Matter: Nova Scotia Power Inc. - CI C0061552 – L6043 Replacements and Upgrades- $3,603,3512026 Q1 Capital Reports
1 passage 1 document

Cost Deferral across all matters →

N-1CI C0061552 – L6043 Replacements and Upgrades- $3,603,351 1 passage
Section 19 p. p. 5
This project is being filed as a Class 3 estimate. The defined deliverables for this project indicate that 70% of Class 3 deliverables are completed. A contingency value of 15% was selected to account for specific risks such as contractor...

AI summary The project is filed as a Class 3 estimate with 70% of deliverables completed. A 15% contingency was selected to account for known risks and unforeseen challenges during the project's scope of work.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →