The document requests the identification of costs for providing underground service, noting a cost of $130,546. It also asks about overhead service costs for specific locations, stating overhead service is not practical. The Utility intends to pay the full cost for overhead service, while the Civic Number owner would cover incremental costs for underground service.
Request IR-24: Regarding the response to IR-3: The IR asked the Utility to provide a breakdown of the project cost to include: Utility related project administrative and overheard costs; Land purchase costs; and Net HST.
AI summary The document requests a detailed breakdown of project costs, including administrative and overhead costs, land purchase costs, and Net HST, as part of the response to IR-3.
- i. Please explain in detail why this work was required. See above. - ii. Please identify the amount included in the cost of this change order that is associated with the "Original Park Area Scope". - The revised scope was priced at $97,9...
AI summary The document discusses a change order for a project involving electrical work in a park area, including the cost breakdown and justification for the change. It also covers another change order related to a padmount transformer installation, explaining the scope of work and the reasons for the adjustment.
to remove the scope of work from the overall construction contract to tender separately without other complications. - iv. Please provide a copy of the signed and approved Change Order 18. Uploaded. - c) As it relates to the costs associat...
AI summary The Town of Edgewater procured the Clearland Road Scope via a Change Order due to funding eligibility concerns. The Utility justified unit costs based on market rates, and Council approved the Change Order after project engineers' recommendations, citing the difficulty of separating the scope for re-tendering.
neers, understanding that costs were reflective of market and it would be difficult to remove the scope of work from the overall construction contract to tender separately without other complications. The unit rates were expected to differ...
AI summary The document discusses the completion of the Clearland Road project, the rationale for underground electrical infrastructure installation, and the inclusion of a 15% contingency in the project's cost estimate. It also addresses differences in unit rates between Clearland Road and Edgewater Street due to differing scope of work descriptions.
103779NSEB (TOMB) IR 22 to 33
3 passages
Request IR-24: - Regarding the response to IR-3: The IR asked the Utility to provide a breakdown of the project - cost to include: Utility related project administrative and overheard costs; Land purchase costs; - and Net HST. - a) Please...
AI summary Request IR-24 seeks clarification on why the Utility excluded administrative and overhead costs, land purchase costs, and Net HST from its project cost estimate, and requests a revised estimate with these items included as separate line items.
Request IR-25: - Regarding the project cost estimate provided in response to IR-3: - a) Please describe the scope of work associated with Change Order 12 Park Area Distribution. - i. Please explain in detail why this work was required. - i...
AI summary Request IR-25 seeks detailed explanations and documentation regarding several change orders and the Clearland Road scope of work, including the rationale for changes, cost determinations, and the decision to install underground electrical infrastructure.
Request IR-33: - Regarding the response to IR-20: please confirm that the estimated 5.56% increase in rates resulting from the current project included the impact of the project related deprecation costs, debt servicing costs and increment...
AI summary The text requests confirmation of whether the estimated 5.56% rate increase includes depreciation, debt servicing, and incremental O&M costs from the current project, and if not, asks for the estimated impact of including these costs.