Matter: Nova Scotia Power Inc. - CI C0085185 – 4S-332 George St Rebuild and Reconfiguration - $0 (U&U)
1 passage 1 document

Cost Considerations across all matters →

N-1CI C0085185 4S-332 George St Rebuild and Reconfiguration U&U - Application - Redacted 1 passage
8.1 Cost Estimates for Modifications p. p. 45
8.1 Cost Estimates for Modifications The preliminary cost estimates for the circuit upgrades associated with a secondary supply to CBRH are included in the tables below. Note that the full actual cost of these modifications will be the res...

AI summary The preliminary cost estimates for circuit upgrades to provide a secondary supply to CBRH are outlined in the tables. The full actual cost of these modifications will be borne by the Cape Breton Regional Hospital.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →