Matter: Nova Scotia Power Inc. - CI 49036 – HYD - Avon 2 Controls Upgrade - $1,073,463
1 passage 1 document

Cost Deferral across all matters →

N-1Application - CI 49036 - HYD Avon 2 Controls Upgrade - Redacted 1 passage
Preamble p. p. 8
This project is being filed as a AACE Class 3 estimate. The defined deliverables for this project indicate that 81% of Class 3 deliverables are completed. AACE recommends applying between 10% and 30% contingency to estimates in this class....

AI summary The project is filed as an AACE Class 3 estimate, with 81% of deliverables completed. A 20% contingency is applied to account for risks such as market volatility and potential refurbishment and overtime costs to ensure completion by Spring 2026.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →