N-1CI 49595 – HYD Tusket Unit 1 Overhaul - Application - Redacted
9 passages
This project is being submitted as a Class 3 estimate. The deliverables of this project indicate that 77% of the Class 3 deliverables have been completed. A 20% contingency has been selected to account for specific risks, including water m...
AI summary The project is submitted as a Class 3 estimate with 77% of deliverables completed. A 20% contingency is included to address risks such as water management during unit isolation and potential refurbishments needed after disassembly.
The budgetary pricing below has been included for further consideration. Costs and associated schedule impacts are subject to adjustment upon evaluation at the time of request. PRELIMINARY ENGINEERING (NOT INCLUDED IN TOTAL CONTRACT PRICE)...
AI summary The text includes preliminary engineering and equipment supply items with associated costs and schedule impacts that may be subject to adjustment. These items are not included in the total contract price and are presented for further consideration.
5.1 EQUIPMENT TRANSPORTATION Costs for each equipment shipment between Norcan's manufacturing facility and the Site Address has been included. Any changes to the equipment transportation resulting in cost adjustments to be identified throu...
AI summary The text outlines the inclusion of equipment transportation costs between Norcan's facility and the Site Address, with adjustments to be handled via Change Orders. It excludes costs related to equipment loading/unloading and specialty lifting devices unless otherwise specified.
5.2 TECHNICAL SUPPORT - EQUIPMENT DISASSEMBLY Costs to provide technical support surrounding the equipment disassembly at the Site Address has not been included. Any changes to the scope of work resulting in cost adjustments to be identifi...
AI summary The text notes that costs for technical support related to equipment disassembly at the Site Address were not included in the initial scope. Any changes leading to cost adjustments must be addressed through a Change Order form and reflected in the final milestone payment invoice.
5.3 TECHNICAL SUPPORT - EQUIPMENT INSTALLATION Costs to provide technical support surrounding the equipment installation at the Site Address has not been included. Any changes to the scope of work resulting in cost adjustments to be identi...
AI summary The text discusses the exclusion of technical support costs for equipment installation at the Site Address, noting that any changes in scope will be handled via Change Order forms and that Norcan is responsible for providing inspection forms for the Customer to complete and return.
5.4 TECHNICAL SUPPORT - UNIT COMMISSIONING UNIT PERFORMANCE TESTING Costs to provide technical support surrounding the unit commissioning at the Site Address has not been included. Any changes to the scope of work resulting in cost adjustm...
AI summary The document discusses the exclusion of costs related to technical support during unit commissioning at the Site Address, noting that any changes to the scope of work will be addressed through a Change Order form and reflected in the final milestone payment invoice.
Item Qty Description Schedule Price (USD) 1 Lot Field Service – Three Woodward Gateshaft Governors - Estimate Including: • One Weekend Day Travel to Site • Five Weekdays on Site • One Weekend Day on Site • One Weekend Day Travel from Site...
AI summary The document outlines cost estimates for field service, parts kits, and labor market impact assessments related to overhauling Woodward Gateshaft Governors. The estimates include travel, lodging, and parts costs, with potential variations based on the condition of the equipment and government requirements.
5. OPINION OF PROBABLE CONSTRUCTION COSTS Harbourside has developed an opinion of probable construction costs (Appendix B) assuming a 4 person crew completing the work. Harbourside has assumed the selected contractor has confined space res...
AI summary Harbourside provides an opinion of probable construction costs for a project involving concrete work, confined space equipment, and site access challenges. The estimate includes labor, materials, and site-specific factors such as remoteness and access restrictions.
REDACTED CI 49595 Attachment 6 Page 5 of 22 REDACTED (CONFIDENTIAL INFORMATION REMOVED) File No: 251166 Harbourside has completed this opinion of probable construction costs using preliminary quantities and schedule and has therefore consi...
AI summary Harbourside Engineering has provided an opinion of probable construction costs for a project, classifying it as a class C estimate with a 20% contingency. The total estimated cost is provided, excluding taxes, with a detailed breakdown in Appendix B. The document includes contact information for the engineers involved.