1 Request IR-2: p. p. 4
1 Request IR-2: 2 - 3 In response to IR 1(h), the utility provided a table breaking down the cost elements for Phase - 4 1 (L5017/L5046 tap) and Phase 2 (83V 504 switch). Please provide a breakdown of the - 5 internal and external labour t...

AI summary The utility is asked to provide a detailed breakdown of internal and external labour tasks, along with allocated hours and associated costs for Phase 1 and Phase 2. The utility responds by referring to a table that includes only internal labour costs, noting that external services are covered under contracts or consultant vendor costs.

101194Letter NSPI re: 2025 Q4 Capital Reports 1 passage
Section 1 p. p. 0
March 11, 2026 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: Fourth Quarter 2025 Capital Reports Dear Ms. Henwood: Capital Reports In this package are the 4th Quarter...

AI summary The Fourth Quarter 2025 Capital Reports detail capital expenditures, active projects, deferred/cancelled projects, and unapproved spending under the 2025 ACE Plan. Reports include compliance with the Board's 2009 ACE Plan Order and NS Power's 2016 ACE Plan commitments.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →