N-1Application - Redacted
18 passages
Figure 2: Cost of Energy Generation (Partially Confidential) $/MWh by Gen. Source 2027 AAR 2026 AAR Percentage Change (%) Solid Fuel Oil & Gas NB Imports ML Surplus 4
AI summary The document provides a table titled 'Cost of Energy Generation (Partially Confidential)', which outlines the projected costs per megawatt-hour ($/MWh) by generation source. The data compares the 2027 Anchor Anchor Rate (AAR) against the 2026 AAR, including percentage changes for sources such as Solid Fuel, Oil & Gas, NB Imports, and ML Surplus.
2.2 Board Directed Sensitivity Analyses 1415 In accordance with the Board's prior AAR directives, NS Power has considered the following sensitivities on the marginal cost: 1617 18 (1) Forward commodity market returns volatility of plus 1.5...
AI summary NS Power has conducted sensitivity analyses on marginal costs in response to the Board's Anchor Anchor Rate (AAR) directives. Specifically, the analysis evaluates the impact of forward commodity market returns volatility, applying a plus 1.5 standard deviation (+1.5 σ) scenario to various fuel prices, including AECO, AGT, HFO, API2, and Mass Hub (Off-Peak and 20 On-Peak). The analysis utilizes the 2027 PLEXOS AAR F&PP model, updated with system assumptions and commodity pricing as of September 17, 2026.
1 5.0 SHORE POWER TARIFF 2 - 3 Service under the SP Tariff is a seasonal priority interruptible service, differentiated by two voltage - 4 levels: transmission and primary distribution. It is available to seaports in Nova Scotia from April...
AI summary The document describes the Shore Power (SP) Tariff, a seasonal priority interruptible service available to Nova Scotia seaports from April 1 to November 30. The tariff is differentiated by transmission and primary distribution voltage levels. The proposed rates for 2027 reflect a decrease compared to 2026 rates, primarily driven by a reduction in the line-loss adjusted Fuel Cost component, which offsets an increase in the Fixed Cost Adder component.
17 Figure 10: Assumptions Underlying the 2027 Forecast DAS Tariff Administration Charge Item Value Number of metering points requiring administration/review 100 Estimated monthly administration effort 3 hours Resource cost $53.57/hour Admi...
AI summary This section presents the underlying assumptions and cost calculations for the 2027 forecast Distribution-connected Aggregation Service (DAS) Tariff Administration Charge. It details the resource requirements, including the number of metering points (100), the estimated monthly administration effort (3 hours), and specific hourly rates for resource costs ($53.57) and administrative overhead ($39.00), resulting in a total monthly charge of $277.71.
Optional Generation Load Following Average incremental cost of generation expressed in cents per kWh as determined by the generation forecast for the rate year plus add on charges as defined for back-up service. This price will be 6.754 ce...
AI summary The text specifies the average incremental cost for optional generation load following, set at 6.754 cents per kWh. This pricing is derived from the generation forecast for the rate year and includes additional charges associated with back-up service.
ENERGY CREDIT The Energy Credit is equal to the average incremental cost of generation as defined under Optional Generation Load Following.
AI summary The text defines the Energy Credit as a financial metric. It specifies that the value of the Energy Credit is determined by the average incremental cost of generation, specifically as defined under the Optional Generation Load Following framework.
REDACTED 2027 AAR Appendix A2 Page 1 of 1 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Marginal Cost ($/MWh) 2027 Peak Off-peak All periods Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year 62.54 REDACTED 2027 ARR Appendix A3 Page 1 of 1...
AI summary The document provides a marginal cost table for the year 2027, specifically listing the annual average marginal cost of $62.54 per MWh. The table is structured to show monthly breakdowns for peak, off-peak, and all periods, though specific monthly values are redacted or omitted in this excerpt.
Sensitivity 1: Prices Adjusted Upwards (+1.5 σ) System Marginal Cost ($/MWh) 2027 Peak Off-peak All periods Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year 73.67 REDACTED 2027 AAR Appendix A6 Page 2 of 5 REDACTED (CONFIDENTIAL INFORMA...
AI summary The document presents sensitivity analyses for the 2027 Annual Adjustment Rate (AAR) regarding system marginal costs. It details three specific scenarios: Sensitivity 1 (Prices Adjusted Upwards +1.5 σ) showing a yearly cost of $73.67/MWh, Sensitivity 2 (Prices Adjusted Downwards -1.5 σ) showing a yearly cost of $54.38/MWh, and Sensitivity 3 (Prices Half Surplus On Peak) showing a yearly cost of $64.86/MWh.
Sensitivity 4: Wind Delay 1 month System Marginal Cost ($/MWh) 2027 Peak Off-peak All periods Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year 71.29 REDACTED 2027 AAR Appendix A6 Page 5 of 5 REDACTED (CONFIDENTIAL INFORMATION REMOVED)
AI summary The document presents a sensitivity analysis regarding a one-month delay in wind energy availability. It provides a table of system marginal costs ($/MWh) for the year 2027, broken down by month and period (Peak, Off-peak, and All periods). The average system marginal cost for all periods in 2027 under this sensitivity scenario is $71.29/MWh.
ENERGY CHARGE NSPI's actual hourly marginal energy costs, plus the following fixed cost adders for on-peak and offpeak usage: On-peak (7:00 am – 11:00 pm, non-holiday weekdays): 6.156¢/kWh Off-peak (11:00 pm – 7:00am, non-holiday weekdays)...
AI summary The text outlines the structure of the energy charge, which is based on NSPI's actual hourly marginal energy costs supplemented by specific fixed cost adders. On-peak usage (7:00 am – 11:00 pm on non-holiday weekdays) incurs an adder of 6.156¢/kWh, while off-peak usage incurs 0.918¢/kWh. Weekend and holiday hours are charged at the off-peak rate. Additionally, a credit of 32 cents per peak kilovolt-ampere is provided for customer-owned transformers. These adders are subject to annual development based on budgeted costs and require Nova Scotia Energy Board approval.
Power Factor Constant Power Factor Constant 90-100% 1.0000 65-70% 1.1255 80-90% 1.0230 60-65% 1.1785 75-80% 1.0500 55-60% 1.2455 70-75% 1.0835 50-55% 1.3335 (8) The Company reserves the right to have a separate service agreement, if in the...
AI summary The document provides a technical table defining constant factors associated with different power factor ranges, likely for use in rate calculations or system costs. Additionally, it includes a provision allowing the Company to enter into separate service agreements to address specific issues not covered in the main document for the benefit of both the Company and its customers.
COST BREADOWN BY FUNCTIONAL AREA Source: 2027 COSS with GRA application Filing EXHIBIT 6.1
AI summary The provided text is a heading and source citation for Exhibit 6.1 of the 2027 COSS with GRA application filing. It indicates that the subsequent section will contain a breakdown of costs organized by functional area. No specific arguments, entities, or data points are provided in this excerpt beyond the structural categorization of costs.
FOR THE YEAR ENDING DECEMBER 31, 2027 (1) MWH SALES (2) ENERGY LINE (3) ENERGY LOSSES REQUIREMENT (4) CLASS NON- DMD. (KW) (5) SYSTEM COINCIDENT COINCIDENT COINCIDENT FACTOR (6) SYSTEM DMD. (KW) (7) LINE (8) DEMAND SYSTEM (9) SYSTEM COIN....
AI summary The document provides a detailed load disaggregation table for the year ending December 31, 2027, as part of the 2027 Annual Adjustment Rate (AAR) proceeding. It outlines MWh sales, energy line requirements, energy losses, and coincident peak factors across various customer classes, including Domestic, Small General, General, Large Industrial, and Municipal. It also provides specific breakdowns for transmission and distribution for customers over 2 MVA, including components for the Port Hawkesbury Paper (PHPCBL) facility and other industrial entities.
REDACTED 2027 AAR Appendix E3 Page 7 of 8 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Total bfr BUTU BTL Classes GRLF 1P - RTP PHP Shore Power EBS Total 68,697 78,835 77,204 60,627 53,036 66,581 56,252 57,015 57,570 63,740 64,166 70,486 21...
AI summary The document provides a detailed data table regarding the 2027 Annual Adjustment Rate (AAR) calculations. It specifically breaks down the 'Total bfr BUTU BTL Classes' for various categories, including Shore Power, EBS, and RTP PHP. The table includes specific load figures (NSR Peak) and calculates the Marginal Cost and Incremental Cost associated with these different classes to determine the total cost impacts for the period.
Backup Service The actual or estimated average time coincident incremental cost of generation including transmission losses for the period service is provided plus 0.500 cents per kWh for additional Operating and Maintenance costs, service...
AI summary The document defines the cost structure for the Backup Service. The rate is calculated based on the actual or estimated average time coincident incremental cost of generation, which includes transmission losses for the period service. Additionally, a fixed amount of 0.500 cents per kWh is added to cover Operating and Maintenance costs, service charges, and Administration & General compensation.
Optional Generation Load Following Average incremental cost of generation expressed in cents per kWh as determined by the generation forecast for the rate year plus add on charges as defined for back-up service. This price will be 7.2366.7...
AI summary The document specifies the average incremental cost of generation for optional load following. This cost is calculated based on the generation forecast for the rate year, including additional charges for backup service. The determined price is set at 7.2366.754 cents per kWh.
ENERGY CREDIT The Energy Credit is equal to the average incremental cost of generation as defined under Optional Generation Load Following.
AI summary The text defines the 'Energy Credit' as a specific financial metric. It establishes that the value of this credit is determined by the average incremental cost of generation, specifically as it is defined under the Optional Generation Load Following framework.
ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF Page 3 of 3 Power Factor Constant Power Factor Constant 90-100% 1.0000 65-70% 1.1255 80-90% 1.0230 60-65% 1.1785 75-80% 1.0500 55-60% 1.2455 70-75% 1.0835 50-55% 1.3335 - (8) The Compa...
AI summary This page of the One Part Distribution Voltage Real Time Pricing Tariff provides a technical table of constants associated with different power factor ranges. Additionally, it includes a provision allowing Nova Scotia Power Inc. to establish separate service agreements if specific issues not covered in the tariff need to be addressed for the benefit of the company and its customers.