Preamble
p. p. 5
This project is being filed as a AACE Class 3 estimate. The defined deliverables for this project indicate that 92% of Class 3 deliverables are completed. AACE recommends applying between 10% and 30% contingency to estimates in this class....
AI summary The project is classified as an AACE Class 3 estimate with 92% of deliverables completed. A 15% contingency was selected to account for risks, particularly related to undetermined concrete repair work after steel structure removal.