NON-CONFIDENTIAL 1 (c) Following several iterations exploring potential overhead routes for the QEII supply, it was 2 determined that an underground solution was required to bring the two required feeders to 3 the hospital expansion area....
AI summary The Company decided to implement an underground solution for the QEII supply due to the high growth area and lack of existing 3-phase infrastructure. A cost-share arrangement was determined to be in the best interest of customers, leading to significant savings. The infrastructure installed during Phase 1 includes additional ductwork to facilitate future expansion.