Topic/Matter Intersection

Topic:"Cost Considerations" in M13050

Matter: Town of Mahone Bay Electric Utility - Edgewater Project $2,650,000
15 passages 7 documents

Cost Considerations across all matters →

M-2ToMB (NSEB) RIRs 1-21 2 passages
Request IR-4:
Request IR-4: Please identify the project cost premium to install the proposed electrical infrastructure underground rather than overhead. Our estimate is that the electrical infrastructure would cost 35-50% more as a result of underground...

AI summary The document estimates that installing electrical infrastructure underground would cost 35-50% more than overhead installation. This premium is lower than typical due to shared excavation work with the Town and existing transmission lines that would have increased costs if overhead installation was chosen.

Request IR-19:
Request IR-19: The application states, "Assessed against future customer growth in the impacted area, the cost of the infrastructure improvement is reasonable". Explain and provide a copy of the assessment carried out by the Utility to mak...

AI summary The application claims the cost of infrastructure improvement is reasonable based on future customer growth. However, no documentation was prepared to support this assessment, and the Utility relied on assumptions about average customer demand and projected housing development.

M-2-(v)2024-25 Electrical Utility Statements 1 passage
Allocation of Town Costs to Electric Utility Funds
Allocation of Town Costs to Electric Utility Funds Where identifiable, costs incurred by the Town of Mahone Bay (the "Town") on behalf of the Utility are charged to the Utility. The salaries of Public Works staff is allocated in proportion...

AI summary The Town of Mahone Bay allocates certain costs to the Electric Utility, including Public Works staff salaries and portions of administrative expenses, based on the time spent working for the Utility.

M-2-(vi)2025-26 Electrical Utility Statements (Draft) 1 passage
Revenue and Expenditure
Revenue and Expenditure Revenue and expenditure items are recorded on an accrual basis. Electricity sales and street lighting revenues are recognized in the period in which the transactions or events that give rise to the revenues occur. C...

AI summary The document outlines the accrual basis of accounting for revenue and expenditure items, with specific rules for recognizing electricity sales, street lighting revenue, and cash-based revenue sources. It also discusses the allocation of Town of Mahone Bay costs to the Utility, including staff salaries and administrative expenses.

M-4TOMB (NSEB) RIR 22 to 33 5 passages
2. Please identify the cost to provide the underground service. $130,546.
2. Please identify the cost to provide the underground service. $130,546. II. Please identify the estimated costs to provide the Civic Number with overhead service. Overhead service was not practical for these three locations, per the abov...

AI summary The document requests the identification of costs for providing underground service, noting a cost of $130,546. It also asks about overhead service costs for specific locations, stating overhead service is not practical. The Utility intends to pay the full cost for overhead service, while the Civic Number owner would cover incremental costs for underground service.

Request IR-24:
Request IR-24: Regarding the response to IR-3: The IR asked the Utility to provide a breakdown of the project cost to include: Utility related project administrative and overheard costs; Land purchase costs; and Net HST.

AI summary The document requests a detailed breakdown of project costs, including administrative and overhead costs, land purchase costs, and Net HST, as part of the response to IR-3.

Section 7
- i. Please explain in detail why this work was required. See above. - ii. Please identify the amount included in the cost of this change order that is associated with the "Original Park Area Scope". - The revised scope was priced at $97,9...

AI summary The document discusses a change order for a project involving electrical work in a park area, including the cost breakdown and justification for the change. It also covers another change order related to a padmount transformer installation, explaining the scope of work and the reasons for the adjustment.

Section 9
to remove the scope of work from the overall construction contract to tender separately without other complications. - iv. Please provide a copy of the signed and approved Change Order 18. Uploaded. - c) As it relates to the costs associat...

AI summary The Town of Edgewater procured the Clearland Road Scope via a Change Order due to funding eligibility concerns. The Utility justified unit costs based on market rates, and Council approved the Change Order after project engineers' recommendations, citing the difficulty of separating the scope for re-tendering.

Section 10
neers, understanding that costs were reflective of market and it would be difficult to remove the scope of work from the overall construction contract to tender separately without other complications. The unit rates were expected to differ...

AI summary The document discusses the completion of the Clearland Road project, the rationale for underground electrical infrastructure installation, and the inclusion of a 15% contingency in the project's cost estimate. It also addresses differences in unit rates between Clearland Road and Edgewater Street due to differing scope of work descriptions.

103418NSEB (ToMB) IR-1 to IR-21 1 passage
Request IR-3:
Request IR-3: - Please provide a detailed construction cost estimate for the project to include the following costs: - a) Electrical distribution infrastructure supply and installation; - b) Electrical service connections supply and instal...

AI summary Request IR-3 asks for a detailed construction cost estimate for a project, including electrical infrastructure, reinstatement, engineering services, administrative costs, land purchase, contingency, and HST. The request lists specific cost categories that need to be broken down and provided.

103779NSEB (TOMB) IR 22 to 33 3 passages
Request IR-24:
Request IR-24: - Regarding the response to IR-3: The IR asked the Utility to provide a breakdown of the project - cost to include: Utility related project administrative and overheard costs; Land purchase costs; - and Net HST. - a) Please...

AI summary Request IR-24 seeks clarification on why the Utility excluded administrative and overhead costs, land purchase costs, and Net HST from its project cost estimate, and requests a revised estimate with these items included as separate line items.

Request IR-25:
Request IR-25: - Regarding the project cost estimate provided in response to IR-3: - a) Please describe the scope of work associated with Change Order 12 Park Area Distribution. - i. Please explain in detail why this work was required. - i...

AI summary Request IR-25 seeks detailed explanations and documentation regarding several change orders and the Clearland Road scope of work, including the rationale for changes, cost determinations, and the decision to install underground electrical infrastructure.

Request IR-33:
Request IR-33: - Regarding the response to IR-20: please confirm that the estimated 5.56% increase in rates resulting from the current project included the impact of the project related deprecation costs, debt servicing costs and increment...

AI summary The text requests confirmation of whether the estimated 5.56% rate increase includes depreciation, debt servicing, and incremental O&M costs from the current project, and if not, asks for the estimated impact of including these costs.

104062NSEB (TOMB) IR 34 to 37 2 passages
Request IR-36:
Request IR-36: Reference Exhibit M-2 ii Cost Estimate which contains the CBCL cost estimate. For the most part, Board staff notes that quantities noted in the estimate are the same as the quantity estimates from the December 20, 2024 tende...

AI summary The document requests confirmation that the line item quantities in the CBCL cost estimate match the final measured unit quantities for which the contractor was paid, and if confirmed, a copy of the final progress claim and certificate. If not confirmed, a revised project cost estimate is requested.

Request IR-37:
Request IR-37: IR-25c)ii. asked the Utility to explain specifically how the Utility determined that the unit costs for the Clearland Road scope associated work are appropriate, particularly given the unit costs for the same items for the E...

AI summary The document requests the Utility to explain how unit rates for the Clearland Road electrical scope were determined, noting that they are significantly higher than those on Edgewater Road. It also asks for examples of tender pricing from similar projects to confirm the reasonableness of the change order price.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →