Section 5
ndard and provide the supporting source), or whether it is an 24 internal NSPI assumption (and, if so, provide the rationale and any 25 validation performed). 26 (d) Please confirm whether the reduction in tree-contact outages in 2025 is a...

AI summary The regulator requests NSPI to clarify assumptions about cost deferral, explain the reduction in tree-contact outages, and reconcile data discrepancies in the 2026 ACE Plan. Specific inquiries include whether outage reductions stem from weather improvements or reliability investments, and why outage events decreased but customer outage hours increased since 2020.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →