CI C0052654 IR-7 Attachment 1 Page 1 of 1 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Cost Element ACE ATO Variance Variance Explanation Steel Towers 113,880 990,177 876,297 Original estimate for foundations was underestimated as NS Power...
AI summary The document presents a cost comparison between the ACE and ATO projects, highlighting significant variances due to underestimated initial costs, increased labor and contract expenses, and the need for additional contingency planning. The request also asks for project numbers, cost comparisons, and explanations of cost allocation and project impacts.