Matter: CI# 40425 - P-510 - NSPI WO - Kempt Road Transformer - $1,093,699Zero dollars spent to date
4 passages 3 documents

Cost Effectiveness across all matters →

N-1Redacted Work Order 1 passage
Why do this project now? p. p. 1
Why do this project now? This project is being advanced at this time such that the probability of loss of load due to a transformer failure is reduced. In addition, favorable pricing is available from the manufacturer on this transformer.

AI summary The project is being advanced now to reduce the probability of load loss from transformer failure and capitalize on favorable manufacturer pricing for the transformer.

N-2Responses to Information Requests IR-1 to IR-14 1/27/2011 1 passage
NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 1 Request IR-14: 2 3 Please discuss the other alternatives and provide a justification that an immediate purchase 4 of a new transformer is the lowest cost option. 5 6 Response IR-14: 7 8 As provided in the response to IR-...

AI summary NSPI justifies immediate purchase of a spare transformer over constructing underground feeders, citing higher costs for duct banks and feeders. Congestion in Halifax Peninsula and 2010 ACE Plan cost data support the transformer option as lower-cost.

064262nd Set of Information Requests (IR-15 to IR-29) 2/21/2011 2 passages
IR-19:
IR-19: With reference to the response to IR-6: - a) Describe any test results regarding the integrity of this third transformer. - b) On page 4 of 20 of the submission NSPI states: liThe remaining unit has been exposed to similar condition...

AI summary IR-19 queries NSPI on test results for a third transformer's integrity, risk assessment of a unit post-procedure, reinforcement measures for transformer integrity, and cost comparison between enhancements and replacement.

IR-28:
IR-28: Please provide and discuss assumed transformers' failure rates, and probabilistic risk assessments of the reliability of power supply to customers in the downtown Halifax area, for the following transformer configurations at the Kem...

AI summary The document requests probabilistic risk assessments and failure rate analyses for transformer configurations at Kempt Road Substation across six timeframes, including pre-2009, post-2010, and scenarios with spare transformers. It also asks for economic analyses comparing urgent transformer purchase versus delayed purchase, referencing prior IR-5(b) responses.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →