HomeCost DeferralM03091Evidence
Topic/Matter Intersection

Topic:"Cost Deferral" in M03091

Matter: CI# 33942 - P-510 - NSPI WO - Coon Pond Pipeline Replacement - $2,075,549
1 passage 1 document

Cost Deferral across all matters →

N-1Redacted Work Order 4/30/2010 1 passage
33942-H555 30-Apr-10 p. p. 1
33942-H555 30-Apr-10 . I - Account Original Revision I Current Revision Variance 001 - Hydro Req. Labour 3,000 8,574 5,574 001 - Reqular Labour (No AO) - 85 85 011 - Travel Expense 75 200 125. 012 - Materials 375,000 013 - Power Prod Contr...

AI summary The document presents a comparison between original and current revisions of various account items, highlighting significant variances in costs such as labour, materials, consulting, and administrative overheads, with total costs increasing substantially from 629,936 to 2,075,549.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →