HomeCost EffectivenessM12282Evidence
Topic/Matter Intersection

Topic:"Cost Effectiveness" in M12282

Matter: EfficiencyOne - New Benefit Cost Analysis Test for Evaluating Demand Side Management (DSM) Plans Application for Approval of New Benefit Cost Analysis Test for Evaluating Demand Side Management (DSM) Plans
513 passages 82 documents

Cost Effectiveness across all matters →

E-1Notice of Application and Evidence 62 passages
Section 2
was extended through a legislative amendment to the PUA that does as follows: a) extends the term of the existing 2023-2025 DSM Plan by one additional year, to December 31, 2026; b) extends the existing approved demand-side management purc...

AI summary The PUA was amended to extend the 2023-2025 DSM Plan to 2026, set a $63.75M investment, and require E1 to seek Energy Board approval for 2026 targets. The TRC Test is used to evaluate DSM Plan cost-effectiveness.

Section 3
s compared to costs. 9. In its 2022 application for approval of the 2023-2025 DSM Plan, E1 sought regulatory approval to conduct a review of cost-effectiveness testing methodologies: 1 E1 submits that a broad review of cost-effectiveness t...

AI summary E1 requested a review of cost-effectiveness testing methodologies for Nova Scotia's DSM Plan due to legislative changes and advancements in demand response. The Nova Scotia Utility and Review Board approved this, directing E1 to collaborate with the DSM Advisory Group before the 2026-2028 DSM Plan application to determine the optimal methodology.

Section 4
herefore, directs E1 to work with the DSMAG before the 2026-2028 DSM Plan application to assess and develop an optimal DSM cost-effectiveness testing methodology. 11. In accordance with the Board’s direction, E1 worked with the DSMAG to re...

AI summary The document outlines E1's collaboration with the DSMAG to develop a new benefit-cost analysis (BCA) test for Nova Scotia's DSM Plan, including workshops and legislative changes. A 2022 PUA amendment shifted cost-effectiveness testing from program to portfolio level, impacting the BCA's application.

Section 5
t to the PUA that enacted the following relevant changes: a) Changing the level at which cost-effectiveness testing would apply from the program level to the portfolio level; and b) Adding a definition of “demand-side management” to includ...

AI summary The text outlines legislative changes under the Public Utilities Act (PUA) and the Energy Reform (2024) Act, which expanded cost-effectiveness testing and redefined demand-side management. These changes informed the development of a new BCA test by EFG, influenced by policy goals and the National Standard Practice Manual for DER.

Section 6
set out in the National Standard Practice Manual (“NSPM”) for Distributed Energy Resources (“DER”); 3 b) Nova Scotia’s policy goals and objectives, as articulated in legislation; c) input from the DSMAG during workshops; and d) Nova Scotia...

AI summary The document outlines the proposed Best Interest of Customers (BCA) test design, incorporating non-utility system impacts like greenhouse gas emissions and air pollutants, aligned with Nova Scotia's sustainability goals. Inputs included the DSMAG's workshop feedback, policy objectives, and E1's DSM Plan performance data.

Section 9
re reflective of accurate and current data, and of any changes to Nova Scotia policy objectives. This ‘evergreen’ review would be conducted in advance of the development of a new DSM Plan. 24. The utility system impacts and other fuel impa...

AI summary E1 proposes replacing the TRC test with the BCA test (1.0 ratio threshold) for assessing DSM Plans, emphasizing accurate data, evergreen reviews, and quantifying impacts via avoided costs, social cost of carbon, and societal benefits using a 2% discount rate. The BCA test is argued to align with ratepayer interests and regulatory priorities.

Section 10
Group, entitled “Development of a Jurisdictional Benefit Cost Analysis Framework for Nova Scotia”, dated May 13, 2025, to be used in assessing the cost effectiveness of future DSM Plans. 28. In support of this Application, E1 relies on the...

AI summary EfficiencyOne (E1) submits an application for a Jurisdictional Benefit-Cost Analysis (BCA) framework to assess future Demand Side Management (DSM) Plans. E1 cites supporting evidence from Energy Futures Group and asserts the requested order aligns with ratepayer interests. The application emphasizes cost-effectiveness and regulatory compliance.

Section 11
6 EVIDENCE May 16, 2025 EfficiencyOne Benefit-Cost Analysis Test Application Evidence TABLE OF CONTENTS 1. Introduction...........................................................................................................................

AI summary The document outlines EfficiencyOne's application for a benefit-cost analysis test, discussing existing cost-effectiveness tests, gaps in the TRC methodology, and evaluations of current and prospective DSM plans (2023-2025, 2026 extension, 2027-2031). It references Board jurisprudence on cost-effectiveness tests and portfolio-level evaluations.

Section 15
...................................... 35 12. Conclusion ..........................................................................................................................................38 LIST OF TABLES Table 1: Impact Categories...

AI summary EfficiencyOne is applying a Benefit-Cost Analysis (BCA) Test, referencing the National Standard Practice Manual (NSPM) steps and principles for BCA development, as well as the Total Resource Cost (TRC) Test and cost-effectiveness testing in other jurisdictions.

Section 17
iii EfficiencyOne Benefit-Cost Analysis Test Application Evidence

AI summary EfficiencyOne submits a benefit-cost analysis test application as evidence in a regulatory proceeding, likely under the Public Utilities Act (PUA). The application evaluates the cost-effectiveness of demand-side management initiatives, aligning with Nova Scotia's energy efficiency goals.

Section 18
1 1. INTRODUCTION 2 The energy landscape in Nova Scotia is in a state of significant change. The ambitious emissions reductions 3 targets under both provincial and federal legislation are fueling a transition to integrating more renewable...

AI summary Nova Scotia's energy sector is undergoing transformation due to provincial and federal emissions targets, with the Energy Reform (2024) Act creating a new Energy Board to regulate sustainable development. The Total Resource Cost (TRC) test is central to evaluating EfficiencyOne's demand-side management (DSM) plans, aligning regulatory assessments with climate policy objectives.

Section 19
screening test used by E1 is the total resource cost 23 test (“TRC”). The Energy Board, in turn, uses the TRC to inform its assessment of the cost-effectiveness of 24 E1’s DSM Plan, in accordance with the Public Utilities Act. 4 25 26 In i...

AI summary The document discusses EfficiencyOne's (E1) use of the Total Resource Cost (TRC) test to assess demand-side management (DSM) plans under the Public Utilities Act. The Energy Board evaluates E1's DSM Plan using TRC, while the Nova Scotia Utility and Review Board (NSUARB) directed E1 to develop an optimal cost-effectiveness test, leading to hiring Energy Futures Group (EFG) for analysis.

Section 20
25 Page 1 of 38 EfficiencyOne Benefit-Cost Analysis Test Application Evidence

AI summary EfficiencyOne (E1) submits a benefit-cost analysis test application, seeking regulatory approval for its proposed efficiency initiatives. The application focuses on demonstrating cost-effectiveness and aligning with demand-side management (DSM) objectives under Nova Scotia's energy regulations.

Section 21
1 engagement process with the Demand Side Management Advisory Group (“DSMAG”) to inform the 2 development of a new cost-effectiveness test for Nova Scotia. 3 4 In December 2023, E1 and EFG initiated engagement with the DSMAG to develop an...

AI summary E1 and EFG engaged the DSMAG to develop a new cost-effectiveness test (BCA) for Nova Scotia's DSM, aligning with updated policy objectives and provincial legislation. The BCA includes non-utility impacts like societal and host customer benefits, differing from the current TRC test. E1 argues this approach reflects best practices and legislative changes.

Section 22
of the energy 23 sector and the corresponding impacts for consideration in relation to DSM planning, the proposed BCA 24 test including the impact categories and the valuation of same, should be reviewed on an evergreen basis 25 through th...

AI summary E1 seeks approval of a new Best Interest of Customers (BCA) test for evaluating Demand Side Management (DSM) Plans, arguing it better serves ratepayers. The proposal includes an evergreen review process by the DSMAG to assess impact categories before future DSM Plan filings.

Section 23
Table 1: Impact Categories Under TRC Test Total Resource Cost Impact Category Sub-Category Utility System Electric • Generation • Transmission • Distribution • General 12 The cost-effectiveness assessment of E1’s current 2023-2025 DSM Plan...

AI summary The document outlines the Total Resource Cost (TRC) test applied to EfficiencyOne's DSM Plan, emphasizing avoided costs in generation, transmission, and distribution. It notes NS Power's current methodology for calculating utility avoided costs and the upcoming transition to the Independent Energy System Operator. The TRC test requires a cost-effective ratio of 1.0 or greater, but the current test is criticized for not aligning with recent legislative changes.

Section 24
Page 3 of 38 EfficiencyOne Benefit-Cost Analysis Test Application Evidence 1 restricted to utility-related impacts alone. As examples, sustainable development and sustainable 2 prosperity invite consideration of societal GHG impacts and ho...

AI summary The text critiques the current TRC test for excluding host customer benefits, violating the NSPM's symmetry principle, and misaligning with industry standards. It argues this creates biased evaluations favoring certain resources and calls for a more balanced cost-effectiveness framework.

Section 25
ith similar policy objectives in legislation. Examples are provided in Table 2, below. 12 13 Table 2: Examples of Cost-effectiveness Testing in Jurisdictions with Similar Policy Objectives State Test Purpose State-specific cost- Align ener...

AI summary The text argues that Nova Scotia's current Total Resource Cost (TRC) test for evaluating Demand Side Management (DSM) Plans is outdated, as it fails to incorporate environmental and societal considerations mandated by updated policy objectives. Examples from other jurisdictions using alternative cost-effectiveness tests (e.g., New Jersey's state-specific cost-benefit test, California's Societal Cost Test) are cited to support the need for reform.

Section 26
E1 delivers are designed to influence the amount and timing of electricity usage, 24 ultimately reducing the overall demand for electricity (with the (new) exception of strategic electrification, DATE FILED: May 16, 2025 Page 4 of 38 Effic...

AI summary EfficiencyOne (E1) programs aim to influence electricity usage timing and volume to reduce overall demand, with an exception for strategic electrification. The document, filed on May 16, 2025, outlines a benefit-cost analysis test application related to these initiatives.

Section 28
1 as discussed below). The recent legislative amendments to the PUA now include strategic electrification 2 within the definition of demand-side management, for which the proposed BCA test allows consideration. 3 The best practice is to us...

AI summary The document discusses legislative amendments to the PUA, incorporating strategic electrification into demand-side management (DSM) and advocating for the Best Interest of Customers (BCA) test over the Total Resource Cost (TRC) framework. E1, as the franchise holder, must seek regulatory approval for its DSM Plan, with the Energy Board required to assess portfolio-level cost-effectiveness. Historical emphasis on DSM cost-effectiveness is highlighted via the 2010 NSUARB case.

Section 29
jectives of environmental protection, reduction in future energy demand and 23 usage of alternative sources of energy. However, going green is not inexpensive. Well- 24 intentioned efforts to promote DSM must be subject to critical analysi...

AI summary The text emphasizes the need for critical analysis of Demand Side Management (DSM) expenditures to ensure cost-effectiveness and public accountability. It highlights that the cost-effectiveness test applies at the portfolio level, requiring aggregate benefits to exceed costs, with a reference to a prior NSUARB decision on NS Power's 2011 DSM Plan.

Section 31
1 do so). E1 uses the cost-effectiveness framework to guide the development of its DSM Plan among other 2 factors, including the concept of a balanced portfolio design; equitable allocation of investment and 3 savings between residential a...

AI summary E1's DSM Plan employs a cost-effectiveness framework and balanced portfolio design to ensure equitable access across sectors. While low-income programs may individually fail the TRC test, the overall portfolio passes, enabling broader participation. The NSUARB endorsed the 'Balanced Plan Approach' in its 2022 decision, emphasizing stakeholder collaboration.

Section 34
1 Overall, the cost-effectiveness test is the primary assessment of a DSM Plan. A benefit-cost ratio threshold 2 of 1.0 or greater of a DSM Plan must always be satisfied at the portfolio level. While measures that do not 3 meet the ratio t...

AI summary The cost-effectiveness test is central to evaluating DSM Plans, requiring a benefit-cost ratio of 1.0 or higher at the portfolio level. While measures failing the TRC test may be included, E1 must justify their inclusion to align with the Balanced Plan Approach. The Board's 2022 Decision emphasizes that measure-level TRC tests could hinder future market development and equitable access, but measures failing TRC should be justified for strategic or long-term benefits.

Section 35
s provide strategic or long-term 23 benefits. 24 25 [129] Although broadly stated, the Board finds that some of the factors outlined in E1’s 26 response to E1(IG) IR-7(b) provide this justification for the inclusion of the questioned 27 me...

AI summary The Board acknowledges some strategic benefits of E1's measures but downplays arguments about TRC test limitations and non-energy impacts. It emphasizes that future applications must provide individual justifications for measures failing cost-effectiveness tests, while ongoing concerns about the test should be addressed through stakeholder processes.

Section 36
Page 7 of 38 EfficiencyOne Benefit-Cost Analysis Test Application Evidence

AI summary EfficiencyOne submits a benefit-cost analysis test application as evidence in a regulatory proceeding, seeking approval for a program or initiative. The analysis evaluates the financial and operational impacts of the proposed measure.

Section 37
1 4. CURRENT AND PROSPECTIVE DSM PLANS 2 4.1 2023-2025 DSM PLAN 3 On September 6, 2022, the NSUARB (as it then was) approved E1’s application for its 2023-2025 DSM Plan 4 (subject to a compliance filing). 5 6 The cost-effectiveness test ap...

AI summary The NSUARB approved E1's 2023-2025 DSM Plan with a compliance filing, directing the development of an optimal cost-effectiveness test. The Board endorsed E1's proposal to review methodologies via the DSMAG ahead of the 2026-2028 Plan. The PUA amendment extended the DSM Plan to 2026 with prescribed investment levels.

Section 38
er, on March 26, 28 2025, the Nova Scotia government passed an amendment to the PUA that extends the term of the current 29 DSM Plan to December 31, 2026 and prescribes an investment level for the 2026 year of $63,750,000.00. 30 The amendm...

AI summary The Nova Scotia government amended the PUA to extend the 2023-2026 DSM Plan to 2026 with a $63.75M investment target. E1 seeks Energy Board approval for revised performance targets under Board Matter M12249. The TRC test applies to the 2026 DSM year due to its inclusion in the previously TRC-approved 2023-2025 Plan.

Section 40
Energy Board’s decision in relation to the application for approval of the 17 new BCA test herein, and to ensuring the development of the 2027-2031 DSM Plan is in keeping with the 18 decision. 19 20 5. BOARD JURISPRUDENCE ON COST-EFFECTIVE...

AI summary The Nova Scotia government amended the Public Utilities Act to evaluate cost-effectiveness at the portfolio level for demand-side management (DSM) plans, rather than the program level. This aligns with the Energy Board's decision on the BCA test and the development of the 2027-2031 DSM Plan.

Section 54
Page 14 of 38 EfficiencyOne Benefit-Cost Analysis Test Application Evidence

AI summary This document is part of a regulatory proceeding related to the EfficiencyOne Benefit-Cost Analysis Test Application, focusing on evidence submission. It involves an analysis of energy efficiency programs and their associated benefits and costs.

Section 61
st E1 in carrying out this directive. Following a 17 competitive RFP process, E1 retained EFG to act as E1’s consultant in relation to the development of the 18 optimal cost-effectiveness test. 19 20 7.2 EFG SCOPE AND MANDATE 21 EFG’s scop...

AI summary E1 retained EFG to assist in developing a cost-effectiveness test for DSMAG workshops, aligning with Nova Scotia legislation, the NSPM, and using recent local data.

Section 65
Step 1: • Determine whether to include host customer impacts, low-income impacts, other fuel and water impacts, and/or societal impacts. STEP 4 Ensure that Benefits and Costs are Properly Addressed Ensure that the impacts identified in Steps...

AI summary This section outlines the process for addressing benefits and costs symmetrically and comprehensively, ensuring transparency in documentation, and referencing the eight guiding principles from the NSPM as part of the BCA process.

Section 106
embers of the Demand Side 11 Management Advisory Group (DSMAG) on a Nova Scotia specific benefit cost framework for screening 12 distributed energy resources, I make the following recommendations: 13 1. E1 adopt the jurisdictionally specif...

AI summary The testimony discusses the adoption of a jurisdictionally specific benefit cost analysis (BCA) framework for screening distributed energy resources in Nova Scotia. The recommendation is for E1 to use the 'Nova Scotia BCA test' as the primary cost-effectiveness test for future DSM plans, including the 2027-2031 plan. The EFG Report provides further detail on the development of this framework.

Section 119
Non-Energy energy benefits or measure costs (for NEBs and presented and refined Benefits beneficial electrification) proposed NEB proxies with the group. 1 2 5. Comparison of Recommended Nova Scotia Test to Prior Test 3 Q: How does the Nova Sco...

AI summary The Nova Scotia BCA Test recommended by EFG differs from the TRC test used for E1’s 2023-2025 DSM Plan. The TRC test excluded other fuel impacts and non-utility benefits, while the new test includes a broader range of impact categories as outlined in Table 4.

Section 205
"4&ÿ$"ÿ +%, -%&<./0ÿ("(%1' '6ÿT,ÿ(332&''&'ÿ,8&ÿ,82&&ÿ ( "ÿ=(1'ÿ,8(,ÿ +%, -%&<./0ÿ("(%1' 'ÿ 'ÿ4$"3+4,&3Rÿ5$2ÿ(ÿ4+',$ &2ÿ' ,&Zÿ5$2ÿ(ÿ)&$)2(-8 4ÿ2&) $"Zÿ("3ÿ5$2ÿ("ÿ &", 2&ÿ+, % ,1ÿ'&2# 4&ÿ,&22 ,$216ÿB(2,ÿTYÿ(%'$ÿ(332&''&'9ÿ(,ÿ(ÿ8 )8ÿ%&#&%9ÿ31...

AI summary The text discusses the analysis of a regulatory proceeding, focusing on the EfficiencyOne Benefit-Cost Analysis (ABC) and its application in evaluating DEF. It references the use of DEF in assessing programs and policies related to energy efficiency and cost-benefit analysis within the context of regulatory oversight.

Section 268
).'+ . '5ÿ80-ÿ186ÿ+)6,3+.)6@ÿ 0.43- 01ÿ=>?6@ÿ.80ÿ7)ÿ 3'ÿ 0',ÿ 4)/)4 9)-ÿ.,6'6ÿ',ÿ844,Hÿ2,+ÿ8ÿ+)48' /)45ÿ6 A 4)@ÿ- +).'ÿ.,A 8+ 6,0ÿ8.+,66ÿ- 22)+)0'ÿ+)6,3+.)6:ÿÿ sLCE$TLoÿTJKLMCB&ÿ A 8.'6ÿ'(8'ÿ8+)ÿ) ).')-ÿ',ÿ7)ÿ,2ÿ6322 . )0'ÿA810 '3-)ÿ',ÿ822...

AI summary The text discusses regulatory proceedings related to energy efficiency programs, cost recovery mechanisms, and the implementation of energy efficiency initiatives. It references the EfficiencyOne Benefit-Cost Analysis and Nova Scotia Power, emphasizing the importance of cost-effectiveness and program evaluation in the regulatory process.

Section 453
1234ÿ678ÿ9 67ÿ ÿ76ÿ8 ÿ 8ÿ78 ÿÿ  ÿ DATE FILED: May 16, 2025 Page 86 of 302 Appendix A - EfficiencyOne Benefit-Cost Analysis Test Application Attachment 2: National Standard Practice Manual ÿ  7 ÿ!"#$ÿ%&'(ÿ) ++ÿ,-$...

AI summary This document discusses the EfficiencyOne Benefit-Cost Analysis Test Application, referencing the National Standard Practice Manual. It outlines the application of benefit-cost analysis in regulatory proceedings, including topics such as cost-effectiveness, standard practice, and the evaluation of efficiency programs.

Section 623
1234ÿ678ÿ9 67ÿ ÿ76ÿ8 ÿ 8ÿ78 ÿÿ  ÿ DATE FILED: May 16, 2025 Page 138 of 302 Appendix A - EfficiencyOne Benefit-Cost Analysis Test Application Attachment 2: National Standard Practice Manual ÿ ÿ !ÿ"#$%&"'#$ÿ() ÿ+,-)'. ,...

AI summary The document outlines the EfficiencyOne Benefit-Cost Analysis Test Application and references the National Standard Practice Manual. It discusses the application of benefit-cost analysis in the context of energy efficiency programs, including considerations for testing and evaluation methods.

Section 700
@ ÿ#),+,ÿ +,+3ÿ+#./(,ÿ .&0-ÿ),0!ÿ00,8"#,ÿ,0, #/" ÿ+$+#,'ÿ+!"D,+3ÿ!.#, #"00$ÿ!8" (ÿ #),ÿ7 $ÿ5./ÿ'./,ÿ, . .'" ÿ,0, #/"5" #". 2ÿ? $ÿ+& )ÿ"'! #+ÿ. ÿ #&/0ÿ(+ÿ+&!!0",+ÿ -ÿ,'"++". +ÿ +).&0-ÿ%,ÿ,80&#,-ÿ. ÿÿ +,4%$4 +,ÿ%+"+2ÿ PQRQRÿ hicVÿj\cVi_XYÿki...

AI summary The text discusses the regulatory proceedings related to the Board of Fuel Costs (BFC) and the Board of Commissioners (BC), focusing on the implementation of the fuel-cost-adjustment mechanism and the impact of the Public Utilities Act (PQR). It references the need for regulatory oversight and the evaluation of cost-effectiveness and compliance.

Section 752
1234ÿ678ÿ9 67ÿ ÿ76ÿ8 ÿ 8ÿ78 ÿÿ  ÿ DATE FILED: May 16, 2025 Page 173 of 302 Appendix A - EfficiencyOne Benefit-Cost Analysis Test Application Attachment 2: National Standard Practice Manual ÿ !"#"$ÿ&'() +,+-.ÿ01'2345 -...

AI summary This section discusses the EfficiencyOne Benefit-Cost Analysis Test Application and references the National Standard Practice Manual. It outlines the process for evaluating benefit-cost analyses, including considerations for program evaluation, cost-effectiveness, and standard practices in regulatory proceedings.

Section 793
1234ÿ678ÿ9 67ÿ ÿ76ÿ8 ÿ 8ÿ78 ÿÿ  ÿ DATE FILED: May 16, 2025 Page 185 of 302 Appendix A - EfficiencyOne Benefit-Cost Analysis Test Application Attachment 2: National Standard Practice Manual ÿ !"#$"%&ÿ () +,-+)./ÿ0+1ÿ ,...

AI summary The text discusses the application of a benefit-cost analysis test under the EfficiencyOne program, referencing the National Standard Practice Manual. It outlines the methodology for evaluating the cost-effectiveness of efficiency programs, including the use of standard practice guidelines and the evaluation of demand-side management initiatives.

Section 799
'ÿ#$( ($!ÿ,!,$'?ÿ1#$ÿ ,"ÿ&5'ÿ$&'ÿ "$'+$( ÿ$"ÿ(? 0$ÿ0#,$"?'),3ÿ2A''ÿB& $')ÿzÿ+-ÿ71 'ÿ z:{%ÿ(+ÿ ($("+ÿ$"ÿB& $'),ÿ n}36ÿ;'$')?(+(+/ÿ&",$ÿ0#,$"?')ÿ(? 0$,%ÿ(+0 #-(+/ÿ+"+:'+')/!ÿ(? 0$,%ÿ9( ÿ )'~#()'ÿ ($("+ ÿ0"+,(-')$("+,ÿ1'!"+-ÿ$&",'ÿ-(,0#,,'-ÿ'...

AI summary The text discusses the application of a benefit-cost analysis test in the context of efficiency programs, referencing the National Standard Practice Manual. It outlines procedures for evaluating the cost-effectiveness of energy efficiency initiatives and mentions the importance of aligning with regulatory standards.

Section 899
aa aUG[YFCVC[QYCMR J^t qÿnfrp arP JIt kUUÿ̀abP Jst ÿ BCDEFGÿHI]^JKÿLFMNCOGPÿQRÿGSQTLUGÿMVÿQÿEPGVEUÿWQXÿYMÿLFGPGRYÿYZGÿFGPEUYPÿMVÿQÿUMRDJYGFTÿLQFYC[CLQYCMRÿ QRQUXPCP\ÿ_YÿLFGPGRYPÿVCNGÿXGQFPÿMVÿZCPYMFC[QUÿ̀abÿLQFYC[CLQYCMRÿFQYGPcÿQPÿWGUUÿQPÿ...

AI summary The text discusses the implementation of a fuel-cost-adjustment mechanism and its impact on base rates, noting a lag of 18 months between actual costs and base rates, which created perverse incentives. It also references the need for regulatory oversight and evaluation of cost-effectiveness in energy programs.

Section 931
 ÿ DATE FILED: May 16, 2025 Page 228 of 302 Appendix A - EfficiencyOne Benefit-Cost Analysis Test Application Attachment 2: National Standard Practice Manual ÿ !!"!"ÿ#$%&$ÿ%&!ÿ'%$($%) ÿ+!%#!!ÿ%&!ÿ'%$($%)ÿ,"ÿ-%&!.ÿ,/!0$!1ÿ#$%&ÿ2(, $/ÿ.!12-...

AI summary This text discusses the EfficiencyOne Benefit-Cost Analysis Test Application and references the National Standard Practice Manual. It outlines considerations related to benefit-cost analysis, including the evaluation of programs, cost-effectiveness, and the application of national standards for analysis.

Section 934
!"#$ÿ &ÿ() ÿ+, )- .ÿ /012ÿ34456718ÿ58493162ÿ0:;ÿ<=>2ÿ?36ÿ9537ÿ@:ÿA3@5ÿ1B43?@2Cÿ367ÿ0:;ÿA3@5ÿ1B43?@2ÿ3A5ÿ71DD5A56@ÿDA:Bÿ?:2@E 5DD5?@1F56522ÿ367ÿ;0Gÿ@05ÿ@;:ÿ20:H97ÿI5ÿ583B1657ÿH216Jÿ2543A3@5ÿ3639G252KÿL@ÿ392:ÿ752?A1I52ÿ0:;ÿ@:ÿ ?:67H?@ÿ3ÿB536...

AI summary The document discusses the regulation of energy efficiency programs, including the evaluation of cost-effectiveness, the role of the Board in setting policies, and the implementation of measures such as demand-side management and energy efficiency initiatives. It also touches on the evaluation of program performance and stakeholder engagement.

Section 974
:ÿ7>BÿD>BM=BA90Fÿ8@A?=89B?ÿ9@ÿM=7A94DFÿ123ÿGBABD49:Kÿ4Aÿ67>948=07>ÿ9;Bÿ =94049Fÿ:F:9B5ÿGBABD49:Hÿj;B:Bÿ:9=?4B:ÿ7>Bÿ9F648700Fÿ<=>4:?4894@AC:6B84D48ÿ9@ÿBA:=>Bÿ9;79ÿ9;BFÿ788=>79B0Fÿ 8769=>Bÿ9;Bÿ@6B>794@A:ÿ7A?ÿ9;Bÿ456789:ÿ@Dÿ9;Bÿ=94049Fÿ:F:9B5...

AI summary The text discusses the application of a benefit-cost analysis test for EfficiencyOne, referencing regulatory practices and procedures. It touches on topics such as regulatory compliance, cost-effectiveness, and the evaluation of programs and policies.

Section 1086
ÿ 0"ÿ;, "ÿ($ÿ;(+-"-ÿ$ ",ÿ#;+/1#ÿ)"/"$+ #ÿ+/ÿH"'ÿGF.ÿ %0+,"ÿ,(%"'ÿ-+#2( / ÿ' "#ÿ0;"ÿÿ5 20ÿ#5 ,,"'ÿ+592 3ÿ IJKLMNÿPQRSÿTUVWJXYZJ[]ÿ[^ÿ_J]X[L\Zÿ̀YZN]ÿaY\\LYWÿVMN]N\ZÿbYWLNÿc[WWYM]dÿ ÿ 17 eÿfgÿ 6ÿ8ÿh8 ÿÿ8ÿ78ÿijjkÿl ÿ678ÿ6...

AI summary The text discusses the analysis of regulatory proceedings, including the evaluation of programs, policies, and legal frameworks, with a focus on topics such as energy efficiency, affordability, and stakeholder engagement. It also references various regulatory processes and the use of cost-effectiveness and prudence reviews.

Section 1118
1234ÿ678ÿ9 67ÿ ÿ76ÿ8 ÿ 8ÿ78 ÿÿ  ÿ DATE FILED: May 16, 2025 Page 284 of 302 Appendix A - EfficiencyOne Benefit-Cost Analysis Test Application Attachment 2: National Standard Practice Manual ÿ !ÿ"#$%&#'ÿ&()& +&,!ÿ-.ÿ+$/...

AI summary The text discusses the application of the EfficiencyOne Benefit-Cost Analysis Test, referencing the National Standard Practice Manual. It highlights the importance of assessing the cost-effectiveness of energy efficiency programs and the need for proper evaluation methodologies.

Section 1127
,&0ÿ/,)0/$%ÿ&ÿ( %$)0 ,ÿ$)ÿ ,/-&(ÿ#$ÿ3#$+ÿ&ÿ0),ÿ""#(#!$ÿ/,)' ($ÿ%))!,ÿ$+&!ÿ+ÿ),ÿ%+ÿ)$+,3#%ÿ3) -'ÿ+&51ÿ G),ÿ$+ÿ"#,%$ÿ$+, ÿ)"ÿ$+)%ÿ""#(#!(.ÿ0 &% ,ÿ(-&%%#"#(&$#)!%8ÿ$+ÿ()%$ÿ#0/&($%ÿ&,ÿ()00)!-.ÿ"-$ÿ)!-.ÿ#!ÿ $+ÿ"#,%$ÿ.&,ÿH#118ÿ$+ÿ#!(,0 !$&-ÿ()%$...

AI summary The text discusses regulatory proceedings related to utility rates and cost recovery, emphasizing the importance of aligning base rates with actual costs, the role of fuel-cost-adjustment mechanisms, and the evaluation of cost-effectiveness in regulatory decisions. It highlights concerns over potential inefficiencies and the need for proper oversight in rate-setting processes.

Section 1147
1234ÿ678ÿ9 67ÿ ÿ76ÿ8 ÿ 8ÿ78 ÿÿ  ÿ DATE FILED: May 16, 2025 Page 293 of 302 Appendix A - EfficiencyOne Benefit-Cost Analysis Test Application Attachment 2: National Standard Practice Manual ÿ !"#$ÿ&'(#)ÿ +ÿ,-(./!)ÿ 9 6...

AI summary This text discusses the application of a benefit-cost analysis test under the National Standard Practice Manual for an EfficiencyOne initiative. It outlines the methodology for evaluating efficiency programs, including the consideration of cost-effectiveness, program design, and alignment with regulatory standards.

Section 1201
Utility Gas Emissions  emissions System Other Estimated health impacts from Societal Environmental  PM, SO2 and NOx air pollutants Embedded in other Public Health E Environmental and GHG Economic Should be addressed outside of Developmen...

AI summary The text discusses the categorization of impacts related to gas emissions, public health, and environmental considerations, emphasizing the need for separate studies outside the BCA framework. It references the structure of these categories and their sub-elements described in the report.

Section 1209
s the new Nova Scotia test include all electric utility system impacts, other fuel impacts, host customer impacts, greenhouse gas impacts, and criteria air pollutant impacts. 2) E1 should screen the cost effectiveness of demand side portfo...

AI summary The new Nova Scotia Jurisdictional Test is proposed to include various system and environmental impacts, and to use updated avoided cost streams for cost-effectiveness screening of demand-side portfolios. The test is expected to evolve, with future responsibility for avoided cost calculations shifting to the Independent Electricity System Operator.

Section 1212
assessed in a separate analysis and that job and that indirect and induced economic impacts not be incorporated into the new jurisdictional test. (See Table 16 and Figure 3). 10) EFG recommends the primary jurisdictional test use a 2% soci...

AI summary EFG recommends using a 2% social discount rate in the primary jurisdictional test for assessing the cost-effectiveness of the E1 portfolio. They also suggest that indirect and induced economic impacts not be included in the test, and that secondary tests like the utility cost test be used for additional perspective, not as a substitute.

Section 1220
energyfuturesgroup.com 20 The results of the illustrative example in Table 5 indicate that the cost effectiveness of the 1,000 heat pump replacements depends upon the type of fuel displaced, and that heat pumps displacing fuel oil or elect...

AI summary The illustrative example in Table 5 shows that replacing 1,000 heat pumps is cost-effective when displacing fuel oil or electric resistance, yielding net benefits of $25 million and $31 million, respectively. However, replacing natural gas with heat pumps results in a net cost increase of $17 million. Electric system costs increase by roughly $26 million in both cases.

Section 1225
Page 23 of 68 EfficiencyOne Benefit-Cost Analysis Test Application Appendix B energyfuturesgroup.com 24 achieve a benefit-cost ratio of 1.0 or higher to be considered cost-effective. Looking forward, it is anticipated plan level screening...

AI summary EfficiencyOne (E1) discusses the benefit-cost analysis (BCA) test application for the 2023-2025 Demand Side Management (DSM) Plan. E1 argues that the Test of Reasonableness (TRC) applied is conservative and unbalanced, violating the symmetry principle of the Nova Scotia Power (NSPM). E1 also raised concerns about understated avoided costs and the need for an optimal BCA methodology.

Section 1226
Review Board (NSUARB) to work with the Demand Side Management Advisory Group (DSMAG) “to assess and develop an optimal DSM cost-effectiveness testing [benefit-cost analysis] methodology.” 16 Through a competitive RFP process, E1 hired Ener...

AI summary The NSUARB is working with the DSMAG to develop a new benefit-cost analysis (BCA) methodology for demand-side management (DSM) programs. E1 hired Energy Futures Group, Inc. to support this effort, which involved stakeholder engagement and a review of the current BCA test. There was a lack of consensus on the impacts included in the current test, leading to a recommendation for clearer documentation in the new BCA framework.

Section 1233
cipants included organizational representation from: Energy Futures Group, Inc PO Box 587, Hinesburg, VT 05461 – USA 802-482-5001 802-329-2143 [email protected] DATE FILED: May 16, 2025 Page 28 of 68 EfficiencyOne Benefit-Cost An...

AI summary The document is an appendix to a Benefit-Cost Analysis Test Application submitted by EfficiencyOne. It includes contact information for Energy Futures Group, Inc., and references the test application filed on May 16, 2025.

Section 1247
categories such as host customer non-energy benefits or environmental benefits, and therefore they are not recommended for separate accounting to avoid potential double counting of impacts. Working group members also identified additional...

AI summary The document discusses the inclusion of utility system impacts (USIs) in cost-effectiveness tests for DERs, emphasizing the need to compare economic merits of DERs with supply-side alternatives. It highlights potential overlaps in impact categories and notes that not all USI impacts may be relevant or material for every DER.

Section 1276
numerous occasions, and there was some discussion of using percent adders for different measure categories as an alternative to the adjusted measure- based values derived from Massachusetts. During the regulatory review of E1’s NEBs Applic...

AI summary The NSUARB ruled it lacks jurisdiction to consider non-energy impacts in cost-effectiveness testing. E1 included host customer costs and savings in its 2023-2025 DSM Plan, but the NSUARB directed their removal. Despite this, the BCA test in the plan still included some host customer costs.

Section 1278
44 measures installed through E1 initiatives. Following the NSPM’s symmetry principle, if host customer costs are counted, then host customer benefits should also be considered. During the fourth through the sixth DSMAG working group sessi...

AI summary The document discusses the inclusion of non-energy host customer impacts in the cost effectiveness screening of energy efficiency programs, based on the Energy Reform Act (ERA) and discussions from the Demand Side Management Advisory Group (DSMAG). It recommends using proxy adders, differentiated by measure category, DER type, and customer segment, and notes that 18 U.S. jurisdictions incorporate non-energy benefits into such screening.

Section 1318
,234 7,878 2,836 1,398 $308 $ 180 $ - $ 308 0.85 $367,454 2034 84,470 4,234 7,878 2,907 1,327 $313 $ 184 $ - $ 313 0.84 $347,527 2035 84,470 4,234 7,878 2,119 2,115 $317 $ 188 $ - $ 317 0.82 $549,937 2036 84,470 4,234 7,878 2,797 1,437 $32...

AI summary The analysis compares the cost effectiveness of displacing different fuels, showing that displacing heating oil is more cost effective than displacing pipeline gas, with net benefits of over $25 million versus a $20 million increase in net energy costs for pipeline gas, partially offset by GHG benefits.

Section 1319
t on the type of displaced fuel and suggests that measures and program initiatives targeting displacement of heating oil fuel may be more cost effective than displacement of pipeline gas. Energy Futures Group, Inc PO Box 587, Hinesburg, VT...

AI summary The text discusses the cost-effectiveness of measures targeting the displacement of heating oil fuel compared to pipeline gas. It also references an appendix containing a Nova Scotia policies inventory and a working group review of current practices for electric utility system impacts.

Section 1320
63 B. Working Group Review of Current Practice for Electric Utility System Impacts Table B1 is a synthesis of the working group homework assignment and discussions of which electric USIs are currently included in the Nova Scotia screening...

AI summary This section discusses the working group's review of current practices for including electric utility system impacts in the Nova Scotia screening test of energy efficiency and demand response programs. It also outlines the social costs of carbon and greenhouse gas impacts based on Canadian guidance.

E-2E1 (ECEL) RIR 1 1 passage
E1 Responses to East Coast Environmental Law (ECEL) Information Requests NON-CONFIDENTIAL p. pp. 0-1
E1 Responses to East Coast Environmental Law (ECEL) Information Requests NON-CONFIDENTIAL Request IR-01: Refer to Exhibit E-1, "Notice of Application and Evidence", within the "Evidence" section, dated May 16, 2025. At page 18, lines 21-25...

AI summary The response explains the National Standard Practice Manual (NSPM) is used across North America for developing cost-effectiveness tests. Adhering to NSPM ensures alignment with national standards and Nova Scotia's policy objectives for demand-side management plans.

E-3E1 (EE) RIR 1-12 2 passages
Preamble p. p. 1
Request IR-01: - Reference: Evidence Page 7: A benefit-cost ratio threshold of 1.0 or greater of a DSM Plan must - always be satisfied at the portfolio level. While measures that do not meet the ratio threshold - can be included, E1 must j...

AI summary The proceeding addresses EfficiencyOne's (E1) approach to justifying demand-side management (DSM) measures that fail to meet a benefit-cost ratio (BCR) threshold of 1.0. E1 plans to use a regulator-approved cost-effectiveness test, citing factors like equity, emerging technologies, and market needs. The request also asks if prior Board approval is required and if stakeholder input is sought for such measures.

E1 Responses to Eastward Energy Inc. (Eastward Energy) Information Requests NON-CONFIDENTIAL p. pp. 1-8
E1 Responses to Eastward Energy Inc. (Eastward Energy) Information Requests NON-CONFIDENTIAL - (b) E1 was directed by the Nova Scotia Utility and Review Board in their Board Order on E1's 2023-2025 DSM Plan "To provide specific justificati...

AI summary E1 is responding to information requests by the Nova Scotia Utility and Review Board (NSUARB), explaining that it will justify DSM measures failing cost-effectiveness testing in future resource plans, including the 2027-2031 DSM Plan. E1 engages with the DSMAG, sharing modelling details and seeking input during plan development.

E-4E1 (IG) RIR 1-6 11 passages
1 Request IR-01: p. p. 1
1 Request IR-01: 2 3 Reference: E-1, Application, page 5, para 26 (pdf page 6 of 450). 4 5 E1 submits that the proposed BCA test is appropriate, reasonable, is in the 6 best interest of ratepayers, and should replace the existing TRC test...

AI summary The document discusses E1's proposed BCA test as a replacement for the existing TRC test for evaluating DSM plans. E1 argues the BCA test is in the best interest of ratepayers and more balanced than the TRC test, which is criticized for being biased due to its inclusion of host customer costs but not participant benefits.

Preamble p. pp. 1-17
Recent legislative changes and evolving energy priorities—especially related to electrification and decarbonization—have further prompted a re-evaluation of this framework. The Nova Scotia Utility and Review Board (now Nova Scotia Energy B...

AI summary Recent legislative changes and energy priorities have prompted a re-evaluation of the cost-effectiveness framework for demand-side management (DSM). The Nova Scotia Energy Board has directed E1 to work with the DSMAG to develop a jurisdiction-specific BCA test to better evaluate DSM investments and align with Nova Scotia's evolving energy and environmental goals.

M12282 – EfficiencyOne (E1) Application for Approval of a New Benefit-Cost Analysis (BCA) Test for Evaluating Demand Side Management (DSM) Plans p. pp. 1-26
M12282 – EfficiencyOne (E1) Application for Approval of a New Benefit-Cost Analysis (BCA) Test for Evaluating Demand Side Management (DSM) Plans

AI summary EfficiencyOne (E1) seeks approval for a new Benefit-Cost Analysis (BCA) test to evaluate Demand Side Management (DSM) plans in Nova Scotia. The application aims to establish a revised methodology for assessing DSM initiatives under regulatory oversight.

E1 Responses to Industrial Group (IG) Information Requests NON-CONFIDENTIAL p. pp. 1-26
E1 Responses to Industrial Group (IG) Information Requests NON-CONFIDENTIAL 1 (d) E1's assertion that the BCA test is in the "best interest of ratepayers" does indicate that the 2 test is intended to continue serving as a key tool for eval...

AI summary E1 responds to Industrial Group (IG) requests regarding the proposed Benefit-Cost Analysis (BCA) test, emphasizing its alignment with policy priorities and provincial legislation. It contrasts the BCA with the existing Total Resource Cost (TRC) test, noting that energy impacts outweigh non-energy impacts. Energy Futures Group (EFG) confirms energy impacts dominate in the BCA test (77% of total impacts). The 2026 DSM Plan extension and DSMAG engagement are referenced.

E1 Responses to Industrial Group (IG) Information Requests NON-CONFIDENTIAL p. p. 1
E1 Responses to Industrial Group (IG) Information Requests NON-CONFIDENTIAL 1 Under the proposed Nova Scotia jurisdictional test, energy impacts will continue to be the 2 most important contributors to cost effectiveness results. In the ne...

AI summary Under the proposed Nova Scotia jurisdictional test, energy impacts will remain the primary factor in cost effectiveness, though non-energy impacts will now be included and may vary by measure type and market segment. The trend of energy impacts outweighing non-energy impacts is expected to continue.

Section 7 p. p. 1
Request IR-03: (a) Approximately how much additional work does E1 anticipate will be required to accomplish its new BCA test compared to the existing TRC for both forecasting and reporting results? (b) Please provide detail of the work pro...

AI summary EfficiencyOne (E1) anticipates some incremental work to implement a new BCA test compared to the existing TRC test, focusing on quantifying new impact streams. The BCA test is intended to be a more accurate and practical tool for assessing the cost-effectiveness of DSM plans. E1 has initiated this work with the DSMAG and believes the BCA balances analytical rigor with practical feasibility.

Section 8 p. p. 1
ds the BCA analysis in real-world data while respecting practical considerations, ensuring the analysis generates meaningful insights without over-investing beyond the point of diminishing returns. 6 7 (b) To implement the proposed BCA tes...

AI summary The text discusses the implementation of a BCA test by E1, requiring quantification of all included impacts as outlined in a table. The focus is on ensuring the analysis is practical and generates meaningful insights without over-investment.

1 p. p. 1
1 1 Request IR-04: 2 3 Reference: E-1, Evidence, Section 2.2, page 4. 4 5 The National Standard Practice Manual ("NSPM"), which provides a comprehensive framework 6 for cost-effectiveness assessment of Distributed Energy Resources, identif...

AI summary The document discusses the principle of symmetry in cost-effectiveness assessments of Distributed Energy Resources, as outlined in the National Standard Practice Manual. It also addresses the use of Program Administrator Cost (PAC) test results in regulatory proceedings, explaining their informational purpose and how they relate to the Total Resource Cost (TRC) test.

4 p. p. 1
4 1 Request IR-06: 2 3 Reference: E-1, Evidence, Section 5.2, Jurisdiction to Consider Non-Energy Impacts, pages 11- 4 12. 5 6 (a) Is it E1s position that the new legislation to consider non-energy impacts eliminates the 7 Board's conclusi...

AI summary The document discusses the implications of new legislation on the definition and assessment of cost-effectiveness for DSM plans, referencing the removal of section 79L from the Public Utilities Act and the substitution with new requirements for the Board to assess the best interests of customers and the approval of demand-side management applications.

E1 Responses to Industrial Group (IG) Information Requests NON-CONFIDENTIAL p. pp. 26-30
E1 Responses to Industrial Group (IG) Information Requests NON-CONFIDENTIAL health impacts. The definitions of "sustainable development"[1](#page-29-0) and "sustainable prosperity"[2](#page-29-1) encompass environmental stewardship and soc...

AI summary E1 responds to the Industrial Group's request regarding public health impact categorization, stating it is already addressed via GHG emissions and air pollutant impacts. The response also references legislative definitions of 'sustainable development' and 'sustainable prosperity' from the Environment Act and Environmental Goals and Climate Change Reduction Act 2021. A request for clarification on addressing NSPM Appendix A (Rate Impacts) and BCA approval stages is noted.

Section 44 p. p. 37
6 Request IR-16: Please indicate if, or how, the proposed BCA test can help inform the appropriate level of incentives or subsidies for participation in efficiency initiatives and provide an example. Response IR-16: One of the factors that...

AI summary The response to Request IR-16 explains how the proposed BCA test will replace the current TRC test to assess the cost-effectiveness of efficiency measures. It highlights that the BCA considers both customer costs and incentive costs, with the ratio calculated by dividing total benefits by total costs. An example from Energy Futures Group is referenced.

E-5E1 (NSEB) RIR 1-46 14 passages
Section 1 p. p. 0
Request IR-01: - Please discuss how the November 9, 2022, Public Utilities Act changes to the level of cost- - effectiveness test from the program level to the portfolio level have changed the analysis - results, citing analysis results, u...

AI summary The November 9, 2022 amendment to the Public Utilities Act changed the cost-effectiveness evaluation level from the program level to the portfolio level. However, this change does not affect how EfficiencyOne performs cost-effectiveness testing or the results, which remain available at multiple levels including the portfolio level.

1 Request IR-03: p. pp. 6-7
1 Request IR-03: 2 3 With regards to Table 2 on page 4 of 38 of E1's Evidence: 4 5 (a) Did E1 review any Canadian jurisdictions with similar policy objectives as Nova Scotia to 6 assess how the current TRC test aligns with standard for cos...

AI summary E1 was asked to review Canadian jurisdictions with similar policy objectives to Nova Scotia for cost-effectiveness testing alignment. E1 responded that their research did not include such a review, as a Nova Scotia-specific BCA must reflect the province's own legislative, regulatory, and policy context.

- 2 system benefit that is not measured and is considered not material. p. p. 8
- 2 system benefit that is not measured and is considered not material. 1 Request IR-05: 2 3 Please describe how the BCA as proposed by E1 aligns with the Treasury Board of Canada 4 Secretariat Canada's Cost-Benefit Analysis Guide for Regu...

AI summary The document outlines a request for information on how the proposed BCA by EfficiencyOne aligns with Canadian federal cost-benefit analysis guidelines. The response indicates that E1's framework is consistent with the principles of transparency, comprehensiveness, and evidence-based decision-making as outlined in the 2019 and 2018 federal guidelines.

Section 17 p. p. 12
electrification. Request IR-07: On page 18 of 38 of E1's Evidence, a hyperlink to the "National Energy Screening Project (NESP), National Standard Practice Manual (NSPM) for Benefit-Cost Analysis of Distributed Energy Resource" is provided...

AI summary The request focuses on the National Energy Screening Project (NESP) and its National Standard Practice Manual (NSPM) for Benefit-Cost Analysis (BCA) of distributed energy resources. It asks for details about NESP members, deviations of the proposed BCA test from the NSPM, the use of the MTR handbook, and how many states have adopted the NSPM framework.

Section 19 p. p. 12
ii) How many states in the database are currently using a Societal Cost Test (SCT) for DSM portfolios, programs or measures? (Please identify the related states and whether the test is applied at the measure, program or portfolio level) ii...

AI summary The text lists nine questions about the use of Societal Cost Test (SCT) and measurement of various societal impacts (resilience, environmental, public health, etc.) in Benefit-Cost Analysis (BCA) for Demand-Side Management (DSM) across states in a database. It seeks details on which states apply these tests/impacts and at what level (measure, program, portfolio).

Section 20 p. p. 12
e currently measuring Host Customer "Asset Value" impacts for their related BCA test? (Please identify the related states and whether the test is applied at the measure, program or portfolio level.)

AI summary The text asks whether the current Benefit-Cost Analysis (BCA) test measures Host Customer 'Asset Value' impacts, and seeks clarification on the states involved and the level (measure, program, portfolio) at which the test is applied.

Section 21 p. p. 12
x) How many states in the database are currently measuring Host Customer "Water Cost" impacts for their related BCA test? (Please identify the related states and whether the test is applied at the measure, program or portfolio level.) xi)...

AI summary The text lists questions inquiring about the number of states measuring various Host Customer impact categories (e.g., Water Cost, O&M Cost) in their BCA tests and the levels at which these tests are applied.

Section 22 p. p. 12
e currently measuring Host Customer "Empowerment" impacts for their related BCA test? (Please identify the related states and whether the test is applied at the measure, program or portfolio level.)

AI summary The document questions the current measurement of Host Customer Empowerment impacts within the BCA test, seeking clarification on related states and the level (measure, program, portfolio) at which the test is applied.

Section 23 p. p. 12
xviii) How many states in the database are currently measuring Host Customer "Pride" impacts for their related BCA test? (Please identify the related states and whether the test is applied at the measure, program or portfolio level.) (e) P...

AI summary The response discusses the National Energy Screening Project (NESP), its mission to improve cost-effectiveness screening practices for distributed energy resources (DERs), and its products including the National Standard Practice Manual (NSPM) and Methods, Tools, and Resources (MTR) Handbook. It highlights NESP's role in convening stakeholders and providing BCA resources.

Section 24 p. pp. 12-20
Resources Handbook](https://www.nationalenergyscreeningproject.org/resources/quantifying-impacts/) [(MTR Handbook)](https://www.nationalenergyscreeningproject.org/resources/quantifying-impacts/) . NESP is primarily funded by E4TheFuture wi...

AI summary EfficiencyOne proposes a BCA framework aligned with NSPM principles for DSM plans. The framework requires further analysis of utility system impacts, though EFG believes benefits may outweigh costs. Impact quantification will occur during DSM plan development, with the MTR handbook as a technical reference.

Section 25 p. pp. 12-20
M portfolio and plan. The MTR handbook provides a useful technical reference for the steps and resources that will be used in quantifying individual impact categories. (d) [https://www.nationalenergyscreeningproject.org/wp-content/uploads/...

AI summary EfficiencyOne (E1) applies for approval of a new BCA test for DSM plans in Nova Scotia, referencing jurisdictional-specific tests adopted by states like Connecticut and Maine, and the societal cost test used in Arizona and Vermont. The application cites the National Standard Practice Manual (NSPM) and the Database of Screening Practices (DSPs) to support its framework.

E1 Responses to Nova Scotia Energy Board (NSEB) Information Requests NON-CONFIDENTIAL p. p. 23
E1 Responses to Nova Scotia Energy Board (NSEB) Information Requests NON-CONFIDENTIAL 1 propose an optimal cost effectiveness test specifically aligned with Nova Scotia's 2 policy objectives.

AI summary The document proposes an optimal cost-effectiveness test aligned with Nova Scotia's policy objectives, aiming to ensure that energy efficiency initiatives are both economically and environmentally effective.

M12282 – EfficiencyOne (E1) Application for Approval of a New Benefit-Cost Analysis (BCA) Test for Evaluating Demand Side Management (DSM) Plans p. pp. 31-42
M12282 – EfficiencyOne (E1) Application for Approval of a New Benefit-Cost Analysis (BCA) Test for Evaluating Demand Side Management (DSM) Plans

AI summary EfficiencyOne (E1) seeks approval for a new Benefit-Cost Analysis (BCA) test to evaluate Demand Side Management (DSM) plans under Nova Scotia regulatory proceedings. The application involves assessing DSM initiatives using updated methodologies, with implications for energy policy and regulatory frameworks.

Preamble p. pp. 63-69
f avoided fuels are counted in the "Other fuels" category, host customer impacts do not include fuel savings benefits for the host (these would be double counted) and focus on the non-energy benefits. Request IR-31: Reference: Appendix B E...

AI summary The response explains that the Planning Reserve Margin (PRM) adjustment reduces Nova Scotia Power's required planning reserve due to demand-side management (DSM). Data sources include NS Power's August 23, 2024, submission and reference to M12249. The adjustment affects E1's cost estimation for avoided capacity.

E-6E1 (SBA) RIR 1-20 6 passages
Preamble p. p. 0
Request IR-01: Refer to Exhibit E-1 EfficiencyOne's Application for Approval of a New Benefit-Cost Analysis (BCA) Test for Evaluating Demand Side Management (DSM) Plans, (the "Application") filed May 16, 2025, E1 Evidence, page 34 of 38, T...

AI summary The document details a regulatory request (IR-01) for EfficiencyOne's (E1) application to approve a new Benefit-Cost Analysis (BCA) test for evaluating Demand Side Management (DSM) plans. E1's response refers to Energy Futures Group's (EFG) workbook and report, which provide formulas, data sources, and examples for calculating non-utility impact categories. Key references include EFG's report (Appendix B) and specific tables from E1's evidence.

Section 7 p. pp. 9-11
Request IR-08: Refer to Exhibit E-1, the Application, page 18 of 38, line 5. Regarding the creation of green jobs and stimulating economic growth, please provide the results of econometric modeling that EOne has performed or commissioned t...

AI summary The response to Request IR-08 indicates that EfficiencyOne has not conducted econometric modeling to assess the economic and job impacts of the proposed BCA Test. The Energy Futures Group (EFG) Report is referenced, suggesting that such impacts should be analyzed separately.

Section 8 p. p. 11
of a Jurisdictional Benefit Cost Analysis Framework for Nova Scotia (EFG Report), Prepared by Energy Futures Group, page 12 & 33 of 68. recommended for inclusion in the proposed BCA. [1](#page-11-0) Request IR-09: Refer to Exhibit E-1, the...

AI summary The response to Request IR-09 discusses how the current Total Resource Cost (TRC) test in Nova Scotia does not adhere to the National Standard Practice Manual (NSPM) in several key principles, including the treatment of DERs, alignment with policy goals, symmetry, and inclusion of material impacts such as host customer costs.

Section 14 p. p. 16
(c) Please see Appendix F of the EFG Report[1](#page-18-0) 1 for a summary table from the National Energy Screening Database for information on jurisdictions that include comfort and health and safety impacts in their cost effectiveness te...

AI summary The text references Appendix F of the EFG Report, which contains a summary table from the National Energy Screening Database. The table lists jurisdictions that include comfort and health and safety impacts in their cost effectiveness tests, including Colorado, Delaware, and others.

Section 20 p. p. 22
ity, greenhouse gas reductions) would have better results than seen under the TRC, however this is not a comment on whether they will pass or fail. Date Filed: July 4, 2025 E1 (SBA) IR-17 Page 1 of 1 Request IR-18: Please list all the fact...

AI summary EfficiencyOne (E1) outlines factors beyond the Benefit Cost Analysis (BCA) test for determining DSM program funding, including equitable allocation, customer bill impacts, Integrated Resource Plan (IRP) requirements, historical spending, industry capacity, and emerging technology support. Responses to IR-19 are incomplete, focusing on financing arrangements and per capita funding data requests.

(a) Summary Table – Canadian Cost Effectiveness Testing p. pp. 22-27
(a) Summary Table – Canadian Cost Effectiveness Testing Province Primary Test Additional Tests Used Non-Energy Benefits Alberta Societal Abatement Cost, Program Province Primary Test Additional Tests Used Non-Energy Benefits Abatement Cost...

AI summary The summary table outlines the cost-effectiveness testing approaches used across Canadian provinces, including primary and additional tests, and the inclusion of non-energy benefits. Nova Scotia uses the Total Resource Cost (TRC) test and the Program Administrator Cost test.

E-7E1 (Synapse) RIR 1-24 3 passages
Preamble p. pp. 0-26
Request IR-01: Refer to EfficiencyOne's (E1) Evidence at page 28, which includes the list of distribution impacts included in the new benefit-cost analysis (BCA) test. (a) Did the Demand Side Management Advisory Group (DSMAG) consider incl...

AI summary The response to IR-01 confirms that DSMAG and EFG considered distribution voltage in the Nova Scotia Jurisdictional Benefit Cost Test but did not assign it a zero value. EFG notes that while DERs can impact voltage on distribution lines, NS Power evaluates these effects during interconnection processes. The analysis references EFG's Report and M12282.

E1 Responses to Synapse Energy Economics (Synapse) Information Requests NON-CONFIDENTIAL p. pp. 0-2
E1 Responses to Synapse Energy Economics (Synapse) Information Requests NON-CONFIDENTIAL alternatives, the potential impacts on distribution voltage at the system wide level were not easily quantified, and likely not material at this time....

AI summary E1 responds to Synapse's information requests, noting distribution voltage impacts are not material. EFG explains GHG cost calculations avoid double-counting by adjusting the social cost of carbon. References include M12282 and E1's Evidence page 33. Uncertainty remains around NS Power's avoided carbon costs.

Section 16 p. p. 8
, as reflected in the EFG Report and in discussions and presentations with the DSMAG was that relying on the gas commodity cost to represent gas system impacts was an appropriate and efficient method. Request IR-11: Refer to the EFG Report...

AI summary EFG recommends using proxy adders over a jurisdiction-specific study for estimating non-energy benefits in Nova Scotia's BCA test. Discussions with DSMAG confirmed this approach, with EFG sharing rationale and values in workshops. The EFG Report (page 17) supports proxy adders for host customer impacts.

E-8See new revised evidence submitted under E-14 (Evidence of P. Bowman, on behalf of IG) 19 passages
INTRODUCTION
INTRODUCTION - This Pre-filed Testimony has been prepared by Mr. Patrick Bowman of Bowman Economic Consulting Inc., - retained by the Industrial Group ("IG") of Nova Scotia. This testimony reviews and assesses the 2025 - EfficiencyOne ("E1...

AI summary Mr. Patrick Bowman of Bowman Economic Consulting Inc., retained by Nova Scotia's Industrial Group, prepares pre-filed testimony assessing Efficiency One's 2025 application to implement a new Benefit-Cost Analysis Test for Demand Side Management Plans. The application was filed with the Nova Scotia Energy Board on May 16, 2025. Bowman emphasizes his role as an independent, objective witness with extensive experience in utility regulation and energy efficiency since 1998.

TERMINOLOGY
TERMINOLOGY - In assessing DSM (both energy efficiency and strategic electrification), it is necessary to assess cost- - effectiveness, and to utilize a metric to compare benefits and costs. Broadly, this process is termed - Benefit-Cost A...

AI summary The document outlines the use of Benefit-Cost Analysis (BCA) in evaluating Demand Side Management (DSM), with Efficiency One (E1) proposing a Nova Scotia-specific Jurisdiction-Specific Test (JST) termed the Proposed BCA. This approach includes fixed items in benefits and costs, resembling the Societal Cost Test (SCT). BCA inputs are structured at varying levels from Measures/Activities to Programs/Portfolios.

BACKGROUND AND CONTEXT
BACKGROUND AND CONTEXT - This evidence relies on the following context for E1, and the broad understanding of the regulation of E1 - and the role of the Board. - E1 is the current franchise holder for development and delivery of DSM plans...

AI summary E1, the current franchise holder for DSM in Nova Scotia, requires Board approval for its DSM activities under the Public Utilities Act sections 79A to 79W. The Act distinguishes between DSM operations and purchase agreements with NSPI but treats both similarly in requiring Board approval. However, the legislation lacks explicit guidance on tests for 'reasonable availability' of DSM, focusing instead on cost-effectiveness.

Preamble
- directed to conduct a "thorough assessment of the relative merits of both the PAC test and a jurisdiction- - specific test" in order to "determine the optimal cost-effectiveness testing methodology for Nova Scotia." 5

AI summary The document directs a thorough assessment of the PAC test and a jurisdiction-specific test to determine the optimal cost-effectiveness testing methodology for Nova Scotia.

What is E1 proposing as a BCA?
What is E1 proposing as a BCA? - E1 has proposed that its current reliance on the Total Resource Cost ("TRC") screening test for cost- - effectiveness (and to a lesser degree, the Program Administrator Cost ("PAC") test) be replaced by a n...

AI summary E1 proposes replacing the Total Resource Cost (TRC) and Program Administrator Cost (PAC) tests with a new Benefit-Cost Analysis (BCA) tailored to Nova Scotia, incorporating societal impacts. The BCA would apply at the Portfolio level to assess public interest, with a 2% discount rate and proxy adders for non-energy benefits. E1 seeks Board approval for these changes.

EVALUATION OF E1'S PROPOSED BCA
EVALUATION OF E1'S PROPOSED BCA

AI summary The document evaluates Efficiency One's proposed Benefit-Cost Analysis (BCA) as part of a regulatory proceeding in Nova Scotia, focusing on energy efficiency programs and their alignment with jurisdiction-specific tests and societal cost considerations.

Why is E1 adopting the new Proposed BCA?
Why is E1 adopting the new Proposed BCA? - E1 indicates that the previous TRC does not show balance, in that participant costs are included in the - Costs component of the BCA, but the benefits (other than energy savings) received by the p...

AI summary E1 adopts the new Proposed BCA due to the previous TRC's imbalance, where participant costs are included in the Costs component but benefits (excluding energy savings) are omitted from Benefits. Legislative changes are cited as removing prior limitations that led to the unbalanced TRC test.

Is the E1 commentary a fair criticism of the TRC as previously applied in Nova Scotia?
Is the E1 commentary a fair criticism of the TRC as previously applied in Nova Scotia? - Yes, from a principled perspective. In general, BCA should include all measurable and meaningful benefits - and costs at the proposed assessment scale...

AI summary The E1 commentary criticizes the TRC for excluding non-energy benefits, but the NSUARB previously limited jurisdiction to energy impacts per M08888. The new Energy and Regulatory Boards Act may permit non-energy considerations, though legal interpretation is pending. Technical challenges remain in revising TRC to meet updated requirements.

Scotia?
Scotia? 2020 NSUARB 56 M08888, pdf page 2 of 19. - No. - First, although the legislation indicates that cost-effectiveness shall be measured at the portfolio level, - there is no prohibition against also assessing cost-effectiveness at oth...

AI summary The NSUARB must assess DSM cost-effectiveness at multiple granularity levels, not just portfolio level, to evaluate alternatives and ensure compliance with legislative requirements. E1's proposal fails to address mandatory customer interest assessments, including cost reduction, reliability, and availability, as previously interpreted by the Board.

Is the Proposed E1 BCA the only possible response to the criticism?
Is the Proposed E1 BCA the only possible response to the criticism? - No. From the outset, the assessment to be conducted was to consider two alternatives to the TRC – - either relying primarily on PAC, or developing a new Nova Scotia spec...

AI summary The Proposed E1 BCA is not the only response to criticism, as three alternatives exist: relying on PAC, developing a Nova Scotia-specific test, or adjusting TRC to include non-energy benefits. Legislative changes enabled the third approach. References include Public Utilities Act sections and a 2020 NSUARB board order.

1 For conversion of electric resistance heating to heat pumps (energy efficiency):
1 For conversion of electric resistance heating to heat pumps (energy efficiency): Proposed BCA (societal perspective) PAC (utility and its customers perspective) Benefits = NPV of avoided electric generation and Benefits: NPV of avoided e...

AI summary The document compares the societal benefits of converting electric resistance heating to heat pumps (avoided generation and transmission costs, health benefits, GHG reductions) with the costs (installation and program administration) from the utility and customer perspective. This analysis is part of a regulatory proceeding in Nova Scotia.

OTHER BCA CONSIDERATIONS
OTHER BCA CONSIDERATIONS - E1's Application relies on the National Standard Practice Manual for Benefit-Cost Analysis of - Distributed Energy Resources ("NSPM"), produced by the National Energy Screening Project. - Does E1 appropriately in...

AI summary The NSUARB found E1's BCA methodology inconsistent with the NSPM's principles, particularly Principle 1, which requires treating DERs as utility system resources. E1's approach uses non-standard discount rates and unbalanced plan design, potentially biasing resource investment decisions against residential and business interests.

Why is the E1 proposal on discount rates inconsistent with utility system resources?
Why is the E1 proposal on discount rates inconsistent with utility system resources? - In conducting Integrated Resource Planning ("IRP"), utilities typically compare alternative new energy - generation resources using their Weighted Avera...

AI summary The E1 proposal to use a 2% social discount rate for DSM evaluation conflicts with NSPM's requirement for consistent methods, as WACC is standard for utility IRP. Treasury Board guidance cited by E1 applies to regulatory proposals, not infrastructure investments. NSPM mandates equal footing for DSM with other resources using WACC, not lower social rates.

Why is E1's approach of using balanced plan design problematic?
Why is E1's approach of using balanced plan design problematic? - E1 indicates that in addition to cost-effectiveness, its proposals are designed to reflect balance, such as - equitable allocation of investment and savings between resident...

AI summary E1's balanced plan design prioritizes equity and access over cost-effectiveness, conflicting with NSPM Principle 1 and Nova Scotia IRP principles (safety, reliability, least cost, decarbonization, robustness). The NSPM allows balance criteria only with explicit policy, while utility resources are typically evaluated economically, not by equity. Examples like PPA allocation illustrate potential inequities in applying balance without policy mandates.

Should E1's proposal that BCA be conducted only at the Portfolio level be adopted?
Should E1's proposal that BCA be conducted only at the Portfolio level be adopted? - No. - Previous sections of this submission highlighted that the Board cannot fulfill its mandate if screening - information or tests are only applied at t...

AI summary The proposal to conduct BCA only at the Portfolio level is rejected, as it would hinder the Board's mandate by failing to identify problematic measures and prevent analysis of customer class cross-subsidization. Measure-level and customer class-level BCA are necessary for effective DSM program evaluation.

Is there any relevance to a Participant Cost Test?
Is there any relevance to a Participant Cost Test? - Yes. - E1 should be directed to provide information on the results of the PCT by measure (or comparable - measures, such as customer payback periods), to indicate whether E1 has proposed...

AI summary The Participant Cost Test (PCT) is relevant, requiring E1 to provide PCT results by measure or comparable metrics to ensure proposed incentives are reasonable and cost-effective for Demand Side Management (DSM) participation without being excessive.

Is there any relevance to measurements considering rate impacts, such as a RIM test?
Is there any relevance to measurements considering rate impacts, such as a RIM test? - A RIM test should not be applied as a screening test for energy efficiency, as it can derive excessively - narrow metrics and fail to measure proper cos...

AI summary The text argues against using RIM tests as a screening tool for energy efficiency due to their narrow metrics and inadequate cost-effectiveness measurement. However, it recommends that E1 continue reporting rate impacts at multiple granularities to enable the Board's assessment of customer impacts, including non-participants.

Are there other concerns with E1's BCA inputs?
Are there other concerns with E1's BCA inputs? - Yes. However, this concern may be more appropriately addressed as part of a specific DSM Plan review, - rather than a BCA review. - E1 has proposed to estimate the benefits of DSM measures u...

AI summary The analysis highlights three concerns with E1's BCA inputs: (1) using inflationary adders instead of evolving baseline conditions for avoided generation costs, (2) misrepresenting GHG emission impacts via average NSPI intensity, and (3) uncertainty about DSM's emission avoidance under fixed emission caps. These issues may require revisiting during DSM plan reviews.

What recommendations do you have?
What recommendations do you have? - Based on the above considerations, I provide the following conclusions and recommendations for the Board: - 1) The current primary TRC test is limited in its ability to singularly inform the Board about...

AI summary The text outlines recommendations for the Board regarding the use of benefit-cost analysis (BCA) tests in evaluating demand-side management (DSM) activities. It suggests using the PAC test as the primary energy efficiency test, incorporating the E1 BCA test for broader considerations, and rejecting the E1 Proposed BCA test as the primary test. It also emphasizes the need for cost-effective measures and proper consideration of avoided utility costs and GHG emissions.

E-9Evidence and Resume of Courtney Lane - Synapse 20 passages
BEFORE THE NOVA SCOTIA ENERGY BOARD p. p. 2
BEFORE THE NOVA SCOTIA ENERGY BOARD In the Matter of an Application by EfficiencyOne for Approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans (NSEB M12282) Evidence of Courtney Lane On Behalf of Counsel...

AI summary EfficiencyOne seeks approval for a new benefit-cost analysis test to evaluate demand side management plans. The proceeding, referenced as NSEB M12282, includes evidence presented by Courtney Lane on behalf of the Nova Scotia Energy Board's counsel.

II. SUMMARY OF CONCLUSIONS AND RECOMMENDATIONS p. pp. 2-4
II. SUMMARY OF CONCLUSIONS AND RECOMMENDATIONS - Q. Please describe your conclusions. - A. My conclusions are: - E1's approach to developing the Nova Scotia Test is reasonable and follows the sound economic guidance from the National Stand...

AI summary The Nova Scotia Test is deemed an improvement over the TRC test for incorporating energy policy goals, other fuels, societal impacts, and non-energy benefits. While proxy values for non-energy benefits are reasonable, E1's justification for specific proxy values is insufficient.

1 be based on a review of literature, proxy values used by other jurisdictions, and p. pp. 4-5
1 be based on a review of literature, proxy values used by other jurisdictions, and 2 should consider differences between jurisdictions. 3 Q. What are your recommendations? 4 A. Based on my conclusions, I offer the following recommendation...

AI summary The text discusses the recommendation to approve the Nova Scotia Test for use in the 2027–2031 DSM Plan, including modifications to NEB proxy adders and a process for updating them in 2029. It also references the current TRC test and its implementation in Nova Scotia, based on the Public Utilities Act.

Section 8 p. pp. 5-6
A. Evidence provided by Synapse on E1's 2023–2025 DSM Plan (M10473) recommended that the Board launch a process to develop a jurisdiction-specific cost-effectiveness test (JST) that reflects Nova Scotia's policy priorities using the NSPM....

AI summary Synapse recommended the Board develop a jurisdiction-specific cost-effectiveness test (JST) for Nova Scotia's DSM Plan, citing issues with the TRC test. E1 rebutted, suggesting a broader review of cost-effectiveness methodologies is needed due to legislative changes and advancements in demand response and electrification.

Section 9 p. pp. 6-7
es 6-12. 7 Rebuttal Evidence of E1 in M10473, June 10, 2022, page 13, lines 12-14. Id ., at page 13, lines 14-17. Evidence of Courtney Lane In its Decision on the 2023–2025 DSM Plan, the Board directed EI "to work with the DSMAG before the...

AI summary E1 complied with the Board's directive to develop an optimal DSM cost-effectiveness test by filing an application for a new BCA test in May 2025, informed by the DSMAG. The process involved seven meetings with an independent consultant, Energy Futures Group, using the NSPM to develop a BCA framework with five steps.

Preamble p. pp. 7-9
A. The NSPM was developed by the National Energy Screening Project (NESP), an organization working to improve cost-effectiveness screening practices for DERs, [13](#page-9-0) to help guide the development of a jurisdiction's cost-effective...

AI summary The NSPM, developed by the National Energy Screening Project, provides guidance on cost-effectiveness screening for DERs. It introduces the Jurisdictional-Cost Test (JST), which aligns with each jurisdiction's policy goals and allows for modifications over time, addressing issues with traditional tests that are static and may not account for public health or GHG emissions.

Q. Why is it appropriate for Nova Scotia to use the NSPM process? p. pp. 9-10
Q. Why is it appropriate for Nova Scotia to use the NSPM process? A. The NSPM provides a set of principles and steps to support jurisdictions with the review and modification of an existing cost-effectiveness test or the development of a n...

AI summary Nova Scotia uses the NSPM process to align with the Board's directive to review or develop cost-effectiveness tests. Recent policy changes, such as amendments to the Public Utilities Act expanding demand-side management, necessitate this approach. The NSPM provides structured principles for jurisdictions to evaluate cost-effectiveness, as referenced in Board Decision M10473.

Evidence of Courtney Lane p. pp. 10-11
Evidence of Courtney Lane 1 20 programs, and the Energy Reform Act that broadens what the Board should consider 2 when it makes regulatory decisions and establishes the Energy and Regulatory Boards 3 21 Act and the More Access to Energy Ac...

AI summary Courtney Lane discusses the use of the Nova Scotia Policy Model (NSPM) in other jurisdictions, noting that 12 U.S. states and the District of Columbia have adopted it for DER cost-effectiveness tests. She also states that no Canadian provinces have used the NSPM for BCA tests, but sees no reason why they should not. The NSPM is described as objective, policy-neutral, and economically sound.

Q. If an impact is not applicable or not material, should it be excluded from the Nova Scotia Test? p. pp. 12-14
Q. If an impact is not applicable or not material, should it be excluded from the Nova Scotia Test? A. No, it should not. It is important to distinguish between the definition of the BCA test and the application of the test. All utility sy...

AI summary The Nova Scotia Energy Board (NSEB) asserts that impacts should not be excluded from the Nova Scotia Test even if not applicable or material. The distinction between the BCA test's definition and its application is critical, ensuring all relevant impacts are included for policy goals while allowing exclusion in specific DER cases. This approach supports transparency and consistency in cost-effectiveness evaluations.

Q. How will the Nova Scotia Test be used to determine cost-effectiveness? p. p. 14
Q. How will the Nova Scotia Test be used to determine cost-effectiveness? - A. As was done in the prior DSM Plans, E1 will conduct the BCA at the measure, program - component, program, resource, and portfolio (i.e., Plan) levels and will m...

AI summary The Nova Scotia Test will evaluate DSM Plans' cost-effectiveness at the portfolio (Plan) level, per the November 9, 2022, Public Utilities Act amendment. E1 will conduct BCA analyses at multiple levels, but the Board's evaluation focus has shifted from program to portfolio level.

Q. What is your overall assessment of the proposed Nova Scotia Test? p. p. 18
Q. What is your overall assessment of the proposed Nova Scotia Test? - A. I find that the proposed Nova Scotia Test is an improvement upon the current TRC test. - Unlike the current TRC test, the Nova Scotia Test accounts for both host cus...

AI summary The proposed Nova Scotia Test is considered an improvement over the current TRC test as it accounts for host customer benefits and costs, ensuring proper valuation of DERs and avoiding biased BCA results. It aligns with Nova Scotia's energy policy goals by incorporating non-energy impacts as directed by recent legislation.

Review of Policy Developments Impacting Host Customer NEBs p. p. 22
Review of Policy Developments Impacting Host Customer NEBs

AI summary The document reviews policy developments affecting Host Customer NEBs, focusing on regulatory frameworks, cost methodologies, and energy management practices in Nova Scotia. Key considerations include DSM, WACC, and GHG regulations, with references to national standards and cost tests.

Q. Did the DSMAG previously investigate NEBs? p. p. 22
Q. Did the DSMAG previously investigate NEBs? - A. Yes. As part of the Settlement Agreement in the 2016–2018 DSM Plan, the parties to the settlement agreed to work with the DSMAG "to pursue the nature and quantification of estimates associ...

AI summary The DSMAG investigated non-energy benefits (NEBs) as part of the 2016–2018 DSM Plan, with E1 retaining VEIC to develop NEB values. In 2020, the Board ruled it lacked jurisdiction to consider NEBs in cost-effectiveness testing under the Public Utilities Act.

Nova Scotia Utility Board, Decision in M0888, April 15, 2020, paragraph 49. p. pp. 22-23
Nova Scotia Utility Board, Decision in M0888, April 15, 2020, paragraph 49. 1 benefits and an array of environmental benefits with the definition of electricity 2 44 efficiency and conservation activities in the Public Utilities Act. Speci...

AI summary The Nova Scotia Utility Board discusses the reevaluation of cost-effectiveness criteria, incorporating environmental and non-energy benefits, based on recent legislative changes such as the Energy Reform Act and the Environmental Goals and Climate Change Reduction Act. This reevaluation aims to align rate-setting with broader policy goals, including sustainability and market competition.

Evidence of Courtney Lane p. pp. 23-26
Evidence of Courtney Lane states that the long-term objective of the Government is to achieve sustainable prosperity, which includes supporting "the well-being and quality of life for all Nova Scotians" and working towards "continues impro...

AI summary Courtney Lane argues the Nova Scotia Energy Board (NSEB) should reconsider its authority to include Non-Energy Benefits (NEBs) in cost-effectiveness screening. E1 proposes quantifying NEBs like asset value, productivity, and health using proxy adders from EFG. The analysis references the Environmental Goals and Climate Change Reduction Act (SNS 2021, c 20) and cites matter M12282.

Section 44 p. pp. 28-29
in Table 4 are already within that range and can be approved without modification. Should E1 want to include the higher NEB values, it should provide justification in its upcoming 2027-2031 DSM Plan. Sutter, M., J. Mitchell-Jackson, S. Sch...

AI summary The document states that values in Table 4 are within an approved range and can be accepted without changes. However, if E1 wishes to use higher NEB values, it must justify this in its 2027-2031 DSM Plan. References to studies on non-energy benefits and cost-benefit analyses are provided.

1 I further recommend that the Board direct E1 to launch a process for updating the NEB p. pp. 29-31
1 I further recommend that the Board direct E1 to launch a process for updating the NEB 2 proxies in 2029 for use in the next DSM Plan. 3 4 Q. Should the Board choose not to adopt the use of host customer NEBs, is there an alternative appr...

AI summary The text discusses the recommendation to update the Non-Energy Benefits (NEB) proxies in 2029 for the next DSM Plan. It also explores the impact of excluding host customer costs and benefits from Benefit-Cost Analysis (BCA) for DERs such as solar PV and EVs, highlighting the need for a comprehensive cost-effectiveness test that includes host customer impacts.

PROFESSIONAL EXPERIENCE p. p. 33
PROFESSIONAL EXPERIENCE Synapse Energy Economics, Inc. , Cambridge, MA. Senior Principal , August 2024 – Present, Principal Associate , September 2022 – August 2024, Senior Associate, November 2019 – September 2022. Provides consulting and...

AI summary The individual's professional experience spans energy consulting, policy analysis, and regulatory work, focusing on demand-side management, energy efficiency, distributed energy resources, and performance-based regulation. Roles include senior positions at Synapse Energy Economics, National Grid, and advocacy groups, with expertise in benefit-cost assessment, program evaluation, and stakeholder engagement in energy initiatives.

PUBLICATIONS p. p. 33
PUBLICATIONS Woolf, T., M. Whited, C. Lane. 2025. Identifying and Accounting for Transfers in Benefit‐Cost Analysis of Distributed Energy Resources . Synapse Energy Economics for the National Energy Screening Project. Fortman, N., J. Micha...

AI summary The document lists publications related to benefit-cost analysis (BCA) of distributed energy resources (DERs), energy efficiency programs, and clean vehicle policies. Key contributors include Synapse Energy Economics, the National Energy Screening Project (NESP), and E4TheFuture. Topics span equity in DERs, rate impacts, and macroeconomic clean energy scenarios.

TESTIMONY p. p. 33
y for Authority to Implement a Multiyear Rate Plan for Electric Distribution Service in the District of Columbia. On behalf of the District of Columbia Government. January 12, 2024 and April 22, 2024. Maryland Public Service Commission (Ca...

AI summary Testimonies by Courtney Lane in multiple regulatory cases across Maryland, New Hampshire, and the District of Columbia regarding electric vehicle programs, cost recovery, and benefit-cost analysis for utility rate plans. Testimonies were provided on behalf of the Maryland Office of People's Counsel and the Office of Consumer Advocate in cases involving Potomac Electric Power Company, Liberty Utilities, and Baltimore Gas and Electric Company.

E-10Evidence of F. Wyatt - CA 2 passages
BEFORE THE NOVA SCOTIA ENERGY BOARD p. p. 2
BEFORE THE NOVA SCOTIA ENERGY BOARD An Application by EfficiencyOne for Approval of a New Benefit-Cost Analysis : : : Test for Evaluating Demand Side Management (DSM) Plans : Matter No. M12282 : : : DIRECT TESTIMONY OF FRANCIS WYATT GREEN...

AI summary EfficiencyOne applied for approval of a new benefit-cost analysis for evaluating Demand Side Management (DSM) plans in Matter No. M12282. Francis Wyatt of Green Energy Economics Group testified on behalf of the Consumer Advocate during the proceeding on July 17, 2025.

2 Q. PLEASE SUMMARIZE YOUR KEY FINDINGS AND OBSERVATIONS p. p. 7
2 Q. PLEASE SUMMARIZE YOUR KEY FINDINGS AND OBSERVATIONS - 3 A. In summary, I respectfully recommend that the Board should: - 4 1) Approve the proposed new benefit cost test as the primary cost-effectiveness test 5 for Nova Scotia. - 6 2)...

AI summary The expert recommends approving a new benefit-cost test as Nova Scotia's primary cost-effectiveness metric, incorporating externalized carbon costs while retaining internalized carbon calculations for secondary tests. Continued stakeholder engagement in refining the test is also advised.

E-10-(i)Resume of Francis Wyatt 10 passages
Professional Experience p. p. 0
Professional Experience December 2005 – Present Co-Founder, Green Energy Economics Group, Inc ., Cuttingsville, VT. Consultancy specializing in energy-efficiency and renewable resource portfolios investing in electricity and gas savings, c...

AI summary The individual's professional experience spans energy efficiency, renewable resources, and civil engineering. They co-founded Green Energy Economics Group, Inc., developed cost-effectiveness models for demand-side management, and worked on energy-saving analyses. Previous roles include Senior Analyst at Optimal Energy, Inc., and civil engineering positions at Enman Engineering and Nowlan Engineering. Their work includes utility regulatory proceedings and program planning.

Ontario p. p. 0
Ontario Ontario Energy Board Served on the Stakeholder Advisory Group (SAG): provided expert advice on efficiency program design and potential study analysis. 2023 - 2024. Small Business Utility Alliance Reviewed Enbridge DSM plan and part...

AI summary The Ontario Energy Board served the Stakeholder Advisory Group (SAG) on efficiency program design (2023-2024). The Small Business Utility Alliance reviewed Enbridge's DSM plan, participated in a litigated proceeding (Matter No. EB-2021-0002, 2021-2022), and testified on program design, cost effectiveness, and stakeholder engagement.

Vermont p. p. 0
Vermont - Reviewed and analyzed program proposals for the Community Energy & Efficiency Development Fund (CEED Fund), including the development of scoring and rebalancing mechanisms and reviewing and revising cost-effectiveness analyses fo...

AI summary Activities include analyzing the Community Energy & Efficiency Development Fund (CEED Fund) proposals, developing cost-effectiveness models for energy efficiency programs, supporting Efficiency Vermont's operations, and assisting Vermont Gas Systems' transition. Work spans 2000–2017, focusing on energy efficiency, reliability gap assessments, and technical tool development for utilities in Vermont.

Pennsylvania p. p. 0
Pennsylvania Program design, implementation planning, regulatory support, technical reference manual development and portfolio cost-effectiveness tool for Columbia Gas of Pennsylvania. Assisted - with testimony before the Pennsylvania Publ...

AI summary Activities include program design, regulatory support, and testimony preparation for energy companies in Pennsylvania before the PUC. Involves Columbia Gas, Philadelphia Gas Works, UGI Gas, and Peoples Natural Gas, with multiple docket numbers spanning 2006–2022. Focuses on energy efficiency, cost-effectiveness analysis, and portfolio design.

Wisconsin p. p. 0
Wisconsin Portfolio and project cost-effectiveness calculator development. Cost-effectiveness analysis, assistance with contractor selection and regulatory support for 3-year energy-efficiency portfolio for Focus on Energy in Wisconsin. Ju...

AI summary A 3-year energy-efficiency portfolio project for Focus on Energy in Wisconsin (2011–2013) involved developing a cost-effectiveness calculator, conducting analyses, supporting contractor selection, and providing regulatory assistance.

Louisiana p. p. 0
Louisiana Empirical costs projections and cost-effectiveness analysis of alternative energy-efficiency resource acquisition scenarios for Entergy New Orleans, prepared for the Alliance for Affordable Energy and submitted as comments to the...

AI summary Empirical cost projections and cost-effectiveness analysis of energy-efficiency resource acquisition scenarios for Entergy New Orleans were prepared by the Alliance for Affordable Energy and submitted to the City Council in April-May 2013 as part of a regulatory proceeding.

District of Columbia p. p. 0
District of Columbia Developed multi-measure cost-effectiveness screening tool for the District of Columbia Sustainable Energy Utility, as a subcontractor to Vermont Energy Investment Corporation. November 2011 – 2014.

AI summary A multi-measure cost-effectiveness screening tool was developed for the District of Columbia Sustainable Energy Utility by Vermont Energy Investment Corporation as a subcontractor between November 2011 and 2014.

Illinois p. p. 0
Illinois Portfolio and project cost-effectiveness calculator development. Cost-effectiveness analysis, assistance with contractor selection and regulatory support for 3-year energy-efficiency portfolio for Peoples Gas in Illinois. Septembe...

AI summary Development of a cost-effectiveness calculator for Peoples Gas Illinois' 3-year energy-efficiency portfolio (2008-2012), including analysis, contractor selection support, and regulatory assistance.

People's Republic of China p. p. 0
People's Republic of China - Developed portfolio and project economic and financial analysis tools for use in China, and provided remote and in-person training sessions on use. For Natural Resources Defense Council and Institute for Sustai...

AI summary The text details work on energy efficiency projects in China, including economic analysis tools for the Natural Resources Defense Council, efficiency retrofits for Guangdong's Economic and Trade Commission, and prefeasibility studies for an Asian Development Bank loan. Projects involved Jiangsu province, Shanghai municipality, and Efficiency Power Plant assessments.

PRIOR ASSIGNMENTS (RESOURCE INSIGHT) – 1992-1996 p. p. 0
PRIOR ASSIGNMENTS (RESOURCE INSIGHT) – 1992-1996 - Technical assistance on DSM program development in the Potomac Electric Power Company collaborative, for the Maryland Office of People's Counsel. Work included characterizing new energy-ef...

AI summary The text details technical contributions to DSM program development (1992–1996), including cost-effectiveness analysis, program design, and regulatory support. Key activities involve commercial/industrial energy efficiency measures, IRP reviews, and stakeholder negotiations. Entities include utilities, regulatory bodies, and environmental organizations.

E-11Evidence of Eastward Energy 5 passages
NOVA SCOTIA ENERGY BOARD p. p. 1
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act, RSNS 1989, c. 380 as amended - and - IN THE MATTER OF: An Application by EfficiencyOne for Approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Managem...

AI summary The Nova Scotia Energy Board is handling a proceeding under the Public Utilities Act, 1989, regarding EfficiencyOne's application for approval of a new benefit-cost analysis test to evaluate Demand Side Management (DSM) plans. The matter is designated as M12282.

Participation in the DSMAG p. pp. 1-3
Participation in the DSMAG In response to Eastward's IR-03 E1 stated three specific reasons why in its view Eastward's participation in the Demand Side Management Advisory Group ("DSMAG") is not suitable. Eastward wishes to address each of...

AI summary Eastward challenges E1's claim that its participation in the DSMAG is unsuitable due to potential conflicts, arguing that NSPI's existing membership (a fossil fuel provider) creates a greater conflict. Eastward also highlights its interest in strategic electrification and the BCA test for cost-effectiveness analysis.

Reliability Impacts p. pp. 5-6
Reliability Impacts In response to Eastward's IR-08(e), E1 stated that " reliability impacts are assumed to be embedded in the avoided cost values provided by NS Power " , and in response to Eastward's IR-08(d) EFG stated that " [t]he valu...

AI summary Eastward challenges the assumption that reliability impacts are embedded in NS Power's avoided cost values, urging confirmation. E1 and EFG assert these impacts are already accounted for. Eastward highlights grid reliability risks from electrification and severe weather, citing examples from Canada. Natural gas system reliability is emphasized, with 99.99998% reliability noted for Eastward's system.

• Natural Gas to Electric Conversions p. p. 7
• Natural Gas to Electric Conversions o Based on the illustrative example provided by EFG, Eastward does not believe that the conversion of gas heating systems to electric heat pumps should be considered as strategic electrification, as it...

AI summary Eastward argues that converting gas heating systems to electric heat pumps should not be considered strategic electrification, citing a negative net benefit of $17.4 million and a benefit cost ratio of 0.45 based on EFG's illustrative example.

• Reliability Impacts p. p. 7
• Reliability Impacts - o Eastward is concerned that peak cost and system reliability impacts are only assumed to be reflected in NSPI's avoided cost values, and believes this should be confirmed with a clear explanation of how those costs...

AI summary Eastward argues that NSPI's avoided cost values may not fully capture peak cost and reliability impacts, requiring clarification. E1's BCA test should account for natural gas reliability losses. Eastward supports Posterity Group's evidence submission.

E-12Evidence of Posterity Group Consulting, on behalf of Eastward Energy 4 passages
NOVA SCOTIA ENERGY BOARD p. p. 1
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act, RSNS 1989, c. 380 as amended - and - IN THE MATTER OF: An Application by EfficiencyOne for Approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Managem...

AI summary The Nova Scotia Energy Board is considering EfficiencyOne's application for approval of a new benefit-cost analysis test to evaluate demand side management (DSM) plans under the Public Utilities Act. The proceeding is designated as Matter M12282.

Introduction p. p. 1
Introduction - Posterity Group was retained by Eastward Energy to review EfficiencyOne's (E1) Application for - Approval of a New Benefit-Cost Analysis (BCA) Test for Evaluating Demand Side Management - (DSM) Plans and make potential recom...

AI summary Posterity Group was retained by Eastward Energy to evaluate EfficiencyOne's application for a new Benefit-Cost Analysis (BCA) Test for Demand Side Management (DSM) Plans. Posterity Group specializes in energy use analysis, climate change, and decarbonization consulting, providing evidence-based recommendations for energy decisions.

Benefits of Hybrid Heating p. pp. 2-3
r this same timeframe." The Study concludes that "there are opportunities for solutions to managing the energy transition through the operation of an integrated gas and electric system."[6](#page-2-4) - Posterity Group has prepared two qua...

AI summary Posterity Group's study demonstrates hybrid heating systems (natural gas furnace + electric heat pump) yield significant net benefits under BCA tests. Replacing electric resistance heaters shows 4.10–4.53x cost benefits, while replacing fuel oil furnaces shows 2.21–2.27x benefits. Hybrid systems reduce electricity demand and offset generation needs from oil-to-hybrid transitions, with BCA results favoring hybrid systems over E1's electrification examples.

1 Table 1: Illustrative Example - Hybrid System Replacing Electric Resistance Heating p. pp. 3-4
1 Table 1: Illustrative Example - Hybrid System Replacing Electric Resistance Heating Category Impact Basis for Estimation Hybrid Replacing Electric Resistance Baseboard Heaters (E1 Costs) Hybrid Replacing Electric Resistance Baseboard Hea...

AI summary Table 1 compares costs and benefits of hybrid systems replacing electric resistance heating in Nova Scotia. It includes avoided costs, environmental compliance, financial incentives, and other factors. EfficiencyOne (E1) and Nova Scotia Power (NSP) are key entities, with calculations involving energy generation, transmission, and distribution impacts. The Benefit-Cost Analysis (BCA) highlights a 4.10 ratio for E1 costs and 4.53 for E3 costs.

E-13Evidence of M. Whitten - SBA 6 passages
III. OBSERVATIONS AND RECOMMENDATIONS p. pp. 4-6
III. OBSERVATIONS AND RECOMMENDATIONS - Q. Please summarize your observations regarding the Application. - A. After reviewing the Application I have the following observations: - The proposed BCA test framework relies on proxy values for c...

AI summary The reviewer observes that the proposed BCA test framework depends on proxy values for non-energy benefits due to insufficient information from E1 to quantify them directly.

5 IV. NEED FOR A NEW BENEFITS-COST ANALYSIS (BCA) TEST p. pp. 6-8
5 IV. NEED FOR A NEW BENEFITS-COST ANALYSIS (BCA) TEST

AI summary The document discusses the need for a new Benefits-Cost Analysis (BCA) test in regulatory proceedings, highlighting potential gaps in current methodologies and the necessity for updated evaluation frameworks.

6 Q. Why did Efficiency One (E1) submit this Application at this time? p. p. 8
6 Q. Why did Efficiency One (E1) submit this Application at this time? - 7 A. E1 submitted this Application in response to a directive in the 2022 Decision issued by the 8 NSUARB that directed E1 to develop an optimal cost-effectiveness te...

AI summary Efficiency One (E1) submitted an application to the NSEB to replace the total resource cost (TRC) test with a benefit-cost analysis (BCA) test for assessing future DSM plans, citing changes in Nova Scotia legislation and regulations since the NSUARB's 2022 directive.

values? p. p. 10
values? A. E1's consultant EFG produced a report that is included as Appendix B to E1's Application. In its report, EFG provided a table listing nine host customer non-energy impacts that could be included in the BCA test, represented by p...

AI summary E1's consultant EFG prepared a report (Appendix B) listing nine non-energy impacts for the BCA test, from which E1 selected six. The selected impacts are detailed in a table from Table 8 of the Application.

- non-energy benefits like empowerment and pride. While our concerns were p. pp. 11-12
- non-energy benefits like empowerment and pride. While our concerns were M12282, Exhibit E-1, Application, page 5 at paragraph 24. 1 acknowledged, I do not feel that they were addressed in the Application. EFG included the 2 following in...

AI summary The stakeholder process revealed a lack of clarity regarding the current cost effectiveness test, with working group members unable to reach consensus on several impacts. Appendix B summarizes the review of the BCA test and its scope.

Q. Did you find this summary of the stakeholder process addresses your concerns? p. p. 12
Q. Did you find this summary of the stakeholder process addresses your concerns? A. No, it does not satisfy Daymark's concerns expressed above, or at the stakeholder sessions mentioned in the EFG report in Appendix B, because it simply sid...

AI summary Daymark asserts that the stakeholder process summary fails to address concerns about quantifying non-utility benefits through third-party measurement and verification, as raised during stakeholder sessions referenced in the EFG report (Appendix B).

E-13-(i)Resume of Melissa Whitten 1 passage
TOPICS OF INTEREST p. p. 0
TOPICS OF INTEREST Resource procurement, short & long term purchase agreements for both electric & natural gas commodity, transmission, distribution, storage. Wholesale and retail market design and analysis, BTM resources. Natural gas mark...

AI summary The document outlines key topics including resource procurement, market design for electricity and natural gas, economic analysis, FERC policy issues, battery storage, integrated resource planning, and infrastructure replacement programs. It emphasizes both short-term and long-term procurement strategies, renewable fuels, and regulatory considerations.

E-14Evidence of P. Bowman, on behalf of IG - Revised (Old evidence filed under E-8) 16 passages
PRE-FILED TESTIMONY OF PATRICK BOWMAN IN REGARD TO EFFICIENCY ONE ("E1") BENEFIT-COST ANALYSIS TEST ("BCA")
PRE-FILED TESTIMONY OF PATRICK BOWMAN IN REGARD TO EFFICIENCY ONE ("E1") BENEFIT-COST ANALYSIS TEST ("BCA") Submitted to: The Nova Scotia Energy Board on behalf of The Industrial Group Prepared by: Bowman Economic Consulting Inc. 161 Rue H...

AI summary Patrick Bowman of Bowman Economic Consulting Inc. submitted a pre-filed testimony to the Nova Scotia Energy Board on behalf of The Industrial Group regarding the Efficiency One (E1) Benefit-Cost Analysis (BCA) test. The document outlines the submission's context, including the preparer and revision date.

INTRODUCTION
INTRODUCTION - This Pre-filed Testimony has been prepared by Mr. Patrick Bowman of Bowman Economic Consulting Inc., - retained by the Industrial Group ("IG") of Nova Scotia. This testimony reviews and assesses the 2025 - EfficiencyOne ("E1...

AI summary Mr. Patrick Bowman of Bowman Economic Consulting Inc., retained by Nova Scotia's Industrial Group, provides pre-filed testimony assessing Efficiency One's 2025 Application to implement a new Benefit-Cost Analysis Test for Demand Side Management Plans. The Application was filed with the Nova Scotia Energy Board on May 16, 2025. Bowman emphasizes his role as an independent, objective witness with extensive experience in utility regulation and energy efficiency.

TERMINOLOGY
TERMINOLOGY - In assessing DSM (both energy efficiency and strategic electrification), it is necessary to assess cost- - effectiveness, and to utilize a metric to compare benefits and costs. Broadly, this process is termed - Benefit-Cost A...

AI summary The document outlines the use of Benefit-Cost Analysis (BCA) in evaluating Demand Side Management (DSM) initiatives, emphasizing the Jurisdiction-Specific Test (JST) as a regulatory framework. E1 proposes a Nova Scotia-specific BCA, termed the 'Proposed BCA,' which incorporates fixed items in benefit and cost calculations. This approach is compared to the Societal Cost Test (SCT) and involves hierarchical categorization of DSM measures into programs and portfolios.

BACKGROUND AND CONTEXT
BACKGROUND AND CONTEXT - This evidence relies on the following context for E1, and the broad understanding of the regulation of E1 - and the role of the Board. - E1 is the current franchise holder for development and delivery of DSM plans...

AI summary E1, the current DSM franchise holder in Nova Scotia, requires Board approval for DSM activities under the Public Utilities Act sections 79A to 79M. The Act links DSM operations and purchase agreements with NSPI, requiring Board review. However, legislative guidance on 'reasonable availability' tests is absent, focusing only on cost-effectiveness within availability constraints.

Preamble
- directed to conduct a "thorough assessment of the relative merits of both the PAC test and a jurisdiction- - specific test" in order to "determine the optimal cost-effectiveness testing methodology for Nova Scotia.["](#page 1-6) 5

AI summary The document directs a thorough assessment of the PAC test and a jurisdiction-specific test to determine the optimal cost-effectiveness testing methodology for Nova Scotia.

What is E1 proposing as a BCA?
What is E1 proposing as a BCA? - E1 has proposed that its current reliance on the Total Resource Cost ("TRC") screening test for cost- - effectiveness (and to a lesser degree, the Program Administrator Cost ("PAC") test) be replaced by a n...

AI summary E1 proposes replacing Nova Scotia's current TRC and PAC tests with a new BCA that evaluates total societal impacts, aligning with policy objectives. The BCA would assess portfolios for public interest and seek approval for a 2% discount rate and proxy adders for non-energy benefits. E1 also requests board direction on these proposals.

EVALUATION OF E1'S PROPOSED BCA
EVALUATION OF E1'S PROPOSED BCA

AI summary The evaluation of E1's proposed Benefit-Cost Analysis (BCA) is being reviewed by the NSUARB, considering its alignment with the Societal Cost Test (SCT) and Jurisdiction-Specific Test (JST). Key focus areas include demand-side management (DSM) effectiveness, program administrator costs (PAC), and total resource costs (TRC).

Why is E1 adopting the new Proposed BCA?
Why is E1 adopting the new Proposed BCA? - E1 indicates that the previous TRC does not show balance, in that participant costs are included in the - Costs component of the BCA, but the benefits (other than energy savings) received by the p...

AI summary E1 is adopting the new Proposed BCA because the previous TRC test does not balance participant costs and benefits, and legislative changes have removed prior limitations. The NSUARB previously imposed an unbalanced TRC test.

Is the E1 commentary a fair criticism of the TRC as previously applied in Nova Scotia?
Is the E1 commentary a fair criticism of the TRC as previously applied in Nova Scotia? - Yes, from a principled perspective. In general, BCA should include all measurable and meaningful benefits - and costs at the proposed assessment scale...

AI summary The E1 commentary is considered a fair criticism of the TRC in Nova Scotia for excluding non-energy benefits. However, prior TRC application was restricted by M08888, which limited the Board’s jurisdiction. The new Energy and Regulatory Boards Act may permit non-energy considerations, though legal interpretation is pending. Technical challenges remain in revising the TRC test if jurisdiction expands.

Does E1 appear to accurately portray the economic and policy framework for DSM in Nova
Does E1 appear to accurately portray the economic and policy framework for DSM in Nova Scotia? 2020 NSUARB 56 M08888, pdf page 2 of 19. - No. - First, although the legislation indicates that cost-effectiveness shall be measured at the port...

AI summary The document states E1 does not accurately portray the DSM framework in Nova Scotia. The NSUARB must assess cost-effectiveness at granular levels beyond the portfolio level to meet legislative requirements, including evaluating alternative DSM plans. E1's proposal fails to address customer interests, which the Board mandates as central to DSM assessments.

Is the Proposed E1 BCA the only possible response to the criticism?
Is the Proposed E1 BCA the only possible response to the criticism? - No. From the outset, the assessment to be conducted was to consider two alternatives to the TRC – - either relying primarily on PAC, or developing a new Nova Scotia spec...

AI summary The Proposed E1 BCA is not the only response to criticism. Alternatives include using PAC, developing a new test, or adjusting TRC to balance non-energy benefits. Legislative changes enabled a third approach. Cited sections of the Public Utilities Act and a 2020 NSUARB order (M08888) are referenced.

OTHER BCA CONSIDERATIONS
OTHER BCA CONSIDERATIONS - E1's Application relies on the National Standard Practice Manual for Benefit-Cost Analysis of - Distributed Energy Resources ("NSPM"), produced by the National Energy Screening Project. - Does E1 appropriately in...

AI summary E1's Benefit-Cost Analysis (BCA) approach is criticized for violating Principle 1 of the National Standard Practice Manual (NSPM) for DERs, which mandates treating DERs as utility system resources and comparing them with other resources using consistent methods. The NSUARB argues E1's BCA uses inconsistent inputs like discount rates and unbalanced plan design.

Why is E1's approach of using balanced plan design problematic?
Why is E1's approach of using balanced plan design problematic? - E1 indicates that in addition to cost-effectiveness, its proposals are designed to reflect balance, such as - equitable allocation of investment and savings between resident...

AI summary E1's balanced plan design approach is criticized for prioritizing equity and access over cost-effectiveness, conflicting with NSPM Principle 1. The NSPM emphasizes cost-effectiveness as the primary DSM test unless explicitly mandated by policy. Nova Scotia's IRP principles (safety, reliability, least cost, decarbonization, robustness) are highlighted as the foundation for resource planning, with balance not typically justified in rate-funded DSM programs.

Should E1's proposal that BCA be conducted only at the Portfolio level be adopted?
Should E1's proposal that BCA be conducted only at the Portfolio level be adopted? - No. - Previous sections of this submission highlighted that the Board cannot fulfill its mandate if screening - information or tests are only applied at t...

AI summary The submission argues against E1's proposal to conduct BCA only at the Portfolio level, stating it would prevent identifying outliers and hinder the Board's mandate. It emphasizes the need for customer-class-level analysis to address cross-subsidization and align with NSPM guidelines. Current DSM cost recovery methods also require class-specific cost assessments.

Are there other concerns with E1's BCA inputs?
Are there other concerns with E1's BCA inputs? - Yes. However, this concern may be more appropriately addressed as part of a specific DSM Plan review, - rather than a BCA review. - E1 has proposed to estimate the benefits of DSM measures u...

AI summary Concerns exist with E1's BCA inputs, particularly its use of inflation-adjusted long-term avoided generation costs and average GHG intensity metrics. These approaches may not align with utility planning standards or Treasury Board guidelines, as they fail to account for evolving baseline conditions, incremental GHG impacts, and fixed emission caps. The analysis should inform future DSM plan justifications.

SUMMARY
SUMMARY

AI summary The document outlines a regulatory proceeding in Nova Scotia involving efficiency programs, cost tests, and stakeholder analyses. Key entities include Nova Scotia Power Inc. (NSPI) and the Nova Scotia Utility and Regulatory Board (NSUARB). The discussion centers on Benefit-Cost Analysis (BCA), Demand Side Management (DSM), and tests like the Societal Cost Test (SCT) and Jurisdiction-Specific Test (JST).

E-15Letters of Comment 8 passages
Preamble p. pp. 0-1
Nova Scotia Energy Board Clerk of the Board P.O. Box 1692, Unit "M" Halifax, N.S. B3J 3S3 [email protected] Re: An application by EfficiencyOne for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management (DSM)...

AI summary Efficiency Canada submits comments on EfficiencyOne's application for a new benefit-cost analysis test for DSM plans in Nova Scotia. The submission highlights their role as national policy analysts, ongoing review of Canadian energy efficiency policies, and preliminary findings. Authors include Brendan Haley, Carol Maas, and Katharine Turner, with ties to Nova Scotia energy policy and EfficiencyOne.

Comparing Canadian cost-effectiveness screening practices p. p. 1
Comparing Canadian cost-effectiveness screening practices Across Canada, we have seen a move away from a narrowly defined Total Resource Cost test as the primary screening test. The implementation of this test is often unbalanced because i...

AI summary This text discusses the shift in Canadian cost-effectiveness screening practices, moving away from the Total Resource Cost test to more balanced approaches that consider both customer and societal benefits, including the use of program administrator cost tests.

Utility/program administrator Primary cost effectiveness test Benefit adders and/or consideration of non-energy benefits p. p. 1
Utility/program administrator Primary cost effectiveness test Benefit adders and/or consideration of non-energy benefits BC Hydro PAC Pre-2023 policy included a 15% benefit adder to the TRC FortisBC Energy (natural gas) FortisBC Inc. (elec...

AI summary The table outlines primary cost-effectiveness tests and benefit adders for various utility and program administrators. It includes entities like BC Hydro, FortisBC Energy, and Efficiency Manitoba, with details on their respective policies and adders to the Total Resource Cost (TRC).

The multiple benefits of energy efficiency p. pp. 3-4
The multiple benefits of energy efficiency The International Energy Agency has highlighted that energy efficiency improvements produce multiple benefits for customers, society, and the environment.4 It does not make sense to have a cost-ef...

AI summary Energy efficiency offers multifaceted benefits, including non-financial advantages for customers and society. Nova Scotia's cost-effectiveness tests must account for these benefits, not just customer costs. E1's framework is praised for focusing on specific benefits, allowing alignment with policy goals. Low-income households and resilience are highlighted as priority areas, with recommendations to adjust benefit quantification as technologies evolve.

Avoided costs p. pp. 5-6
Avoided costs Utility system avoided costs will remain one of the most material benefits of energy efficiency programs. Across jurisdictions, these avoided costs are often not transparent and misaligned with forward-looking utility system...

AI summary Avoided costs from energy efficiency programs are critical but often lack transparency and alignment with future utility risks. The Independent Electricity System Operator's (IESO) approach to calculating avoided costs could improve accuracy, with recommendations for technical review committees to ensure stakeholder accountability.

Strategic or unstrategic electrification? p. pp. 6-7
Strategic or unstrategic electrification? A renewed cost-effectiveness test is particularly important for Nova Scotia to make sound decisions about managing electrification. The proposed test enables the inclusion of other fuel impacts alo...

AI summary Nova Scotia seeks a renewed cost-effectiveness test to evaluate electrification's strategic value by incorporating multi-fuel impacts. Efficiency Canada's report emphasizes aligning energy efficiency with net-zero goals across fuels. Efficiency Nova Scotia is positioned to balance interests as a multi-fuel administrator, mitigating electricity system costs through integrated programs like demand response and heat pumps.

Learning from the past by accounting for the future p. p. 7
Learning from the past by accounting for the future Re-balancing Nova Scotia's cost-effectiveness test has a particular salience for one of our co-authors (Brendan Haley). Acting as an intervener for the Ecology Action Centre during the 20...

AI summary The document discusses the 2007 Nova Scotia Integrated Resource Plan (IRP) process, highlighting concerns about the Total Resource Cost (TRC) test's exclusion of customer benefits in Demand Side Management (DSM) cost assessments. Ecology Action Centre (EAC) intervenor Brendan Haley criticized the unbalanced methodology, which led to an arbitrary decision by Nova Scotia Power. The text advocates for updating the Nova Scotia Test framework to adapt to evolving DSM strategies and ensure comprehensive cost-benefit analysis.

Katharine Turner p. pp. 8-9
Katharine Turner Policy Research Associate, Energy Poverty Efficiency Canada August 26, 2025 Nova Scotia Energy Board 3rd Floor, Summit Place 1601 Lower Water Street Halifax, Nova Scotia B3J 3P6 ATTN: Crystal Henwood Clerk of the Board E-m...

AI summary Katharine Turner, acting on behalf of the Kwilmu'kw Maw-klusuaqn Negotiation Office and the Assembly of Nova Scotia Mi'kmaw Chiefs, supports EfficiencyOne's proposed DSM plan with a Benefit-Cost Analysis (BCA) test. They emphasize the inclusion of non-energy benefits as a positive policy development, highlighting its potential to benefit Mi'kmaq communities by reflecting broader impacts beyond utility savings.

E-16SBA (NESB) RIR 1 2 passages
EfficiencyOne's Application for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management (DSM) Plans (NSEB M12282) SBA Responses to NSEB Board Staff Information Requests NON-CONFIDENTIAL
EfficiencyOne's Application for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management (DSM) Plans (NSEB M12282) SBA Responses to NSEB Board Staff Information Requests NON-CONFIDENTIAL

AI summary EfficiencyOne seeks approval for a new Benefit-Cost Analysis Test to evaluate Demand Side Management (DSM) plans under NSEB matter M12282. The SBA has responded to information requests from the NSEB Board Staff regarding the application.

Request IR-1:
Request IR-1: - Regarding recommendation 1 on page 16, - a) Is it Daymark's position that non-energy benefits relating to "amenity", "empowerment" and "pride" cannot be independently quantified? - b) Please explain whether Daymark is able...

AI summary Daymark asserts that non-energy benefits like 'amenity', 'empowerment', and 'pride' cannot be independently quantified for a BCA test. It argues Efficiency One (EOne) failed to demonstrate quantification in its application, relying instead on EFG's proxy adders. Daymark questions the necessity of third-party evidence for quantifying these benefits.

E-17SBA (IG) RIR 1 to 2 1 passage
Response to IR-2:
Response to IR-2: a) No, the only reason why I discussed the non-energy benefits in my evidence was to provide my opinion for the Board's consideration, in the event that the Board decides that it will include non-energy benefits in its de...

AI summary The respondent clarifies that discussing non-energy benefits was to inform the Board's potential inclusion of such benefits in decisions, but considers quantifying them premature. They advocate for using the PAC test over the proposed BCA test to avoid quantifying hard-to-measure benefits like amenity and pride, while suggesting PAC could be supplemented with other data.

E-18IG (ECEL) RIR 1 1 passage
Section 1 p. p. 1
2025 M12282 NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act IN THE MATTER OF: An Application by EfficiencyOne for approval of a New Benefit- Cost Analysis Test for Evaluating Demand Side Management Plans RESPONSES TO IN...

AI summary EfficiencyOne seeks approval for a new benefit-cost analysis test for demand side management (DSM) plans. Bowman Economic Consulting Inc. and The Industrial Group respond to East Coast Environmental Law's inquiry about Nova Scotia's regulatory framework, noting that DSM analysis at the societal level is uncommon in Canada. The response references clause 6(2)(d) of the Energy and Regulatory Boards Act, which mandates consideration of sustainable development.

E-19IG (NSEB) RIR 1 to 4 5 passages
1 Request IR-2: p. p. 1
1 Request IR-2: - 2 Please provide versions of the two tables on page 14 that also include a column for the - 3 total resource cost test, adjusted to include non-energy benefits, as contemplated in - 4 "Option 1" described on page 12.

AI summary Request IR-2 seeks updated versions of two tables on page 14, requiring an additional column for the total resource cost test adjusted to include non-energy benefits as outlined in 'Option 1' on page 12.

11 For conversion of electric resistance heating to heat pumps (energy efficiency): p. p. 1
11 For conversion of electric resistance heating to heat pumps (energy efficiency): Proposed BCA (societal perspective) TRC including Non-Energy Benefits (utility and its customers + participant perspective) PAC (utility and its customers...

AI summary The document compares cost-benefit analyses (BCA, TRC, PAC) for converting electric resistance heating to heat pumps. Benefits include avoided generation/capacity costs, transmission/distribution savings, health impacts, and GHG reductions. Costs involve installation, program administration, and taxes. Perspectives vary between societal, utility/customer, and host customer viewpoints.

Response: p. pp. 1-4
Response: The TRC test, as outlined in IR-2, suffers from a number of issues. First, the TRC test provides incomplete insight into the impact on a utility and its customers. It only looks at the aggregated impact on those parties, when com...

AI summary The response critiques the TRC test for aggregating impacts and ignoring subsidies, which can mask adverse effects on utilities and non-participating customers. It cites a Newfoundland board order and argues for the PAC measure as a more accurate assessment tool for utility and customer impacts.

Request IR-4: p. p. 4
Request IR-4: - On page 15, it is stated that, "The use of a primary screening tool can help reach - conclusions on the cost-effectiveness of a plan, but is not an absolute requirement nor - veto on any given plan component." Given this, p...

AI summary The text questions the significance of selecting between the program administrator cost test and the 'Proposed BCA' as the primary test for evaluating the cost-effectiveness of plans, noting that a primary screening tool is not an absolute requirement.

Response: p. p. 4
Response: - From the outset, the focus should be on the fundamental E1 transaction, which is spending on - subsidies and programs towards energy efficiency and electrification. - Anyone can undertake energy efficiency activities at any tim...

AI summary The response emphasizes that E1's role is to provide incentives and share information to boost energy efficiency and electrification, not achieve these goals directly. It argues that PAC is a more accurate measure of E1's cost-effectiveness than TRC, which overemphasizes participant spending and overlooks E1's incentive programs. The Energy Board's focus on cost-effectiveness aligns with PAC's targeted evaluation.

E-20IG (Synapse) RIR 1 to 3 4 passages
Preamble p. p. 2
2025 M12282 NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act IN THE MATTER OF: An Application by EfficiencyOne for approval of a New Benefit- Cost Analysis Test for Evaluating Demand Side Management Plans RESPONSES TO IN...

AI summary EfficiencyOne seeks approval for a new benefit-cost analysis test for evaluating demand side management plans. Synapse Energy Economics requests information on how energy efficiency measures impact utility revenues, differences in treating electrification measures, and jurisdictional practices regarding BCA tests and the PAC test.

Response: p. pp. 2-5
Board should only ever look at the portfolio level (which appears to be contrary to the definition of Demand Side Management under s.79A(b) of the Act, which includes activities, programs, and plans). To be clear, Mr. Bowman's proposal is...

AI summary The text argues that the Board should assess electrification at the portfolio level, conflicting with DSM definitions under the Act. Mr. Bowman proposes including electrification revenues as benefits, contrasting with energy efficiency programs that avoid NSP fuel costs. The ACEEE database is referenced, noting states include lost revenues in BCA tests.

Request IR-2: p. p. 3
Request IR-2: - Refer to the Evidence of Patrick Bowman at page 15, which states that "E1 has proposed - its BCA include multiple specific inputs that are not consistent with methods and - assumptions for alternative resource investments"....

AI summary The Board questions whether 'alternative resource investments' are approved like the E1 DSM Plan and if a BCA is required for them, citing Patrick Bowman's evidence that E1's BCA methodology differs from standard practices for alternative investments.

Request IR-3: p. p. 5
Request IR-3: - Refer to the Evidence of Patrick Bowman at page 18, which states "A RIM test should not - be applied as a screening test for energy efficiency, as it can derive excessively narrow - metrics and fail to measure proper cost-e...

AI summary Patrick Bowman's evidence challenges the use of the RIM test for energy efficiency, arguing it produces narrow metrics. The proceeding questions why revenue changes in the PAC test are appropriate and how it differs from RIM. Key issues involve cost-effectiveness methodologies and regulatory testing frameworks.

E-21Synapse (IG) RIR 1 to 2 6 passages
Request IR-1:
Request IR-1: - Reference: Exhibit E-9, page 6-7. - Synapse cites Step 1 as being to articulate Nova Scotia's applicable policy goals related - to distributed energy resources (DER). - (a) Please confirm or otherwise explain whether Synaps...

AI summary Request IR-1 asks Synapse to clarify whether it considered the Public Utilities Act's requirement that DER activities must serve customers' best interests, whether a broader BCA test aligns with policy goals, and if adopting a PAC test would conflict with Nova Scotia's policy objectives. The inquiry centers on regulatory interpretations of DER policy and evaluation methodologies.

Synapse Energy Economics Responses to the Industrial Group Information Requests NON-CONFIDENTIAL
Synapse Energy Economics Responses to the Industrial Group Information Requests NON-CONFIDENTIAL the Evidence of Courtney Lane on page 19, lines 17-20 and page 20 lines 1-2). (c) It is unclear what is meant by "with information from the so...

AI summary Synapse Energy Economics responds to Industrial Group's information requests, arguing that excluding societal impacts (resilience, GHG emissions, health effects) from the BCA test contradicts Nova Scotia policy goals. They reference Courtney Lane's evidence to support this claim.

Request IR-2:
Request IR-2:

AI summary The document outlines Request IR-2, focusing on distributed energy resources (DER), demand-side management (DSM), and benefit-cost analysis (BCA) within a Nova Scotia regulatory proceeding. Key arguments and entities are not explicitly detailed in the provided text.

Reference: Exhibit E-9 page 23.
Reference: Exhibit E-9 page 23. - (a) Does Synapse's support of the E1 proposed BCA test consider the source of funds for the DER programming? Specifically, given the funds for the programming are derived from utility rates, does Synapse e...

AI summary The text questions Synapse's BCA test for DER programming, querying whether benefits/costs should align with utility function (vs societal perspective) given funding from utility rates, and if non-monetary benefits (e.g., comfort, pride) meet utility principles for inclusion in electricity rates.

Response IR-2:
Response IR-2: (a) Yes. Synapse's support for E1's proposed BCA test does consider the fact that DER programs are funded by ratepayers. Synapse does not think there should be a closer linkage between the benefits/costs included in the BCA

AI summary Synapse supports E1's proposed BCA test, acknowledging that DER programs are funded by ratepayers. However, they argue against establishing a closer linkage between the benefits and costs included in the BCA.

Synapse Energy Economics Responses to the Industrial Group Information Requests NON-CONFIDENTIAL
Synapse Energy Economics Responses to the Industrial Group Information Requests NON-CONFIDENTIAL test to the utility function. A BCA test that only links benefits/costs to the utility function is essentially the PAC (also known as the util...

AI summary Synapse Energy Economics argues that the BCA test (PAC/UCT) does not align with Nova Scotia's policy goals, as noted in Courtney Lane's evidence. The Energy Board evaluates DSM plans at the portfolio level, not individual DER measures. Synapse contends that DER measures with cost-effective BCA results, including non-energy benefits, are 'useful' and 'used' once operational.

E-22CV - Chris Neme - E1 3 passages
Selected Projects p. p. 0
Selected Projects - Natural Resources Defense Council (Illinois, Michigan and Ohio). Critically review energy efficiency, demand response, electrification, distribution system investment and integrated resource plans filed by IL, MI and OH...

AI summary The document outlines two key projects: Natural Resources Defense Council (NRDC) engaging in energy efficiency reviews, regulatory testimony, and legislative support in Illinois, Michigan, and Ohio from 2010 to present. E4TheFuture co-authored the National Standard Practice Manual (NSPM) for distributed energy resources (DERs) and conducted training from 2016 to present, with updates expected in 2025.

Energy Futures Group, Inc p. pp. 0-3
Energy Futures Group, Inc - Maryland Public Service Commission. Part of team that led a year-long stakeholder Work Group in the development of a unified benefit-cost analysis (UBCA) framework for consideration of all distributed energy res...

AI summary Energy Futures Group, Inc. leads benefit-cost analysis frameworks for DERs in Maryland and Nova Scotia, advises on gas DSM and IRP committees in Ontario, and represents environmental groups in regulatory proceedings. They focus on UBCA development, demand response, electrification, and decarbonization strategies.

Selected Publications and Reports p. pp. 5-6
Selected Publications and Reports - National Standard Practice Manual for Benefit Cost Analysis of Distributed Energy Resources , Second Edition, to be published December 2025 (with Tim Woolf and others) - New Jersey's Electric Grid Has He...

AI summary The document lists publications and reports on energy efficiency, distributed energy resources (DERs), and clean heat standards (CHS). Key topics include benefit-cost analysis of DERs, building decarbonization, residential electrification, and heat pump adoption. Reports are authored by individuals and organizations such as the Natural Resources Defense Council, Environmental Defense Fund, and Vermont Energy Action Network.

E-23CV - Chris Pulfer, P.Eng. - EE 1 passage
Energy Efficiency Technology and Market Research p. p. 0
Energy Efficiency Technology and Market Research - Year 8 Building Energy Benchmarking: City of Edmonton (Nov. 2024 ongoing) - Building Controls Program Design Support: FortisBC (Jun. 2024 November 2024) - 2024 Conservation Potential Revie...

AI summary The document outlines multiple energy efficiency and market research initiatives underway in 2023-2025, involving organizations like FortisBC, Fortis Energy Inc., Natural Resources Canada, and others. Projects include building benchmarking, conservation reviews, retrofit studies, and grid integration analyses, spanning provinces and focusing on residential, commercial, and transportation sectors.

E-24Rebuttal Evidence of E1 including Appendix A - Energy Futures Group Rebuttal Evidence 28 passages
EfficiencyOne p. p. 0
EfficiencyOne IN THE MATTER OF The Public Utilities Act , RSNS 1989, c. 380, as amended -and- IN THE MATTER OF An Application for Approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans

AI summary The document pertains to a regulatory proceeding under the Public Utilities Act, RSNS 1989, c. 380, involving an application to approve a new benefit-cost analysis test for evaluating demand side management plans. EfficiencyOne is referenced as the subject of the proceeding.

1 1. INTRODUCTION p. pp. 0-3
1 1. INTRODUCTION - On May 16, 2025, EfficiencyOne ("E1") submitted an Application for Approval of a New Benefit-Cost - Analysis ("BCA") Test for Evaluating Demand Side Management ("DSM") Plans before the Nova Scotia - Energy Board (the "B...

AI summary EfficiencyOne submitted a new BCA test for DSM plans to the Nova Scotia Energy Board in Matter 12282. Multiple intervenors, including Synapse and the Industrial Group, provided evidence, with E1 rebutting claims about alternative BCA tests, portfolio-level cost-effectiveness, proxy values for non-energy benefits, and discount rates. The Industrial Group opposed E1's proposed framework, prompting E1's detailed rebuttal.

Bowman p. p. 4
Bowman Scotia.[1](#page-4-2) He states: The evidence of Patrick Bowman of Bowman Economic Consulting Inc., for the Industrial Group, represents the only intervenor party to take issue with E1's position that cost-effectiveness screening of...

AI summary Patrick Bowman of Bowman Economic Consulting Inc. challenges E1's position that DSM cost-effectiveness should be assessed at the portfolio level, arguing that the legislation allows for granular assessments at program or measure levels. He asserts the Board must evaluate alternative DSM plans at various scales to ensure cost-effectiveness and compliance with statutory mandates, including customer interests and reasonable program availability.

E1 Response p. pp. 4-7
E1 Response - The argument that the Board can, and must, measure cost-effectiveness at the measure level requires - legislative interpretation and is a legal argument. Questions of law are within the power of the Board to - determine. Nota...

AI summary E1 argues that measure-level cost-effectiveness testing for DSM may hinder proactive market development and reduce overall benefits, advocating for portfolio-level evaluation. The Board previously allowed program-level screening but 2022 legislative amendments now mandate portfolio-level assessment. E1 asserts BCA is primarily a portfolio-level tool but will also be used at lower levels for informational purposes.

2.2.2 N S POWER CUSTOMER INTERESTS p. pp. 7-8
2.2.2 N S POWER CUSTOMER INTERESTS Unlike the PAC test, which accounts for only the DSM Administrator's costs and NS Power's avoided costs, the BCA test accounts for the DSM Administrator's costs and customer costs while recognizing the ex...

AI summary The BCA test is preferred over PAC and UCT as it includes customer costs and legislative requirements like those from the Energy Reform (2024) Act, ensuring alignment with sustainable development and ratepayer interests.

Bowman p. p. 8
Bowman Mr. Bowman further submits: E1 should be directed to pursue measures and programs that are cost-effective as the primary criteria, minimizing the other "balanced" criteria in program design to support non-cost-effective measures and...

AI summary Mr. Bowman argues that EfficiencyOne (E1) should prioritize cost-effective measures in its programs, minimizing other criteria that might support less cost-effective initiatives. This submission references evidence from Efficiency Canada and prior testimony.

E1 Response p. p. 8
E1 Response - E1 submits that the non-USIs considered in the proposed BCA test address the goals of strategic - electrification, sustainable development and sustainable prosperity. All these goals are legislated matters - for consideration...

AI summary E1 argues that non-USIs in the BCA test align with legislated goals of strategic electrification and sustainable development. They oppose narrowing DSM criteria, claiming it would undermine secondary objectives and contradict stakeholder-supported Balanced Plan Approach, harming ratepayer interests and effective demand-side management.

Bowman p. p. 9
Bowman Mr. Bowman suggests that E1's focus on balanced plan design is problematic. He explains: [T]his is generally inconsistent with NSPM Principle 1, unless explicitly established by policy. Just as generation energy resources are compar...

AI summary Mr. Bowman argues that E1's emphasis on balanced plan design conflicts with NSPM Principle 1, which prioritizes cost-effectiveness for DSM over equity and access. He highlights that utility resources are not typically designed for balance, using wind developer PPA examples. He reaffirms Nova Scotia's IRP principles: safety, reliability, least cost, decarbonization, and robustness to assumption changes, unless explicit policy mandates balanced DSM access.

E1 Response p. p. 11
ISSIONS - Bowman - Mr. Bowman asks that the Board require E1 to show that any avoided GHG emissions are in fact the result - of DSM, and not due to an outside factor such as a cap.[15](#page-11-2) - E1 Response - As part of the 'evergreen'...

AI summary E1 responds to Bowman's request for demonstrating GHG emission reductions from DSM by proposing a methodology that accounts for emissions caps. E1 clarifies that PCT and payback periods are program design tools, not directly addressed by BCA. The analysis emphasizes differentiating DSM impacts from external factors and aligns with E1's incentive-setting framework.

E1 Response p. p. 12
E1 Response - E1 supports this recommendation with the addition of a review and update for all impacts—not solely - those related to NEB proxies—commencing prior to the development of the next DSM Plan via the - proposed 'evergreen' proces...

AI summary E1 supports a recommendation to review all impacts, not just non-energy benefits (NEB) proxies, via an 'evergreen' process before developing the next DSM Plan. Engagement with DSMAG is expected to begin in 2029. E1 proposes a multi-step process to ensure the BCA test remains current, including quantifying impacts using jurisdictional data and customer surveys, with DSMAG input.

Green Energy p. p. 13
Green Energy Mr. Wyatt states: I express overall support of the proposed benefit cost test as a more balanced test. The new benefit values in the proposed test should be vetted and include stakeholders in the process.[20](#page-13-2)

AI summary Mr. Wyatt supports the proposed benefit-cost test as more balanced, advocating for stakeholder involvement in vetting new benefit values.

Green Energy p. p. 14
Green Energy Mr. Wyatt raised the following concern: I support the addition of externalized cost of carbon in the new test, but ask that the internalized cost of carbon be kept separate from the externalized cost of carbon for use with the...

AI summary Mr. Wyatt supports including externalized carbon costs in the new test but advocates keeping internalized carbon costs separate for use with the Program Administrator Cost (PAC) test, as noted in footnote 21.

Daymark p. p. 14
Daymark - Melissa Whitten of Daymark Energy Advisors, Inc. ("Daymark") provides the following observations and - conclusions regarding the Application: - The proposed BCA test framework relies on proxy values for certain non-energy - benef...

AI summary Daymark Energy Advisors criticizes the proposed BCA test framework for relying on unquantifiable proxy values for non-energy benefits, warning that this could introduce bias and lead to suboptimal DSM Plan decisions. They argue that plans derived from biased frameworks should not be prioritized for customers.

E1 Response p. pp. 14-16
E1 Response E1's position is that the use of proxy values for certain non-energy benefits is both reasonable and appropriate and consistent with jurisdiction specific studies. The NSPM for screening energy efficiency and distributed energy...

AI summary E1 argues that using proxy values for non-energy benefits (NEBs) in BCA is reasonable and aligns with the NSPM, supported by EFG and Synapse Energy Economics. E1 rejects claims of bias, emphasizing symmetric treatment of impacts. Daymark's Melissa Whitten counters, requesting third-party validation of NEB quantification (amenity, empowerment, pride).

5.3 QUANTIFICATION p. pp. 16-17
5.3 QUANTIFICATION

AI summary This section outlines the quantification process in the Nova Scotia regulatory proceeding, involving Nova Scotia Power (NSP) and the Nova Scotia Utility and Review Board (NSUARB). It focuses on Benefit-Cost Analysis (BCA) and Demand Side Management (DSM), with considerations of non-energy benefits (NEB) and adherence to the National Standard Practice Manual (NSPM).

Daymark p. p. 17
Daymark - In the alternative to the recommendation for further analysis on NEBs, Ms. Whitten suggests that the - Board "make the value assigned to the Unquantified Non-Energy Benefits Nil until the work outlined above - can be completed an...

AI summary Ms. Whitten recommends that the Board set the value of Unquantified Non-Energy Benefits (NEBs) to Nil until further analysis is completed and approved. This suggestion is part of a regulatory proceeding involving a Benefit-Cost Analysis (BCA) framework for Nova Scotia, with references to evidence and appendices from Matter M12282.

E1 Response p. p. 17
E1 Response - To assign a nil value to unquantified NEBs defaults such benefits to zero, notwithstanding the associated - benefit. Utilising this approach would lead to greater distortion of the results than employing the - conservative pr...

AI summary The response criticizes assigning nil values to unquantified Non-Energy Benefits (NEBs) in Benefit-Cost Analysis (BCA), arguing this distorts results. It advocates using E1's conservative proxy values instead, citing Francis Wyatt of Green Energy's perspective on the issue.

Posterity Group p. p. 18
Posterity Group - Posterity Group Consulting Inc. ("Posterity") "recommends that E1 specifically recognize the benefits of - hybrid heating to reduce peak load impacts as part of the 2027-2031 DSM Plan,"[34](#page-18-4) and prepared two -...

AI summary Posterity Group Consulting Inc. recommends that E1 recognize hybrid heating's benefits in reducing peak load impacts for the 2027-2031 DSM Plan, supported by BCA examples. They cite evidence from M12282.

E1 Response p. p. 18
E1 Response - E1 acknowledges the value of hybrid heating. Such measures can accurately be evaluated under the - proposed BCA framework. The inclusion of specific hybrid heating measures may be considered in the - 2027-2031 DSM Plan, but p...

AI summary E1 acknowledges the value of hybrid heating measures, which can be evaluated under the proposed BCA framework. Specific hybrid heating measures may be included in the 2027-2031 DSM Plan, though program design decisions remain pending.

E1 Response p. p. 20
E1 Response - E1 notes that NS Power's avoided cost of capacity implicitly includes reliability impacts through a planning reserve margin adjustment. This captures any changes in reliability requirements based on changes in load. If reliab...

AI summary E1 notes that NS Power's avoided cost of capacity includes reliability impacts via a planning reserve margin adjustment. This accounts for reliability changes based on load variations. E1 suggests that if reliability differs between scenarios, incremental reliability impacts beyond existing avoided costs could be assessed.

Eastward p. p. 21
Eastward Eastward Energy also argues: [...A]ny benefit cost analysis related to natural gas must incorporate the expanded legislated mandate of the natural gas system as noted above. It must also capture the lost value of the natural gas s...

AI summary Eastward Energy argues that any benefit-cost analysis (BCA) for natural gas must account for the expanded legislated mandate of the natural gas system and the lost value of system reliability, as highlighted in a cited reference.

7.5 DSMAG PARTICIPATION EASTWARD p. pp. 21-22
7.5 DSMAG PARTICIPATION EASTWARD

AI summary Section 7.5 discusses DSMAG's participation in the Eastward project, emphasizing the need for Benefit-Cost Analysis (BCA) and Non-Energy Benefits (NEB) assessments. The NSUARB oversees the process, with E1 and EFG involved as key participants.

Rebuttal Evidence of Energy Futures Group Inc. M12282 p. pp. 22-23
Rebuttal Evidence of Energy Futures Group Inc. M12282 IN THE MATTER OF The Public Utilities Act , RSNS 1989, c. 380, as amended -and- IN THE MATTER OF An Application for Approval of a New Benefit-Cost Analysis Test for Evaluating Demand Si...

AI summary Energy Futures Group Inc. (EFG) submits rebuttal evidence in M12282 regarding a new Benefit-Cost Analysis (BCA) test for evaluating Demand Side Management (DSM) plans under the Public Utilities Act. The proceeding involves Nova Scotia Energy Board and focuses on DSM program evaluation methodologies.

Synapse p. p. 25
Synapse Courtney Lane of Synapse states: - The use of proxy values is a reasonable approach to estimate host customer non energy benefits (NEB) in cost-effectiveness analysis. However E1 has not sufficiently justified its proposal for NEB...

AI summary Courtney Lane of Synapse argues that while proxy values are reasonable for estimating non-energy benefits (NEB) in cost-effectiveness analysis, EfficiencyOne (E1) has not adequately justified its proposed NEB proxy values. She emphasizes the need for proxies to be grounded in literature, other jurisdictions' practices, and jurisdictional differences rather than arbitrary choices.

EFG Response p. pp. 25-28
EFG Response The approach of using proxy values was deliberate and not arbitrary. The approach was reviewed and discussed with the Demand Side Management Advisory Group ("DSMAG") in two workshop sessions, and open to written review and com...

AI summary EFG defends using proxy values for non-energy impacts (NEIs), citing discussions with DSMAG and referencing the ACEEE database. They argue that adopting values from other jurisdictions is imprecise and that proxy adders, though small, require regular review to remain accurate. EFG recommends adopting their proposed values with an ongoing 'evergreening' process.

EFG Response p. p. 28
EFG Response - To make the value assigned to the unquantified NEBs nil would result in bias the result which Ms. Whitten - is seeking to avoid. E1 notes that completely excluding known, but hard-to-quantify benefits would default - such be...

AI summary EFG argues against setting unquantified non-energy benefits (NEBs) to zero in benefit-cost analysis (BCA), stating it would bias results. They suggest using conservative proxy values instead, as proposed by E1, to avoid distorting BCA outcomes.

8 4. BOWMAN EVIDENCE p. pp. 28-29
8 4. BOWMAN EVIDENCE

AI summary Section 8.4 of the regulatory proceeding document presents Bowman's evidence, which likely involves analysis related to energy efficiency, demand-side management, and benefit-cost assessments in Nova Scotia. Key entities and acronyms are referenced, including regulatory bodies and programs.

4.2 2% DISCOUNT RATE p. p. 29
4.2 2% DISCOUNT RATE

AI summary This section discusses the application of a 2% discount rate in the Benefit-Cost Analysis (BCA) for regulatory proceedings in Nova Scotia. The analysis involves considerations by Nova Scotia Power (NSP) and the Nova Scotia Utility and Review Board (NSUARB), focusing on the implications of this rate for energy and non-energy benefits.

E-27Opening Statement - IG 2 passages
3 NOVA SCOTIA UTILITY AND REVIEW BOARD p. p. 0
3 NOVA SCOTIA UTILITY AND REVIEW BOARD 4 IN THE MATTER OF: The Public Utilities Act 5 IN THE MATTER OF: An Application by EfficiencyOne for approval of a New 6 Benefit-Cost Analysis Test for Evaluating Demand Side 7 Management Plans 8

AI summary The Nova Scotia Utility and Review Board is considering an application by EfficiencyOne under the Public Utilities Act for approval of a new benefit-cost analysis test to evaluate demand side management plans. The proceeding involves regulatory review of a proposed method for assessing energy efficiency initiatives.

9 COUNSEL OPENING STATEMENT 10 ON BEHALF OF THE INDUSTRIAL GROUP p. p. 0
9 COUNSEL OPENING STATEMENT 10 ON BEHALF OF THE INDUSTRIAL GROUP 11 As required by the Public Utilities Act , NSPI is required to undertake cost-effective, reasonably - 12 available, demand side management (" DSM ") by entering into a purc...

AI summary The Industrial Group argues against the Proposed E1 BCA test, which incorporates non-energy benefits and societal impacts, and instead recommends the Program Administrator Cost (PAC) test as the primary measure of cost-effectiveness for demand side management (DSM) programs. They emphasize alignment with Canadian regulatory practices and the best interests of customers.

E-28Opening Statement - Patrick Bowman - IG 3 passages
1 M12282 - EfficiencyOne
- Ontario, PEI, Saskatchewan, Newfoundland and Labrador, and Yukon. This PAC test also has the 1 M12282 - EfficiencyOne 26 27 28 29 30 31 The second option would be to change from the TRC test, to now add in not only customer benefits, but...

AI summary The text discusses a proposed change from the TRC test to include broader societal costs and benefits in the evaluation of demand-side management programs. This approach is not commonly used in Canada and has only been referenced in the now-abandoned Alberta Energy Efficiency Office.

Section 6
- benefit of being a key part of the approach needed to fulfill the Board's role under section 79L(4) of - the Act, where it must specifically assess impacts on NS Power's customers. - The PAC test is also beneficial as it permits a BCA as...

AI summary The text argues for the adoption of the PAC test over E1's proposed BCA approach, emphasizing cost-effectiveness and the inclusion of customer incentives. It also criticizes the use of a low discount rate for assessing DSM measures and highlights the importance of including revenue benefits from electrification in the PAC test.

Section 8
olio level. I have reviewed the E1 rebuttal on this matter, and I suspect that ultimately my position differs from E1's in nomenclature more than substance. To be clear - DSM should be assessed at the - measure, and program, and portfolio...

AI summary The text argues that Demand Side Management (DSM) should be assessed at measure, program, and portfolio levels, not just portfolio level, to ensure individual components are evaluated for cost-effectiveness. It clarifies that the PAC test may yield different metrics but does not necessarily reduce DSM investment, emphasizing that the Board could still prioritize societal benefits despite potential rate impacts.

E-29Opening Statement - E1 1 passage
EfficiencyOne p. p. 0
EfficiencyOne IN THE MATTER OF The Public Utilities Act , RSNS 1989, c. 380, as amended -and- IN THE MATTER OF An Application for Approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans

AI summary The document outlines an application for approval of a new benefit-cost analysis test to evaluate demand-side management (DSM) plans under the Public Utilities Act. The proceeding involves regulatory considerations for assessing the cost-effectiveness of DSM initiatives.

E-34Response to Undertaking 2 passages
1 Undertaking U-1: p. p. 0
1 Undertaking U-1: 2 3 To provide the results using the Program Administrator Costs (PAC) test method and exclude 4 the Host Customer Impacts from the proposed BCA to the analysis of the differences in the 5 screening results as presented...

AI summary The document outlines an undertaking (U-1) to apply the Program Administrator Costs (PAC) test method while excluding Host Customer Impacts from a Benefit-Cost Analysis (BCA) of a Demand Side Management (DSM) plan. Energy Futures Group (EFG) responds, referencing Dr. Hill's evidence and an illustrative example of 1,000 heat pump replacements. The matter is linked to Exhibit E-1 of application M12282.

Figure 1: Program Administrator Cost Test - Illustrative Results p. pp. 0-1
Figure 1: Program Administrator Cost Test - Illustrative Results Under the PAC test, the benefit cost ratio for replacement of electric resistance systems is 4.95. Using the PAC test, the benefit cost ratio for replacing fuel oil and natur...

AI summary The PAC test yields a benefit-cost ratio of 4.95 for replacing electric resistance systems but 0.0 for fuel oil and natural gas systems due to absent utility benefits. The analysis references Dr. Hill's evidence and EfficiencyOne's proposed BCA methodology, excluding host customer impacts.

97785Hearing Order 2 passages
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF AN APPLICATION BY EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans BEFORE : Stephen T. McGrath, K.C., Chair Steven...

AI summary The document outlines a regulatory proceeding under the Public Utilities Act, involving EfficiencyOne's application to approve a new benefit-cost analysis test for evaluating demand side management plans. The proceeding is before a three-member board chaired by Stephen T. McGrath, K.C., with Steven M. Murphy and Darlene Willcott as members.

HEARING ORDER
HEARING ORDER EfficiencyOne (E1) applied to the Nova Scotia Energy Board on May 16, 2025, for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management (DSM) Plans.

AI summary EfficiencyOne (E1) applied to the Nova Scotia Energy Board on May 16, 2025, seeking approval for a new benefit-cost analysis test to evaluate demand side management (DSM) plans. The application aims to establish a framework for assessing the economic viability of DSM initiatives.

97786Notice of Public Hearing 1 passage
NOTICE OF PUBLIC HEARING
NOTICE OF PUBLIC HEARING _____________________________________________________________________________ EfficiencyOne (E1) applied to the Nova Scotia Energy Board on May 16, 2025, for approval of a New Benefit-Cost Analysis Test for Evaluat...

AI summary EfficiencyOne (E1) seeks approval from the Nova Scotia Energy Board for a new Benefit-Cost Analysis Test to evaluate Demand Side Management (DSM) Plans. A public hearing is scheduled for September 22-23, 2025, at the Office of the Board in Halifax.

100256Board Decision 30 passages
IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 3
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF AN APPLICATION by EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans BEFORE: Stephen T. McGrath, K.C., Chair Steven...

AI summary EfficiencyOne applied for approval of a new benefit-cost analysis test for demand side management plans. The Board rejected the application, directing instead to focus on reducing electricity costs for customers. Multiple intervenors, including consumer advocates, industry groups, and Nova Scotia Power, participated in the proceeding.

Preamble p. p. 3
- [1] In the course of addressing EfficiencyOne's (E1) application to the Nova Scotia Utility and Review Board (NSUARB) for approval of its supply agreement with Nova Scotia Power Incorporated (NS Power) and demand-side management (DSM) re...

AI summary The NSUARB is reviewing EfficiencyOne's application for a supply agreement with NS Power and its DSM plan. Concerns were raised about the cost-effectiveness test used, specifically the TRC test, which excludes non-energy benefits. Synapse recommended using the PAC test instead, though it does not account for participant costs and benefits.

2.0 PROPOSED BENEFIT-COST ANALYSIS TEST p. pp. 3-5
2.0 PROPOSED BENEFIT-COST ANALYSIS TEST - [8] E1 is the holder of a franchise issued by the Minister of Energy to provide demand-side management activities to NS Power. Under the Public Utilities Act , E1 must develop a demand-side managem...

AI summary E1, a franchise holder under the Public Utilities Act, must develop demand-side management (DSM) plans for NS Power, subject to Nova Scotia Utility and Review Board approval. The DSM framework uses a tiered structure (measure, program, portfolio levels) and cost-effectiveness testing to evaluate plans, ensuring measurable benefits for ratepayers.

3.1 Consumer Advocate p. p. 14
3.1 Consumer Advocate [28] The Consumer Advocate is a signatory to the Consensus Agreement. The Consumer Advocate argues that recent amendments to the Public Utilities Act altered the criteria the Board is to apply in evaluating E1's propo...

AI summary The Consumer Advocate argues that amendments to the Public Utilities Act require the NSUARB to evaluate demand-side management at the portfolio level, incorporating sustainability and environmental factors. They support E1's BCA test over the PAC test, citing its alignment with policy goals like sustainable development and greenhouse gas reduction. The 2% social discount rate is preferred for long-term impacts, and the 10% proxy value for beneficial electrification is maintained.

3.2 Industrial Group p. pp. 14-16
3.2 Industrial Group [34] The Industrial Group is not a party to the Consensus Agreement. It objects to the use of the proposed BCA test as the new primary cost-effectiveness test. It recommends the Board approve the PAC test as the primar...

AI summary The Industrial Group opposes using the BCA test for DSM Plan applications, advocating instead for the PAC test at portfolio, program, and measure levels. They argue the Board should exclude non-energy impacts like carbon social effects. The group also highlights changes to the Public Utilities Act that expanded DSM to include strategic electrification, emphasizing cost reduction as the Act's focus.

3.3 Small Business Advocate p. pp. 16-20
3.3 Small Business Advocate [45] The Small Business Advocate agreed to the Consensus Agreement and recommends the Board adopt the proposed BCA test as amended by the Consensus Agreement. In closing submissions, the Small Business Advocate...

AI summary The Small Business Advocate agreed to the Consensus Agreement, recommending the Board adopt the amended BCA test. Concerns were raised about quantifying non-energy benefits like amenity and empowerment, with recommendations to set unquantified benefits to zero or adopt the PAC test instead. The Advocate emphasized the need for further work on quantifying non-energy benefits.

3.4 Nova Scotia Power p. pp. 20-21
3.4 Nova Scotia Power [48] NS Power does not support E1's proposed BCA test and recommends the Board approve the current TRC with two modifications which would consider, in the context of strategic electrification, GHG emissions reductions...

AI summary Nova Scotia Power opposes E1's proposed BCA test, advocating for TRC modifications to include GHG emissions reductions (net tonnage) and electricity cost reductions. It emphasizes that the Public Utilities Act mandates strategic electrification to reduce emissions and costs, arguing that the Board's core mandate is ensuring just and reasonable rates, not broader social considerations.

3.6 Eastward Energy p. pp. 23-24
3.6 Eastward Energy [61] In its submissions, Eastward Energy asked the Board to make a preliminary and final order that Eastward be added as a full member of DSMAG. On November 4, 2025, the Board noted that Eastward has a valuable perspect...

AI summary Eastward Energy requested DSMAG membership, which the NSUARB approved. They supported strategic electrification testing methods aligning with Posterity Group's recommendations and advocated for hybrid heating in E1's 2027-2031 DSM Plan, emphasizing economic benefits and regulatory alignment with the PUA.

4.1.1 Introduction p. p. 27
4.1.1 Introduction [69] The Public Utilities Act requires NS Power to engage E1 to undertake "costeffective demand-side management". The Board must approve these agreements and "determine the cost-effective demand-side management that must...

AI summary The NSUARB must determine the cost-effectiveness test for demand-side management under the Public Utilities Act. E1 argues the Board now has jurisdiction to consider non-energy impacts, while some intervenors disagree. Legislative amendments since 2020, including the Energy Reform (2024) Act, expanded the Energy Board's consideration scope. The Board will assess statutory interpretation and the meaning of 'cost-effective' in DSM provisions.

4.1.3 Board Approval of Demand-side Management p. p. 30
Incorporated, and Nova Scotia Power Incorporated may rely upon the expertise of the franchise holder in respect of the delivery of demand-side management. - (4) The Energy Board shall approve an application pursuant to this Section if, in...

AI summary The Energy Board must approve demand-side management (DSM) applications if they serve customers' best interests and meet Section 79I requirements. Evaluations must occur at the portfolio level per Section 79H, considering aggregate DSM programs. The Board also assesses cost-effectiveness and relies on franchise holder expertise for delivery.

4.1.4 The 2020 Non-energy Benefits Decision p. pp. 30-33
4.1.4 The 2020 Non-energy Benefits Decision - [83] The NSUARB determined it did not have the jurisdiction to consider nonenergy benefits in the cost-effectiveness testing for demand-side management in Re EfficiencyOne , 2020 NSUARB 56. In...

AI summary The NSUARB ruled it lacked jurisdiction to consider non-energy benefits in DSM cost-effectiveness testing in Re EfficiencyOne , 2020 NSUARB 56. E1 argued that the Public Utilities Act grants the NSUARB broad discretion to assess factors like thermal comfort and property value impacts as part of customers' best interests, beyond mere electricity savings.

4.1.6 The Meaning of "Cost-effective" under the Public Utilities Act p. pp. 36-40
4.1.6 The Meaning of "Cost-effective" under the Public Utilities Act [96] From the text used by the Legislature in s. 79I(1) of the Public Utilities Act , it follows that NS Power's statutory duty relates to demand-side management (as defi...

AI summary Section 79I of the Public Utilities Act mandates that NS Power's demand-side management (DSM) must be cost-effective and reasonably available, with the goal of reducing customer costs. The NSUARB must review DSM agreements, ensuring compliance with s. 79I and evaluating cost-effectiveness at the portfolio level. The Act does not explicitly define 'cost-effective,' leaving regulatory interpretation to the Board.

The current version is: p. p. 40
The current version is: (iv) strategic electrification of energy end uses currently powered by fossil fuels in a manner that reduces overall greenhouse gas emissions and electricity costs [108] E1 submits that strategic electrification can...

AI summary E1 argues that strategic electrification, defined under the PUA amendment, requires expanding cost-effectiveness testing beyond traditional PAC/TRC frameworks to account for non-utility benefits like fuel savings and GHG reductions. E1 claims this is essential to fulfill its mandate under the updated DSM definition.

4.1.6.1 Findings p. p. 52
nergy supply in the Province" in s. 6(2)(c) could alter the requirement in s. 67 of the Public Utilities Act that all tolls, rates and charges shall always, under substantially similar circumstances and conditions in respect of service of...

AI summary The NSUARB interprets the Public Utilities Act (PUA) to require NS Power to implement demand-side management (DSM) to reduce electricity costs. The Industrial Group emphasizes that legislative objectives cannot override clear statutory language, and the Board confirms NS Power's obligation is met via its agreement with E1. The Board rejects ambiguity in PUA provisions regarding DSM.

4.2 Benefit-Cost Test Alternatives p. pp. 52-57
4.2 Benefit-Cost Test Alternatives [143] No party in this proceeding argued that the existing TRC test should be maintained in its present form. [144] As discussed in more detail previously, E1's proposed BCA test includes utility system a...

AI summary No party supports maintaining the existing TRC test. E1 proposes a BCA test incorporating utility and non-utility system impacts, aligning with Nova Scotia's legislative changes and sustainability goals. Table 5 compares the existing TRC and proposed BCA tests.

[146] In its closing submissions, the Industrial Group said: p. p. 57
[146] In its closing submissions, the Industrial Group said: Where the PUA has clearly mandated the focus of DSM to be on the reduction of costs, the PAC is able to demonstrate that as a primary test; the Proposed BCA cannot. As confirmed...

AI summary The Industrial Group argues that the Program Administrator Cost (PAC) test aligns with the PUA's mandate to reduce electricity costs, unlike the Proposed BCA. NS Power proposes a modified Total Resource Cost (TRC) test to account for fuel switching benefits, while E1 criticizes both approaches, claiming they fail to meet legislative requirements or address strategic electrification mandates. The debate centers on cost-effectiveness criteria for demand-side management.

4.2.1 Findings p. pp. 57-60
4.2.1 Findings [151] E1 and its consultants purported to follow guidance in the NSPM in determining the proposed BCA test. However, a process that simply takes account of an inventory of energy and climate change policy goals and objective...

AI summary The NSUARB rejects E1's proposed BCA test for DSM cost-effectiveness, citing misalignment with the PUA's mandate to reduce electricity costs. The TRC test is criticized for asymmetrical application, while the PAC test is endorsed as it aligns with statutory goals. The Board directs E1 to use the PAC test for DSM plans starting in 2027.

4.3 Strategic Electrification p. pp. 60-62
4.3 Strategic Electrification [158] Strategic electrification that reduces overall GHG emissions and electricity costs is included in the definition of "demand-side management" in s. 79A(b)(iv) of the Public Utilities Act . The PAC test, a...

AI summary The document discusses challenges in applying the traditional PAC test to strategic electrification programs under the Public Utilities Act. Mr. Bowman proposes modifying the PAC test to include increased revenues from electrification as a benefit, ensuring cost-effective programs. The Industrial Group supports this approach, aligning with E1's mandate to reduce electricity costs for NSPI customers.

[160] Eastward made similar comments in its submissions: p. p. 62
[160] Eastward made similar comments in its submissions: In this regard the IG has noted that the approach proposed by Mr. Bowman to costeffectiveness testing for E1 for strategic electrification – running the PAC test with the additional...

AI summary Eastward supports Mr. Bowman's modified PAC test for strategic electrification, aligning with Posterity Group's recommendations to ensure cost-effective programs. E1 argues the test assesses rate impacts, not cost-effectiveness, and has focused on GHG emissions rather than electricity cost reductions in its BCA.

4.3.1 Findings p. pp. 62-63
4.3.1 Findings [162] The Board accepts the Industrial Group's suggestion that traditional cost effectiveness tests may be modified to suit specific jurisdictional requirements. The means of assessing strategic electrification in Nova Scoti...

AI summary The NSUARB accepts modifying traditional cost-effectiveness tests for strategic electrification in Nova Scotia. E1's approach to demonstrating cost reductions remains incomplete, so it must follow Mr. Bowman's PAC test recommendation temporarily. The Board allows E1 to propose an alternative method in its 2027-2031 DSM Plan if it meets statutory requirements for reducing both GHG emissions and electricity costs.

4.4 Portfolio Level Assessment p. pp. 63-64
4.4 Portfolio Level Assessment [164] Section 79H(2) requires the Board to evaluate the proposed cost-effective demand-side management at the portfolio level. In its submissions, the Industrial Group urged that it was particularly important...

AI summary Section 79H(2) of the PUA mandates the NSUARB to assess demand-side management at the portfolio level. The Industrial Group and NS Power argue for applying cost-effectiveness tests at portfolio, program, and measure levels, while E1 insists on portfolio-level screening.

4.4.1 Findings p. p. 64
4.4.1 Findings [166] There is no ambiguity in s. 79H(2): the Board must evaluate the proposed cost-effective demand-side management at the portfolio level. As noted previously in this decision, the Board agrees with E1 that there is a diff...

AI summary The NSUARB mandates evaluation of cost-effective demand-side management (DSM) at the portfolio level, not individual measures. E1 must justify DSM measures failing primary cost-effectiveness tests and may use revised BCA tests with NS Power's WACC comparisons. The Board allows alternative tests if the overall portfolio passes, citing s. 6(2) of the Energy and Regulatory Boards Act.

4.5 Discount Rate p. pp. 64-65
4.5 Discount Rate [169] Benefit-cost analysis involves comparing all the costs and benefits of a program over a period of time. There will be a stream of costs and benefits that are usually spread over several years, and in some cases, dec...

AI summary The section discusses the role of discount rates in Benefit-Cost Analysis (BCA) for distributed energy resources. It explains that discount rates determine the present value of future costs and benefits, with the NSPM outlining three categories: WACC, customer-focused rates, and societal discount rates. Higher rates prioritize near-term costs, while lower rates balance long-term considerations.

4.5.1 Findings p. pp. 65-71
4.5.1 Findings [192] Discounting is a fundamental component of BCA. Applying a social discount rate places greater emphasis on future benefits than a standard discount rate typically would. Environment and Climate Change Canada's SC – GHGs...

AI summary The document discusses the importance of discounting in BCA, noting that Environment and Climate Change Canada's SC-GHG guidance uses a lower discount rate. It criticizes E1 for not following the Treasury Board's policy on when to apply a social discount rate, emphasizing compliance with the Treasury Board's Cost-Benefit Analysis Guide.

s. 7.1 about the discount rate to be used: p. p. 71
s. 7.1 about the discount rate to be used: The discount rate is the rate at which future costs and benefits are converted to their present equivalents. Discounting accounts for the fact that: - there is a time preference for current consum...

AI summary The NSUARB mandates using the opportunity cost of capital (WACC) as the discount rate for DSM programs, aligning with Treasury Board guidelines. This reflects the alternative investment returns of funds from NS Power ratepayers. The Board rejects social discount rates except for long-term regulatory proposals, emphasizing WACC's consistency with NS Power's IRP and PAC test requirements.

[201] In its response, E1 stated: p. p. 73
[201] In its response, E1 stated: The approach E1 is proposing in the 'evergreen' process for calculating the emissions intensity of DSM savings for the purposes of benefit cost analyses is the Difference in Carbon Emissions (DICE) method....

AI summary E1 proposes using the Difference in Carbon Emissions (DICE) method for calculating emissions intensity in DSM savings, aligning with NSPM and IRP for long-term planning. They argue this is more accurate than using marginal generator emissions, especially for significant load changes. In BCA, they use average emissions rates for illustrative examples.

4.6.1 Findings p. pp. 73-75
4.6.1 Findings [204] The Board considers the issue regarding average versus marginal generation emission rates to be worthy of further consideration. During crossexamination, E1's witnesses stated that, for expediency, average emission rat...

AI summary The Board emphasizes using long-run marginal emission rates over average rates in E1's BCA modeling, citing the need for refined assumptions. E1 used average data from NS Power but acknowledges the need for improvement.

4.8 Avoided Costs p. pp. 77-78
4.8 Avoided Costs [212] Eastward raised concern about NS Power's avoided cost values and requested confirmation that ancillary service costs, peak costs and system reliability are embedded in the avoided cost values. Eastward also requeste...

AI summary Eastward questioned NS Power's avoided cost values, seeking confirmation that ancillary service costs, peak costs, and system reliability are included. NS Power explained that peak demand, ancillary services, and reliability are factored into avoided cost modeling, using the latest IRP model and ongoing DSMAG discussions. The Board accepted this response as adequate.

4.9 Natural Gas System Reliability p. p. 78
4.9 Natural Gas System Reliability [215] In its evidence [Exhibit E-11], Eastward raised concerns about the potential for E1 to propose natural gas to electricity conversion as a strategic electrification project in its upcoming DSM portfo...

AI summary Eastward raised concerns about E1's proposed natural gas-to-electricity conversion project, citing a negative net benefit and low benefit-cost ratio. Eastward emphasized the need to account for natural gas system reliability in such projects. E1 responded that it agrees to consider reliability impacts in future proposals, which the Board accepted as sufficient.

5.0 SUMMARY OF BOARD FINDINGS p. pp. 78-79
5.0 SUMMARY OF BOARD FINDINGS [217] The Board finds it does not have the authority to approve E1's proposed BCA because the Public Utilities Act restricts the Board's ability to consider non-energy and societal benefits in assessing the co...

AI summary The Board cannot approve E1's proposed BCA due to Public Utilities Act restrictions on non-energy benefits. E1 must use PAC test and NS Power's WACC for DSM plan assessments. Strategic electrification must meet GHG and cost reduction criteria. Eastward is added to DSMAG. Portfolio-level evaluation allows overall cost-effective DSM plans despite individual measure failures.

100257Board Order 2 passages
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF AN APPLICATION by EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans BEFORE : Stephen T. McGrath, K.C., Chair Steven...

AI summary EfficiencyOne seeks approval for a new Benefit-Cost Analysis Test to evaluate Demand Side Management Plans under the Public Utilities Act. The proceeding is before a three-member regulatory board, including Chair Stephen T. McGrath and Members Steven M. Murphy and Darlene Willcott.

ORDER
ORDER EfficiencyOne (E1) applied to the Nova Scotia Energy Board on May 16, 2025, for approval of a New Benefit-Cost Analysis (BCA) Test for Evaluating Demand Side Management (DSM) Plans. The Board issued its Decision on December 10, 2025....

AI summary EfficiencyOne (E1) sought approval for a new BCA test for DSM plans, but the Nova Scotia Energy Board rejected it, directing E1 to use the PAC test with NS Power's WACC. The Board mandated portfolio-level screening, strategic electrification criteria, and inclusion of Eastward in the DSM Advisory Group. E1 may use a revised BCA test for supplemental information.

97702Letter EOne re: Application for Approval of Benefit Cost Analysis Test for Evaluating Demand Side Management (DSM) Plans 3 passages
Section 1 p. p. 0
James R. Gogan Direct +1 (902) 563 5920 [email protected] 292 Charlotte Street Suite 300 Sydney NS Canada B1P 1C7 Tel +1 (902) 563 1000 Fax +1 (902) 563 1113 Our File: 254441 May 16, 2025 Nova Scotia Energy Board 3rd Floor, Sum...

AI summary EfficiencyOne is seeking regulatory approval for a new Benefit Cost Analysis Test to evaluate Demand Side Management (DSM) Plans. This follows a previous request for approval of its 2023-2025 DSM Plan and a review of cost-effectiveness testing methodologies. The Board directed EfficiencyOne to work with the DSM Advisory Group to determine the optimal testing methodology for Nova Scotia.

Section 2 p. p. 0
ing methodology for Nova Scotia[:](#page-0-0) 1 1 Efficiencyone (E1) (Re), 2022 NSUARB 137 [M10473], Board Decision, paragraph 73. mcinnescooper.com The Board finds that E1's suggested approach is reasonable. The Board, therefore, directs...

AI summary The Nova Scotia Utility and Review Board directed Efficiencyone (E1) to develop an optimal DSM cost-effectiveness testing methodology with the DSMAG. Legislative changes in 2022 and 2024, including amendments to the Public Utilities Act and the Energy Reform (2024) Act, significantly impacted the BCA test.

Section 3 p. p. 0
t , SNS 2024, c 2 received Royal Assent. This legislation expanded the list of factors for the Board to consider in relation to all applications. Included among this list of factors are the following: - a) energy efficiency - b) sustainabl...

AI summary The legislation received Royal Assent in 2024 expanded the factors the Board must consider in applications, including energy efficiency, sustainable development, and greenhouse gas emissions reductions. These changes informed the development of a new BCA test by the DSMAG, which EfficiencyOne now recommends for approval by the Board.

97910Notice of Intervention - SBA 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act - and- IN THE MATTER OF: an application by EfficiencyOne for approval of a New Benefit-Cost Analysis Test for Evaluating SBA Consultant Melissa Whitten Daymark Energy Advi...

AI summary The Nova Scotia Energy Board is considering EfficiencyOne's application for approval of a new benefit-cost analysis test for evaluating Demand Side Management Plans under the Public Utilities Act. Melissa Whitten from Daymark Energy is involved as an SBA Consultant.

97912Notice of Intervention - EE 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act, RSNS 1989, c.380, as amended - and - IN THE MATTER OF: NSEB Matter No. M12282 – EfficiencyOne – New Benefits Cost Analysis Test for Evaluating Demand Side Management (DSM...

AI summary The Nova Scotia Energy Board is addressing a proceeding under the Public Utilities Act, involving EfficiencyOne's proposed new benefits cost analysis test for evaluating Demand Side Management (DSM) plans, referenced as NSEB Matter No. M12282.

97925Notice of Intervention - East Coast Environmental Law 2 passages
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act , RSNS 1989, c 380, as amended – and – IN THE MATTER OF: An Application by EfficiencyOne for approval of a new Benefit- Cost Analysis test for evaluating demand-side manag...

AI summary The Nova Scotia Energy Board is considering an application by EfficiencyOne under the Public Utilities Act for approval of a new Benefit-Cost Analysis test to evaluate demand-side management (DSM) plans. The proceeding involves regulatory review of a proposed methodological change for assessing DSM initiatives.

NOTICE OF INTERVENTION
NOTICE OF INTERVENTION TO: The Nova Scotia Energy Board ("Board") AND TO: EfficiencyOne - 1. East Coast Environmental Law Association (2007) ("East Coast Environmental Law") requests to participate in the above-noted proceeding as an Inter...

AI summary East Coast Environmental Law Association requests intervention in a Nova Scotia Energy Board proceeding involving EfficiencyOne's DSM plans. The organization seeks to ensure the Board's mandate considers a new Benefit-Cost Analysis test for sustainable development. They aim to address issues related to environmental and climate justice, emphasizing sustainable prosperity.

97928Notice of Intervention - KMKNO & ANSMC 2 passages
RE: An Application by EfficiencyOne for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans p. p. 0
RE: An Application by EfficiencyOne for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans Please find enclosed the following document: - (i) Notice of Intervention on behalf of: - a) Kwilmu'kw Maw-klu...

AI summary EfficiencyOne seeks approval for a new Benefit-Cost Analysis Test to evaluate Demand Side Management Plans. The Kwilmu'kw Maw-klusuaqn Negotiation Office (KMKNO) and Assembly of Nova Scotia Mi'kmaw Chiefs (ANSMC) have filed a Notice of Intervention. Twila Gaudet, Director of Consultation at KMKNO, signed the notice.

NOTICE OF INTERVENTION of KWILMU'KW MAW-KLUSUAQN NEGOTIATION OFFICE and ASSEMBLY OF NOVA SCOTIA MI'KMAQ CHIEFS p. p. 0
NOTICE OF INTERVENTION of KWILMU'KW MAW-KLUSUAQN NEGOTIATION OFFICE and ASSEMBLY OF NOVA SCOTIA MI'KMAQ CHIEFS TAKE NOTICE that Kwilmu'kw Maw-klusuaqn Negotiation Office (KMKNO) hereby seeks to intervene in the above Applications and Proce...

AI summary KMKNO and ANSMC intervene in a regulatory proceeding, asserting Mi'kmaw Aboriginal title to Nova Scotia and opposing potential adverse impacts on Indigenous rights. They seek input on the modified Benefit-Cost Analysis Test for Demand Side Management Plans, emphasizing sustainable development and consultation processes.

97936Notice of Intervention - CA 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The PUBLIC UTILITIES ACT -and- IN THE MATTER OF: An Application by EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans

AI summary The Nova Scotia Energy Board is considering an application by EfficiencyOne under the Public Utilities Act to approve a new benefit-cost analysis test for evaluating demand side management plans. The proceeding involves regulatory review of a proposed methodology for assessing energy efficiency initiatives.

97942Notice of Intervention - DOE 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act , RSNS 1989, c 380 as amended - and – IN THE MATTER OF: an application by EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Managem...

AI summary The Nova Scotia Energy Board is considering an application by EfficiencyOne for approval of a new benefit-cost analysis test to evaluate demand side management plans under the Public Utilities Act. The proceeding involves regulatory review of proposed methodologies for assessing energy efficiency initiatives.

97956Participant List 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF AN APPLICATION BY EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans

AI summary The Nova Scotia Energy Board is considering an application by EfficiencyOne to approve a new benefit-cost analysis test for evaluating demand side management plans. The proceeding involves assessing the methodology proposed by EfficiencyOne for regulatory approval.

98015Board Letter re: Extension for IG 1 passage
Section 1 p. pp. 0-1
June 11, 2025 [[email protected]](mailto:[email protected]) Nancy Rubin Stewart McKelvey Suite 600 – 1741 Lower Water Street P.O. Box 997 Halifax, NS B3J 2X2 Dear Ms. Rubin: M112282 - EfficiencyOne - New Benefit Cost Anal...

AI summary The Board grants an extension to the Industrial Group for filing Information Requests related to EfficiencyOne's new benefit cost analysis test for Demand Side Management (DSM) plans, moving the deadline to June 16, 2025. The original request was dated June 11, 2025.

98028Synapse (E1) IR 1 to 24 9 passages
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: AN APPLICATION by EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans

AI summary The Nova Scotia Energy Board is considering an application by EfficiencyOne under the Public Utilities Act for approval of a new benefit-cost analysis test to evaluate demand side management plans. The proceeding focuses on methodological standards for assessing energy efficiency initiatives.

Request IR-1:
Request IR-1: - Refer to EfficiencyOne's (E1) Evidence at page 28, which includes the list of distribution impacts included in the new benefit-cost analysis (BCA) test. - a. Did the Demand Side Management Advisory Group (DSMAG) consider in...

AI summary The document references EfficiencyOne's evidence on distribution impacts in a new BCA test and asks whether DSMAG and EFG considered including Distribution Voltage in the Nova Scotia Jurisdictional Benefit Cost Test but valuing it at zero. It seeks explanations for their inclusion or exclusion decisions.

Request IR-2:
Request IR-2: Refer to E1's Evidence at page 33, which states "EFG is proposing to apply the Federal social cost of carbon to the savings (after accounting for the avoided cost of carbon portion included in the current avoided cost of ener...

AI summary Request IR-2 asks for an Excel example of a calculation applying the Federal social cost of carbon to savings, avoiding double-counting by accounting for NS Power's current avoided cost of energy (August 2024). The example is requested based on E1's Evidence at page 33, which outlines EFG's proposal.

Request IR-3:
Request IR-3: - Refer to E1's Evidence at page 35, Table 11: Test Case Application of BCA Test (Heat Pumps). - a. Please provide all supporting analysis and workpapers in Microsoft Excel format with all cells unlocked, and formulas intact....

AI summary The request asks E1 to provide supporting analysis and workpapers in Excel format for their BCA test case on heat pumps, and inquires if they used the TRC Test methodology. It references E1's Evidence at page 35, Table 11, and seeks clarification on whether a BCA was conducted using the TRC Test.

Request IR-4:
Request IR-4: Refer to pages 8 and 9 of the Evidence of David Hill, regarding the statements "The numbers in the cells of this table indicate how many of the DSMAG organizations indicated each policy (in the rows) was relevant to each impa...

AI summary The text requests clarification on why policy relevance, as indicated in a table from David Hill's evidence, implies support for including specific impact categories in the BCA test. It references DSMAG and EFG interpretations of policy and legislative support for factors like GHG emissions, resilience, and DEI impacts.

Request IR-8:
Request IR-8: - Refer to Appendix B, Development of a Jurisdictional Benefit Cost Analysis Framework for Nova - Scotia report prepared by EFG (hereinafter, the "EFG Report") on pages 12-14. Table 1 indicates - that all Electric Utility Sys...

AI summary Request IR-8 seeks clarification on whether all Electric Utility System Impacts, including those deemed not applicable or not material, are included in the proposed Nova Scotia Test, referencing the EFG Report's Tables 1-3 and Appendix B.

Request IR-11:
Request IR-11: - Refer to the EFG Report on page 17, which states "For host customer impacts the new - jurisdictional test should include both measure costs and non-energy benefits. EFG recommends - a proxy adder approach to estimate the c...

AI summary The EFG Report recommends using proxy adders to estimate non-energy benefits for host customers, varying by DER type and segment. It suggests this approach addresses harder-to-quantify benefits, with rationale in Section V and Appendix F. Questions ask if DSMAG or EFG discussed jurisdiction-specific studies for NEB and whether proxy adders are preferred over such studies.

Request IR-14:
Request IR-14: - Page 35 of the EFG Report states that the "best option may be to consider ancillary services as embedded within the generation and capacity avoided costs." - a. Please explain how the avoided costs for generation and capac...

AI summary Page 35 of the EFG Report suggests embedding ancillary services within generation and capacity avoided costs. The request seeks clarification on how avoided costs account for ancillary services' impact, highlighting a key debate in cost methodology and resource valuation.

Request IR-20:
Request IR-20: EFG states that the "consultant team developed two quantitative examples to translate proxy values into impacts per kWh and per MMBtu NEI values" on page 47 of the EFG report. Please provide all associated workpapers in Micr...

AI summary EFG states that their consultant team developed two quantitative examples to translate proxy values into impacts per kWh and per MMBtu NEI values on page 47 of the EFG report. The request is for all associated Excel workpapers with unlocked cells and intact formulas.

98029ECEL (E1) IR 1 2 passages
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act , RSNS 1989, c 380, as amended – and – IN THE MATTER OF: An Application by EfficiencyOne for Approval of a New Benefit- Cost Analysis Test for Evaluating Demand-side Manag...

AI summary The Nova Scotia Energy Board is considering an application by EfficiencyOne under the Public Utilities Act for approval of a new benefit-cost analysis test to evaluate Demand-side Management (DSM) plans. The proceeding involves regulatory review of a proposed method for assessing DSM initiatives.

Request IR-1
Request IR-1 Refer to Exhibit E-1, "Notice of Application and Evidence", within the "Evidence" section, dated May 16, 2025. At page 18, lines 21-25, EfficiencyOne states: "EFG's scope included assisting E1 in leading a series of DSMAG work...

AI summary EfficiencyOne states that EFG's scope included leading DSMAG workshops, researching Nova Scotia legislation, and ensuring cost-effectiveness test design aligns with the National Standard Practice Manual (NSPM). The request asks for an explanation of NSPM's application in North America and its relevance to Nova Scotia's demand-side management (DSM) cost-effectiveness testing.

98032EE (E1) IR 1 to 12 1 passage
2 Reference: Evidence Page 7: A benefit-cost ratio threshold of 1.0 or
2 Reference: Evidence Page 7: A benefit-cost ratio threshold of 1.0 or 3 greater of a DSM Plan must always be satisfied at the portfolio 4 level. While measures that do not meet the ratio threshold can 5 be included, E1 must justify their...

AI summary The text discusses the requirement for a benefit-cost ratio threshold of 1.0 or greater for a DSM Plan. Measures that do not meet this threshold can still be included if E1 justifies their inclusion based on the Balanced Plan Approach. The text requests a detailed description of the process E1 intends to use for this justification.

98033NSEB (E1) IR 1 to 46 27 passages
Request IR-2:
Request IR-2: - Page 2 of 38 of EfficiencyOne's (E1) Evidence states: "Including non-utility impacts reflects both - best practice in benefit cost analysis test design, as well as recently enacted provincial legislation. - While the relati...

AI summary EfficiencyOne (E1) argues that including non-utility impacts in the BCA test framework aligns with best practices and provincial legislation like the Public Utilities Act and Energy Reform (2024) Act . The request seeks clarification on indirect benefits/costs, weight assignments, sensitivity analysis, policy alignment, and performance requirements for non-utility benefits in DSM evaluations.

Request IR-3:
Request IR-3: - With regards to Table 2 on page 4 of 38 of E1's Evidence: - a) Did E1 review any Canadian jurisdictions with similar policy objectives as Nova Scotia to assess how the current TRC test aligns with standard for cost-effectiv...

AI summary Request IR-3 asks E1 (EfficiencyOne) to explain whether it reviewed Canadian jurisdictions with similar policy objectives to Nova Scotia regarding the TRC test's alignment with cost-effectiveness standards. It also requests a comparative table and identification of similar DSM policy objectives in listed states.

Request IR-4:
Request IR-4: - Page 4 of 38 discusses the shortfalls of the TRC test as ignoring the symmetrical benefits - corresponding to a cost, arguing that such an approach "unjustly favour or disadvantage certain - resources." - a) In the BCA are...

AI summary The text critiques the TRC test for ignoring symmetrical benefits, leading to unfair resource treatment. It questions the BCA's completeness, asking if benefits without costs or costs without benefits are included, highlighting potential methodological gaps in cost-benefit analysis.

Request IR-5:
Request IR-5: - Please describe how the BCA as proposed by E1 aligns with the Treasury Board of Canada - Secretariat Canada's Cost-Benefit Analysis Guide for Regulatory Proposals, 2019 and Canada's - Policy on Cost-Benefit Analysis (2018)...

AI summary Request IR-5 asks EfficiencyOne (E1) to explain how its proposed Benefit-Cost Analysis (BCA) aligns with Canada's 2019 Cost-Benefit Analysis Guide and 2018 Policy on Cost-Benefit Analysis. Specific elements under review include scope, time horizon, market distortions, health impacts, and social costs of greenhouse gases.

Request IR-6:
Request IR-6: - Page 17 of 38 of E1's Evidence states: "To perform cost effectiveness testing of strategic - electrification you must include the relevant benefits and costs. In the case of strategic - electrification, the electric utility...

AI summary The document raises two key questions regarding strategic electrification's cost-effectiveness testing. First, whether host customer costs (e.g., EV chargers) are included in BCA tests. Second, how the proposed BCA ensures strategic electrification reduces electricity costs as mandated by the Public Utilities Act's definition of demand-side management.

Request IR-7:
Request IR-7: - On page 18 of 38 of E1's Evidence, a hyperlink to the "National Energy Screening Project (NESP), National Standard Practice Manual (NSPM) for Benefit-Cost Analysis of Distributed Energy Resource" is provided: - a) Please de...

AI summary Request IR-7 seeks information on the National Energy Screening Project (NESP), deviations from the NSPM in the proposed BCA test, use of the MTR handbook for quantifying benefits/costs, and data from the DSPs on states' adoption of NSPM, SCT, and resilience metrics in energy efficiency evaluations.

Request IR-8:
Request IR-8: - With respect to the NSPM for Benefit-Cost Analysis of Distributed Energy Resource: - a) Please identify any Canadian jurisdictions that have adopted the NSPM as their standard approach to BCA for DSM or Distributed Energy R...

AI summary Request IR-8 seeks information on Canadian jurisdictions adopting Nova Scotia Power's (NSPM) BCA methodology for DER/DSM, differences in application compared to E1's proposal, and alternative BCA methodologies used, including California's Standard Practice Manual.

Request IR-9:
Request IR-9: - Please provide a summary of the feedback provided by the DSMAG regarding the final draft EFG - report, as referenced on page 20 of 38 of E1's Evidence. - Request IR-10: - Table 4: NSPM BCA Guiding Principles - a) Principle...

AI summary The document outlines regulatory requests related to DSM and DER BCA analyses. Key issues include clarifying the basis for comparing DER scenarios in BCA, identifying unlisted utility impacts, and evaluating the inclusion of policy goals in BCA tests. E1 is asked to confirm the Board's discretion in approving portfolios despite BCA results.

Request IR-13:
Request IR-13: - Page 30 of 38 of E1's Evidence states: "The impact of changes in pipeline gas consumption are based on commodity prices, and do not reflect gas utility system impacts. However, presuming gas commodity prices are the larges...

AI summary E1's Evidence in Request IR-13 questions whether avoided gas costs in DSM include base energy and transportation charges, not just commodity prices. The BCA test is based on commodity prices as an approximation. The request is for confirmation if avoided costs include those other charges.

Request IR-17:
Request IR-17: - Please provide supporting empirical evidence demonstrating causation for the following Host - Customer Impacts: - a) energy efficiency investments and increases in business productivity in industries that operate in Nova S...

AI summary The document requests empirical evidence linking energy efficiency investments in Nova Scotia to increased business productivity, economic benefits, and health/safety improvements, emphasizing the need for causation.

Request IR-20:
Request IR-20: - a) Please cite the source for the cost of carbon used in the BCA. - b) Please explain how the proxy for the host customer was selected and measured. - i. Please describe how the proxy is estimated and applied in the BCA. -...

AI summary Request IR-20 seeks clarification on the BCA's carbon cost source, proxy selection methodology, discount rate justification, and use of Canadian vs. American rates in NSPM. Questions focus on transparency, methodology, and regional applicability of economic assumptions.

Request IR-21:
Request IR-21: - Table 10: Impact Categories for BCA Test identifies that Impacts Measured for Gas is embedded in Other Fuels, Resilience is embedded in Host Customer, and that Public Health is embedded in another GHG Emissions. Please con...

AI summary The text references Table 10 of the BCA Test, which lists impact categories such as Gas embedded in Other Fuels, Resilience in Host Customer, and Public Health in GHG Emissions. It requests confirmation and an explanation for their inclusion in the presentation.

Request IR-23:
Request IR-23: - Page 8 of 18 of Mr. Hill's evidence notes that criteria air pollutant non-utility impacts for the - proposed BCA test are based on modelling of estimated health impacts for the New England - region. Are there any reasons t...

AI summary The document raises a question about whether health impact models from the New England region, used in the BCA test, are applicable to Nova Scotia, given potential differences in health impacts.

Request IR-25:
Request IR-25: - Table 3 on Page 12 of 18 of Mr. Hill's Evidence: Data Sources and Application in Developing Recommended Nova Scotia Test: - a) For the Utility System Impact "Program Administration and Incentives", the Application in Repor...

AI summary Request IR-25 seeks clarification on assumptions in the BCA related to program administration, fuel price adjustments, placeholder cost assumptions, and proxy values for non-energy benefits. Questions focus on EFG's assumptions, carbon price removal rationale, US Energy Information Administration fuel cost data, and adjustments to avoid double-counting energy benefits.

Request IR-26:
Request IR-26: - Please provide the proposed BCA in excel format with cells intact and worksheets unprotected. - Additionally, provide references for each measure, with empirical evidence that supports the link - between the benefit and as...

AI summary Request IR-26 seeks the proposed Benefit-Cost Analysis (BCA) in Excel format with intact cells and unprotected worksheets, along with empirical evidence linking each measure's benefits to costs. The request emphasizes transparency in data presentation and rigorous validation of cost-benefit claims.

Request IR-27:
Request IR-27: - Page 8, under Non-Energy benefits states "If host customer benefits are not included in a jurisdictional test, then the host customer costs should be excluded." - a) Please describe the host customer costs and if they incl...

AI summary Request IR-27 seeks clarification on host customer costs and benefits related to E1 programs, specifically whether E1's costs are included and if benefits are uniform across programs. It references a rule excluding host customer costs if benefits are not included in jurisdictional tests.

Request IR-28:
Request IR-28: - Page 8, under Not Material explains that some outcomes that don't produce a large enough effect - are excluded from the BCA. Please identify and briefly describe the outcomes/impacts identified - by E1/EFG/DSMAG that have...

AI summary Request IR-28 asks to identify outcomes excluded from the BCA by E1/EFG/DSMAG due to insufficient impact. The query focuses on excluded impacts not producing a large enough effect in the analysis.

Request IR-30:
Request IR-30: - Table 4: Non-Utility Impacts Consistent with Nova Scotia Policy Goals in the Notes for Econ - Devt/Jobs state that these impacts should be separate from the BCA calculations to avoid double - counting. Please describe how...

AI summary The text requests E1 to explain how non-utility impacts related to Nova Scotia policy goals are separated from BCA calculations to avoid double-counting in their analysis.

Request IR-31:
Request IR-31: - Text Box 1: Summary of Key EFG Recommendations item 3) states that actual avoided capacity - cost stream should have a planning reserve margin adjustment. It also states that constrained - and unconstrained locations can b...

AI summary Request IR-31 seeks explanations on three aspects of E1's costing methodology: (a) avoided capacity adjustment and data sources, (b) constrained/unconstrained transmission/distribution locations influenced by E1 programs, and (c) basis for estimating transmission/distribution cost growth.

Request IR-33:
Request IR-33: - Text Box 1: Summary of Key EFG Recommendations item 8) recommends using benefit per kWh - for local non-greenhouse gas air pollutants using estimates from the US Environmental Protection - Agency for New England. - a) Plea...

AI summary Request IR-33 seeks clarification on using benefit per kWh for local non-GHG pollutants in Nova Scotia's BCA, referencing E1's programs and US EPA data from New England. It asks to identify local pollutants, explain appropriateness of local vs. New England data, and describe pollutant sources/measures.

Request IR-34:
Request IR-34: - Text Box 1: Summary of Key EFG Recommendations item 11) states that secondary tests are - not meant to be used in a sequential fashion or as a replacement of the recommended primary - test. Please elaborate on this recomme...

AI summary Request IR-34 seeks clarification on EFG's recommendation that secondary tests should not replace primary tests in BCA evaluations for demand-side management. It asks how secondary tests would function in Nova Scotia's context, particularly regarding portfolio-level cost-effectiveness assessments.

Request IR-35:
Request IR-35: - Please confirm that Table 5: Illustrative Example of Recommended Nova Scotia Test, provides - only the summary of the benefits associated with 1,000 Heat Pumps Replacements in Program - Year 2026. If the BCA test is and me...

AI summary Request IR-35 seeks clarification on Table 5's scope, which summarizes benefits of 1,000 heat pump replacements in 2026. It also asks if E1 will provide detailed BCA calculations if the Board approves the BCA test methodology.

Request IR-36:
Request IR-36: - Page 20 describes the example in Table 5 as showing that the cost effectiveness of the 1,000 - heat pump replacements is influenced by which fuel is displaced. - a) Are the costs to E1 for heat pump incentives and programs...

AI summary The text examines the cost-effectiveness of 1,000 heat pump replacements, questioning whether E1's costs are limited to Financial Incentives and Program Administration, and how displaced fuel affects cost-effectiveness. It references Table 5 and seeks clarification on additional costs incurred by E1.

Request IR-37:
Request IR-37: - Table 6: Illustrative Example Present Value Benefits, Costs and Ratios, provides the present - value of the heat pump replacements. Not limited to this table, how many years will the costs and - the benefits be discounted...

AI summary Request IR-37 asks about the discount period for present value calculations in Table 6, which illustrates benefits, costs, and ratios for heat pump replacements. The request seeks clarification on the number of years used to discount costs and benefits, and the specific years associated with each impact.

Request IR-38:
Request IR-38: - Page 36, Credit and collections, highlights that NS Power hasn't found a change for costs associated with delinquent accounts, disconnection and reconnection costs. Why does E1 consider it appropriate to include this measu...

AI summary Request IR-38 questions E1's inclusion of credit and collection costs in DSM, challenging how E1 attributes savings to DSM versus other programs like Customer Energy Management or Low-Income Working Group initiatives. It also asks why DSM incentives are expected to significantly reduce credit and collection expenditures, particularly for low-income renters.

Request IR-40:
Request IR-40: - Table 9 identifies the impacts included in the BCA. Please explain the reasons that E1 considers - the effects from DSM on Transmission and Distribution are significant enough to be included.

AI summary Request IR-40 asks E1 to justify including DSM's impacts on transmission and distribution in the BCA. The inquiry focuses on why these effects are deemed significant enough to be part of the analysis, highlighting the importance of transmission and distribution considerations in DER evaluations.

Request IR-41:
Request IR-41: - Table 13 in Appendix B lists the Host Customer Impacts. How does E1 propose to quantify the - following: - a) Transaction Costs - b) Risks - c) Resilience - d) Productivity - e) Comfort - f) Amenity - g) Empowerment - h) P...

AI summary The document requests E1 to explain how it quantifies various Host Customer Impacts, including transaction costs, risks, resilience, and others, as listed in Table 13 of Appendix B.

98036SBA (E1) IR 1 to 20 11 passages
Request IR-3:
Request IR-3: - Refer to Exhibit E-1, the Development of a Jurisdictional Benefit Cost Analysis Framework for - Nova Scotia (the "Report"), Appendix B, Table 14, pages 45-46 of 68. For the "host customer" - impact of the NEB category, prov...

AI summary Request IR-3 seeks justification for proxy adder percentages in the NEB category's host customer impact analysis, referencing Exhibit E-1, Appendix B, Table 14. It also requests a sensitivity analysis of portfolio BCA ratios under ±50% changes to adders.

Request IR-4:
Request IR-4: - Refer to Exhibit E-1, the Report, page 20 of 68. Describe the safeguards built into the BCA Test - methodology to prevent the double counting of benefits such as where avoided GHG benefits - and avoided fuel cost benefits c...

AI summary Request IR-4 asks for an explanation of safeguards in the BCA Test methodology to prevent double-counting of benefits, specifically overlapping avoided GHG emissions and avoided fuel cost benefits. The focus is on ensuring accurate benefit quantification in regulatory analysis.

Request IR-5:
Request IR-5: - Refer to Exhibit E-1, the Application, E1 Evidence, Table 11, page 35 of 38. Beyond the heat - pump test case, provide at least two additional test runs, other than energy efficiency lighting, - demonstrating the new BCA's...

AI summary Request IR-5 seeks additional test runs beyond the heat pump and energy efficiency lighting examples to demonstrate the new BCA's operation, including intermediate outputs, as outlined in Exhibit E-1, Table 11, page 35 of 38.

Request IR-6:
Request IR-6: - Please provide a list of each potential benefit being proposed to be included in the new BCA test - and note for each benefit whether the BCA Test will be assuming that the numerical value of the - benefit is the same throu...

AI summary Request IR-6 seeks a list of benefits for the new BCA test, including whether benefits are assumed constant over time. It questions how the test will address scenarios like NSPI’s decarbonized supply mix, which would render carbon savings zero.

Request IR-7:
Request IR-7: - Refer to Exhibit E-1, the Application, Table 2, page 4 of 38. For each listed state: - a) Please provide the specific state's stated policy objectives, legislation, or publicly adopted goals that align with Nova Scotia legi...

AI summary Request IR-7 seeks alignment of state policies with Nova Scotia legislation, requiring specific legislative references and a comparison of cost/benefit types in Nova Scotia's BCA against state cost-effectiveness testing frameworks.

Request IR-8:
Request IR-8: - Refer to Exhibit E-1, the Application, page 18 of 38, line 5. Regarding the creation of green jobs and stimulating economic growth, please provide the results of econometric modeling that EOne has performed or commissioned...

AI summary Request IR-8 asks EOne to provide econometric modeling results demonstrating net jobs created and economic growth from adopting the BCA Test compared to the current methodology, including work papers with spreadsheets. The request references Exhibit E-1, page 18, line 5 of the Application.

Request IR-9:
Request IR-9: - Refer to Exhibit E-1, the Application, page 18 of 38, line 21-25, specifically where it states "…ensuring the design of the cost-effectiveness test adhered to the National Standard Performance Manual (NSPM) where possible…"...

AI summary Request IR-9 seeks clarification on adherence to the National Standard Performance Manual (NSPM) in cost-effectiveness testing and how benefits are incorporated into the proposed Benefit-Cost Analysis (BCA). It asks for detailed descriptions of non-compliance with NSPM and the methodology for aligning BCA elements with NSPM standards.

Request IR-17:
Request IR-17: - Please list the programs and potential funding level that are expected to pass the new BCA Test - that would not have passed the current cost-benefit testing.

AI summary Request IR-17 seeks programs and funding levels expected to pass the new BCA Test but fail under current cost-benefit testing. Key entities include Nova Scotia Power Inc. (NSPI) and Demand Side Management (DSM), with reference to the National Standard Performance Manual (NSPM).

Request IR-18:
Request IR-18: - Please list all the factors that EOne will evaluate to decide on program funding in addition to the - proposed new BCA test.

AI summary Request IR-18 asks EOne to list factors beyond the proposed new BCA test for evaluating program funding. The context involves DSM programs and NSPI, with BCA and DSM as key acronyms.

Request IR-19:
Request IR-19: - Please provide efficiency program funding per capita in each Canadian province and if the cost-effectiveness test includes all the 'benefits' being proposed in this application. - a) Please indicate if the programs are 100...

AI summary The request seeks per capita efficiency program funding data across Canadian provinces and clarification on whether the cost-effectiveness test includes all proposed benefits, along with inquiries about program financing arrangements.

Request IR-20:
Request IR-20: - Please comment on whether a test similar to the proposed BCA Test should be used by the following: - a) Natural Gas Utilities for customer programs and resource planning. - b) Water Utilities for customer programs and reso...

AI summary Request IR-20 seeks input on applying a BCA Test to Natural Gas and Water Utilities, the Province of Nova Scotia's budgeting, and NSPI's resource planning and capital expenditure criteria. The proposal aims to standardize evaluation methods for customer programs, resource planning, and infrastructure decisions.

98098IG (E1) IR 1 to 16 7 passages
Preamble
- 8 (d) Does E1s assertion that its proposed BCA test is in the "best interest of 9 ratepayers" indicate that the new cost effectiveness test will continue to 10 determine whether its Plan is affordable and result in the lowest long-term 1...

AI summary The question challenges E1s' assertion that its proposed BCA test is in the best interest of ratepayers, asking whether the new cost effectiveness test will ensure affordability and the lowest long-term cost of electricity.

12 Request IR-2:
12 Request IR-2: 13 Reference: E-1, Evidence, page 2 of 38. Including non-utility impacts reflects both best practice in benefit cost analysis test design, as well as recently enacted provincial legislation. While the relative weight of sp...

AI summary The text argues that including non-utility impacts in the cost-effectiveness framework is appropriate, citing best practices and provincial legislation. The decision to include such impacts should be based on their relevance to DSM activities in Nova Scotia, guided by policy priorities and legislative objectives.

- 28 (b) Please compare the new BCA test against the current TRC test for the 29 three examples provided in section 11 of E1's Evidence.
- 28 (b) Please compare the new BCA test against the current TRC test for the 29 three examples provided in section 11 of E1's Evidence. 1 2 (i) In the calculation provided, do the "non-energy impacts" outweigh the "energy-related" impacts...

AI summary The text outlines several requests to compare the new BCA test with the current TRC test, focusing on non-energy impacts, relative weights, and additional work required. It also references the National Standard Practice Manual and asks about the principle of symmetry in the BCA test.

21 Request IR-10:
21 Request IR-10: - 22 References: E-1, Evidence, page 26, Table 5; and pages 34-35, Table 9 and 10. - 23 Preamble: E1 has included a number of non-utility system impacts in relation to the 24 new proposed BCA Test, including a "Societal"...

AI summary Request IR-10 seeks clarification on the legislative basis for including 'public health' in the Benefit-Cost Analysis (BCA) Test. E1 argues that public health impacts, such as medical cost changes, are embedded in the BCA, citing Tables 9 and 10. The NSUARB is asked to justify its authority to consider public health in utility regulation.

17 Request IR-14:
17 Request IR-14: - 18 Reference: E-1, Appendix B. - 19 Does the requested approval of a new BCA include the following as approved values, or are they 20 inputs that would be considered at each future DSM Plan review: - 21 (a) use of a 2%...

AI summary The document questions whether the approval of a new BCA includes specific values (2% social discount rate and NEB proxy adders) as fixed approvals or if they are inputs for future DSM Plan reviews, referencing E-1, Appendix B.

23 Request IR-15:
23 Request IR-15: - 24 Please provide a mathematical representation of the proposed BCA test, including each value 25 that would be summed as part of the "benefit" portion of the calculation, and each that would be 26 summed as part of the...

AI summary The document requests a mathematical representation of the proposed BCA test, detailing components of benefits and costs, including incentives to customers, energy efficiency industry participants, and utility administrative costs.

2 Request IR-16:
2 Request IR-16: - 3 Please indicate if, or how, the proposed BCA test can help inform the appropriate level of - 4 incentives or subsidies for participation in efficiency initiatives and provide an example.

AI summary Request IR-16 asks how the proposed Benefit-Cost Analysis (BCA) test can inform the appropriate level of incentives or subsidies for participation in efficiency initiatives, seeking an example.

98396Letter E1 re: RIRs 1 passage
Section 1 p. p. 0
James R. Gogan Direct +1 (902) 563 5920 [email protected] 292 Charlotte Street Suite 300 Sydney NS Canada B1P 1C7 Tel +1 (902) 563 1000 Fax +1 (902) 563 1113 Our File: 254441 July 4, 2025 Nova Scotia Energy Board 3 rd Floor, 16...

AI summary EfficiencyOne submits responses to multiple information requests in regulatory proceeding M12282 concerning a proposed new benefit-cost analysis test for evaluating demand side management plans. Responses are provided by various stakeholders including environmental groups, industry representatives, and the Nova Scotia Energy Board.

98575Letter from NS Power re: not filing evidence 1 passage
Section 1 p. pp. 0-1
July 17, 2025 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: M12282 – EfficiencyOne Application for a Benefit Cost Analysis Test for DSM Evaluation Dear Ms. Henwood: N...

AI summary NS Power is not submitting evidence regarding EfficiencyOne's application (M12282) for a Benefit Cost Analysis Test for DSM Evaluation. The application is being processed by the Nova Scotia Energy Board, with Jennifer Ross of NS Power informing the clerk, Crystal Henwood, of their non-participation. Tim Wood and Jamie Chipp are cc'd.

98792NSEB (Bowman - IG) IR 1 to 4 2 passages
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: AN APPLICATION by EfficiencyOne for Approval of New Benefit Cost Analysis Test for Evaluating Demand Side Management (DSM) Plans INFORMATION REQU...

AI summary Nova Scotia Energy Board requests information from Bowman Economic Consulting Inc. regarding a cost analysis test for Demand Side Management (DSM) plans under the Public Utilities Act. EfficiencyOne applied for approval of a new benefit. Responses are due August 21, 2025.

Request IR-4:
Request IR-4: - On page 15, it is stated that, "The use of a primary screening tool can help reach conclusions on - the cost-effectiveness of a plan, but is not an absolute requirement nor veto on any given plan - component." Given this, p...

AI summary The text requests clarification on why the choice of primary screening tool (program administrator cost test vs. Proposed BCA) affects the evaluation of a plan's cost-effectiveness, noting that such tools are not absolute requirements.

98795IG (Synapse) IR 1 to 2 2 passages
Preamble
1 2025 M12282 2 NOVA SCOTIA ENERGY BOARD 3 IN THE MATTER OF: The Public Utilities Act 4 IN THE MATTER OF: An Application by EfficiencyOne for approval of a New Benefit- 5 Cost Analysis Test for Evaluating Demand Side Management 6 Plans 7 8...

AI summary EfficiencyOne seeks approval for a new Benefit-Cost Analysis (BCA) test to evaluate demand-side management plans. The Industrial Group requests clarification from Synapse Energy Economics on whether Synapse considered the Public Utilities Act's requirement that DER activities serve customers' best interests and whether a broad societal-type BCA test aligns with Nova Scotia policy goals.

13 Reference: Exhibit E-9 page 23.
13 Reference: Exhibit E-9 page 23. - 14 (a) Does Synapse's support of the E1 proposed BCA test consider the source 15 of funds for the DER programming? Specifically, given the funds for the 16 programming are derived from utility rates, do...

AI summary The text raises two questions about Synapse's BCA test for DER programming. Question (a) asks if the BCA appropriately links benefits/costs to utility functions (vs. societal perspective) given funding from utility rates. Question (b) inquires whether non-monetary benefits like comfort and empowerment meet utility principles for inclusion in electricity rates.

98796ECEL (IG) IR 1 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act , RSNS 1989, c 380, as amended – and – IN THE MATTER OF: An Application by EfficiencyOne for Approval of a New Benefit- Cost Analysis Test for Evaluating Demand-side Manag...

AI summary The Nova Scotia Energy Board is considering EfficiencyOne's application to approve a new benefit-cost analysis test for evaluating demand-side management (DSM) plans under the Public Utilities Act, RSNS 1989, c 380, as amended.

98801Synapse (IG) IR 1 to 3 4 passages
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: AN APPLICATION by EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans

AI summary The Nova Scotia Energy Board is considering an application by EfficiencyOne for approval of a new benefit-cost analysis test to evaluate demand side management plans under the Public Utilities Act. The proceeding involves regulatory review of proposed methodologies for assessing energy efficiency initiatives.

Request IR-1:
Request IR-1: - Refer to the Evidence of Patrick Bowman at page 14, which describes the PAC including the benefits of added utility revenue for electrification measures. - a. Do energy efficiency measures impact utility revenues? - b. Why...

AI summary The document references Patrick Bowman's evidence on PAC and its benefits for utility revenue from electrification. It includes four questions about energy efficiency's impact on revenues, treatment of electrification measures, other jurisdictions' BCA tests, and use of PAC as a primary test.

Request IR-2:
Request IR-2: - Refer to the Evidence of Patrick Bowman at page 15, which states that "E1 has proposed its BCA include multiple specific inputs that are not consistent with methods and assumptions for alternative resource investments". - a...

AI summary The document references Patrick Bowman's evidence that E1's BCA includes inputs inconsistent with alternative resource investment methods. The Board seeks clarification on whether alternative resource investments are approved similarly to the E1 DSM Plan and if a BCA is required for such investments, specifying the test used.

Request IR-3:
Request IR-3: - Refer to the Evidence of Patrick Bowman at page 18, which states "A RIM test should not be applied as a screening test for energy efficiency, as it can derive excessively narrow metrics and fail to measure proper cost-effec...

AI summary Patrick Bowman argues against using the RIM test as a screening tool for energy efficiency due to its narrow metrics. The proceeding questions why revenue changes should be considered in the PAC test and how this differs from the RIM test's approach.

99100Letter E1 re: Witnesses/counsel 1 passage
Section 1 p. p. 0
Our File: 254441 August 26, 2024 Nova Scotia Energy Board 3 rd Floor, 1601 Lower Water Street Halifax, Nova Scotia B3J 3S3 Dear Ms. Henwood, RE: M12282 EfficiencyOne Application for Approval of a New Benefit-Cost Analysis Test for Evaluati...

AI summary EfficiencyOne notifies the Nova Scotia Energy Board of participants for the hearing in M12282, including counsel James Gogan and Lucia Westin-Eastaugh, and witnesses Gina Thompson, Kate McDonald, David Hill, and Christopher Neme. Enclosures include resumes for expert witnesses.

99107Letter ECEL re: Hearing Logistics 1 passage
Section 1 p. p. 0
East Coast Environmental Law 6061 University Ave. PO Box 15000 Halifax, NS B3H 4R2 Nova Scotia Energy Board 3rd Floor, 1601 Lower Water St. Halifax, NS B3J 3S3 August 27, 2025 Dear Ms. Henwood, Re: M12282 – EfficiencyOne: Application for A...

AI summary East Coast Environmental Law (ECEL) confirms participation in the hearing for M12282, represented by Kostantina Northrup. ECEL will not call witnesses and does not object to virtual testimony by other parties' witnesses. The proceeding involves EfficiencyOne's application for a new benefit-cost analysis test for Demand Side Management (DSM) plans.

99112Email NSEB re: Extension approved for IG to provide hearing logistics 1 passage
\ \ EXTERNAL EMAIL / COURRIEL EXTERNE \ \ p. p. 0
mailto:[email protected])[[email protected]](mailto:[email protected])>; Patel, Girish [ ; Patrick Bowman [ ; Pronko, Steve [ ; Rebekah Powell [ ; Scott, Jessica [ ](mailto:Jessica.Scott@nova...

AI summary Matter M12282 involves EfficiencyOne proposing a new benefit-cost analysis test for evaluating demand-side management (DSM) plans. The email chain includes stakeholders such as Nova Scotia government officials, consultants, and legal representatives, indicating a regulatory review process.

99114E-mail DOE re: Hearing Logistics & no objection to late LOC 1 passage
Preamble p. p. 1
From: [Painting-MacLean, Kimberly](mailto:[email protected]) To: [Painting-MacLean, Kimberly](mailto:[email protected]) Subject: M12282 - EfficiencyOne - New Benefit Cost Analysis Test for Evalua...

AI summary The document outlines a regulatory proceeding (M12282) regarding EfficiencyOne's proposed new Benefit Cost Analysis Test for evaluating Demand Side Management (DSM) Plans. Daniel Boyle from the Department of Energy (DOE) confirms attendance on behalf of the DOE, states no witnesses will be presented, and does not object to late filings or virtual witness participation.

99119Letter SBA re: Hearing Logistics 1 passage
Section 1 p. p. 0
August 27, 2025 VIA EMAIL Ms. Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax NS B3J 3S3 Dear Ms. Henwood: Re: M12282 - EfficiencyOne - New Benefit Cost Analysis Test for Evaluating De...

AI summary A letter from Melissa P. MacAdam, Small Business Advocate, confirms attendance at the hearing for M12282 - EfficiencyOne's new benefit cost analysis test for DSM plans. The Small Business Advocate requests virtual testimony for Melissa Whitten of Daymark Energy Advisors Inc., with no objection to other virtual witnesses.

99131E-mail IG re: Hearing Logistics 3 passages
Nancy G. Rubin, K.C.\ p. p. 1
Nancy G. Rubin, K.C.\ Partner She/Her Stewart McKelvey D: 902.420.3337 \ Law Corporation From: Henwood, Crystal D Sent: August 27, 2025 11:12 AM To: Nancy G Rubin ; Alice Napoleon ; Allison Coffin ; Angela Costello ; Angela Zeng ; Bill Mah...

AI summary An email from Crystal Henwood regarding hearing logistics for a new Benefit-Cost Analysis (BCA) test for Demand Side Management (DSM) under matter M12282. Recipients include legal counsel, energy consultants, and Nova Scotia Power (NSP) representatives involved in the proceeding.

Statement of Confidentiality p. p. 1
m](mailto:[email protected])>; Theo Love <[[email protected]>](mailto:[email protected]); Twila Gaudet <[[email protected]](mailto:[email protected])> Subject: RE: M12282 - E1 - New BCA Tes...

AI summary Email correspondence related to regulatory proceeding M12282-E1 concerning a new Benefit-Cost Analysis (BCA) test for Demand Side Management (DSM) in Nova Scotia. Stakeholders include participants from Washington Mahody, Green Energy Economics, and Mikmaq Rights.

\ \ EXTERNAL EMAIL / COURRIEL EXTERNE \ \ p. p. 1
encyone.com)>; Taylor Montgomery [ ; Theo Love [ ; Twila Gaudet [ Subject: M12282 - EfficiencyOne - New Benefit Cost Analysis Test for Evaluating Demand Side Management (DSM) Plans

AI summary The document pertains to regulatory proceeding M12282, involving EfficiencyOne's proposal for a new Benefit-Cost Analysis (BCA) test to evaluate Demand Side Management (DSM) plans under Nova Scotia Power (NSP). The proceeding focuses on assessing DSM plan effectiveness through updated BCA methodologies.

99226Letter from E1 enclosing Rebuttal Evidence 1 passage
Section 1 p. p. 0
James R. Gogan Direct +1 (902) 563 5920 [email protected] 1969 Upper Water St., Suite 1300 McInnes Cooper Tower - Purdy's Wharf Halifax, NS B3J 3R7 TEL: 902.425.6500 FAX: 902.425.6350 Our File: 254441 September 4, 2025 Nova Sco...

AI summary EfficiencyOne submits rebuttal evidence, including Energy Futures Group's Appendix A, supporting their application (M12282) for approval of a new benefit-cost analysis test for evaluating demand side management plans before the Nova Scotia Energy Board.

99314Letter E1 re: Opening Statement 1 passage
Section 1 p. p. 0
James R. Gogan Direct +1 (902) 563 5920 [email protected] 1969 Upper Water St., Suite 1300 McInnes Cooper Tower - Purdy's Wharf Halifax, NS B3J 3R7 TEL: 902.425.6500 FAX: 902.425.6350 Our File: 254441 September 11, 2025 Nova Sc...

AI summary EfficiencyOne submits an Opening Statement to the Nova Scotia Energy Board (M12282) proposing a new Benefit-Cost Analysis Test for evaluating Demand Side Management Plans. Stephen MacDonald, EfficiencyOne's CEO, will present the statement at the hearing. The application seeks approval for the proposed test methodology.

99408Letter E1 re: Consensus Agreement 1 passage
Section 1 p. p. 0
James R. Gogan Direct +1 (902) 563 5920 [email protected] 1969 Upper Water St., Suite 1300 McInnes Cooper Tower - Purdy's Wharf Halifax, NS B3J 3R7 TEL: 902.425.6500 FAX: 902.425.6350 Our File: 254441 September 19, 2025 Nova Sc...

AI summary EfficiencyOne has reached consensus with the Consumer Advocate, Small Business Advocate, and East Coast Environmental Law on specific issues related to its application for a new benefit-cost analysis test for evaluating demand side management plans. A Consensus Agreement is submitted to the Nova Scotia Energy Board for consideration.

99409Email IG re: Change start time of Hearing to 12:30 3 passages
Preamble p. p. 2
From: [Nancy G Rubin](mailto:[email protected]) To: [Painting-MacLean, Kimberly](mailto:[email protected]); [MacNeil, Janet](mailto:[email protected]) Cc: [Alice Napoleon;](mailto:anapoleon@syna...

AI summary Email communication regarding the partial consensus agreement for EfficiencyOne's application for approval of a new Benefit Cost Analysis Test, with board acknowledgment. Part of regulatory proceeding M12282.

Nancy G. Rubin, K.C.\ p. p. 2
Nancy G. Rubin, K.C.\ Partner She/Her Stewart McKelvey D: 902.420.3337 \ Law Corporation From: Painting-MacLean, Kimberly Sent: September 19, 2025 3:21 PM To: MacNeil, Janet Cc: Alice Napoleon ; Allison Coffin ; Angela Costello ; Angela Ze...

AI summary Email communication regarding EfficiencyOne's application (M12282) for approval of a new Benefit Cost Analysis Test, with reference to a Partial Consensus Agreement and Board Acknowledgement. Nancy G. Rubin, K.C. is listed as a partner at Stewart McKelvey, and the email is sent by Kimberly Painting-MacLean of Nova Scotia's regulatory team.

Statement of Confidentiality p. p. 2
Statement of Confidentiality This message (including any attachments) may contain private or protected information meant for a specific person or organization. If you received this by mistake, please let the sender know, do not communicate...

AI summary A confidentiality notice regarding EfficiencyOne's M12282 application for a new Benefit Cost Analysis Test with a Partial Consensus Agreement. Sent by Janet MacNeil of McInnes Cooper to Crystal Henwood at the Nova Scotia government, with recipients from multiple organizations.

99410Email NSEB re: Hearing to start 12:30 pm On Monday September 22, 2025 4 passages
Preamble p. p. 0
From: [Painting-MacLean, Kimberly](mailto:[email protected]) To: ["Nancy G Rubin"](mailto:[email protected]) Cc: [Alice Napoleon;](mailto:[email protected]) [Allison Coffin](mailto:acoffin@eastward...

AI summary Email correspondence regarding Matter M12282, involving EfficiencyOne's application for approval of a new Benefit Cost Analysis Test, with partial consensus achieved. The email is sent by Kimberly Painting-MacLean of Nova Scotia to multiple stakeholders, including legal counsel, energy consultants, and industry representatives.

Statement of Confidentiality p. p. 0
Statement of Confidentiality This message (including any attachments) may contain private or protected information meant for a specific person or organization. If you received this by mistake, please let the sender know, do not communicate...

AI summary The email discusses M12282, EfficiencyOne's application for approval of a new Benefit Cost Analysis Test, involving a Partial Consensus Agreement and Board Acknowledgement. Recipients include Nova Scotia government officials, legal counsel, and energy consultants.

Nancy G. Rubin, K.C.\ p. p. 0
[email protected]](mailto:[email protected])>; Lucia Westin-Eastaugh [ ; McKayla Cameron [ ; Melissa Davies [ ; Melissa MacAdam [ ; Melissa Whitten <[[email protected]](mailto:[email protected])>; Mersey,...

AI summary The document pertains to a regulatory proceeding involving EfficiencyOne's application for approval of a new Benefit Cost Analysis Test, with a partial consensus agreement and Board acknowledgment. Key participants include EfficiencyOne and various legal and consulting professionals.

Statement of Confidentiality p. p. 3
Statement of Confidentiality This message (including any attachments) may contain private or protected information meant for a specific person or organization. If you received this by mistake, please let the sender know, do not communicate...

AI summary An email from Janet MacNeil to Crystal Henwood regarding EfficiencyOne's application for approval of a new Benefit Cost Analysis Test under matter M12282, with a partial consensus agreement. The message includes a confidentiality notice and lists multiple recipients from law firms and organizations involved in the regulatory proceeding.

99637Letter E1 re: Closing submissions 1 passage
Section 1 p. p. 0
James R. Gogan Direct +1 (902) 563 5920 [[email protected]](mailto:[email protected]) 1969 Upper Water St., Suite 1300 McInnes Cooper Tower - Purdy's Wharf Halifax, NS B3J 3R7 TEL: 902.425.6500 FAX: 902.425.6350 Our...

AI summary Closing submissions from EfficiencyOne regarding their application for approval of a new benefit-cost analysis test for evaluating demand side management plans in matter M12282 before the Nova Scotia Energy Board. Submitted by James R. Gogan of McInnes Cooper on behalf of EfficiencyOne.

99638Closing Submission - E1 18 passages
EfficiencyOne p. p. 0
EfficiencyOne IN THE MATTER OF The Public Utilities Act , RSNS 1989, c. 380, as amended -and- IN THE MATTER OF An Application for Approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans

AI summary The document pertains to an application under the Public Utilities Act for approval of a new benefit-cost analysis test to evaluate Demand Side Management Plans. The proceeding involves EfficiencyOne and focuses on regulatory approval for a methodological change in assessing demand-side management initiatives.

Preamble p. pp. 2-39
On May 16, 2025, EfficiencyOne ("E1") submitted its Application for Approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management ("DSM") Plans (the "Application") to the Nova Scotia Energy Board ("NSEB" or "the Board"...

AI summary EfficiencyOne submitted an application for approval of a new benefit-cost analysis test for evaluating demand-side management plans to the Nova Scotia Energy Board, in accordance with a 2022 directive. The application includes a partial Consensus Agreement supported by various stakeholders, including the Consumer Advocate and Efficiency Canada, and addresses methodological improvements for DSM cost-effectiveness testing.

2. CONTEXT AND USE OF THE COST EFFECTIVENESS TEST IN DSM PLAN REVIEW p. pp. 2-4
2. CONTEXT AND USE OF THE COST EFFECTIVENESS TEST IN DSM PLAN REVIEW Cost effectiveness testing has long been utilized in the evaluation of DSM plans in Nova Scotia, serving as a foundational element in the Board's assessment process to en...

AI summary Nova Scotia's Board uses the Total Resource Cost (TRC) test for DSM plan reviews, but proposes replacing it with a jurisdiction-specific Benefit-Cost Analysis (BCA) test to address TRC's deficiencies. The BCA test aligns with NSPM principles and Nova Scotia policy, following prior Board approvals to shift TRC analysis from measure to program level starting 2012.

3.2 ALIGNMENT OF PROPOSED BCA WITH STATUTORY PROVISIONS p. pp. 7-9
3.2 ALIGNMENT OF PROPOSED BCA WITH STATUTORY PROVISIONS As is discussed further below, E1 asserts that its Proposed BCA aligns with the above-noted policy and legislative objectives of the province, by incorporating utility system impacts,...

AI summary E1 argues its Proposed BCA aligns with provincial policy and legislative objectives by incorporating utility system, fuel, GHG, and health impacts into cost-effectiveness testing. EFG followed NSPM guidelines, while Ms. Lane testified that existing policies, not direct legislation, justify including societal factors like resilience and GHG reduction in the BCA framework.

4. OVERVIEW OF PROPOSED BCA FRAMEWORK & QUANTIFICATIONS, WITH PCA CONSIDERATIONS p. pp. 9-10
4. OVERVIEW OF PROPOSED BCA FRAMEWORK & QUANTIFICATIONS, WITH PCA CONSIDERATIONS

AI summary The section introduces the proposed BCA framework and quantifications for a regulatory proceeding, incorporating PCA considerations. Key entities and acronyms related to energy regulation and stakeholder groups are referenced.

4.1 CORE ELEMENTS p. pp. 10-11
4.1 CORE ELEMENTS E1 is requesting the Board approve the Proposed BCA as the new cost-effectiveness test for DSM, which is to be screened at the portfolio level. In designing the Proposed BCA, EFG followed the NSPM. None of the experts con...

AI summary E1 is requesting the Board to approve a new Benefit-Cost Analysis (BCA) as the cost-effectiveness test for Demand-Side Management (DSM), designed using the National Standard Practice Manual (NSPM) and aligned with Nova Scotia's policies. Experts like Ms. Lane and Mr. Bowman acknowledge the NSPM's value and policy neutrality. The Proposed BCA addresses utility system impacts, countering claims that it is disconnected from the utility and its customers.

- against the TRC test which is currently used by the Board for cost-effectiveness testing.[18](#page-12-0) p. p. 11
- against the TRC test which is currently used by the Board for cost-effectiveness testing.[18](#page-12-0) Impact Category Sub-Category BCA Test TRC Test Utility System Electric Generation Transmission Distribution General All All Gas Onl...

AI summary The text discusses the comparison between the BCA test and the TRC test for cost-effectiveness, highlighting differences in impact categories and sub-categories, such as the inclusion of gas commodity costs, societal resilience, and public health impacts. The Proposed BCA does not reduce the utility system impact categories compared to the TRC test.

4.3 APPLICABLE DISCOUNT RATE p. pp. 15-18
4.3 APPLICABLE DISCOUNT RATE E1, relying on expert analysis provided by EFG, submits that the adoption of a 2% real discount rate for evaluating impacts under the Proposed BCA test is both reasonable and legally sound. It reflects a societ...

AI summary E1, supported by EFG, argues that a 2% real discount rate is legally sound and aligns with NSPM and Nova Scotia legislation, including GHG mitigation and sustainable development. They oppose using WACC, claiming it misrepresents long-term benefits and legislative goals, with support from Efficiency Canada.

4.4 EVERGREEN PROCESS p. pp. 18-19
4.4 EVERGREEN PROCESS - E1's proposed evergreen process represents a foundational commitment to maintaining the integrity, - relevance, and adaptability of its Proposed BCA framework. This process ensures that the BCA test remains - aligne...

AI summary E1's evergreen process ensures the BCA framework remains aligned with evolving legislation, policy, and market conditions in Nova Scotia. It involves periodic reviews, stakeholder engagement, and collaboration with DSMAG to quantify non-energy impacts. E1 claims no opposition to the process.

5. SUMMARY OF EVIDENCE AND HEARING RECORD p. pp. 19-22
5. SUMMARY OF EVIDENCE AND HEARING RECORD Cost-effectiveness testing is not new in Nova Scotia. Section 79H(1) of the Public Utilities Act requires that the Board "determine the cost-effective demand-side management that must be undertaken...

AI summary The Nova Scotia Utility and Review Board is evaluating the replacement of the Total Resource Cost (TRC) test with a Benefit-Cost Analysis (BCA) for demand-side management (DSM) cost-effectiveness. Critics, including EfficiencyOne and the Consumer Advocate, argue the TRC test is asymmetrical and fails to incorporate new legislative priorities like sustainable development. E1 proposes the BCA test as a more comprehensive alternative.

6.1 INTRODUCTION p. pp. 23-25
6.1 INTRODUCTION - It is E1's position that the Proposed BCA satisfies the legislative requirements for cost-effectiveness testing, - including new or amended legislative requirements. More specifically, E1 submits that the Proposed BCA -...

AI summary E1 argues that their proposed BCA meets legislative requirements for cost-effectiveness testing, including portfolio-level DSM assessment and sustainable development considerations. They also claim Mr. Bowman's approach fails to satisfy statutory requirements.

6.3 THE PURPOSE OF COST-EFFECTIVENESS LEGISLATION p. pp. 25-26
6.3 THE PURPOSE OF COST-EFFECTIVENESS LEGISLATION

AI summary The section discusses the purpose of cost-effectiveness legislation, though no detailed content is provided in the given text. It likely addresses how such legislation aims to balance cost and benefit considerations in regulatory decisions.

6.3.1 E1'S PROPOSED BCA p. pp. 26-28
6.3.1 E1'S PROPOSED BCA In addressing this matter, it is appropriate to apply the rules of statutory interpretation and consider the relevant provisions "in their entire context and in their grammatical and ordinary sense harmoniously with...

AI summary E1's proposed BCA under the Public Utilities Act outlines statutory obligations for the NSUARB to evaluate DSM initiatives at the portfolio level. The Act requires NS Power to enter DSM purchase agreements with E1, which must be approved by the Board. The evaluation of cost-effectiveness is distinct from high-level portfolio assessments.

6.3.2 THE IG'S PROPOSED APPROACH p. pp. 28-35
6.3.2 THE IG'S PROPOSED APPROACH - The IG's proposed approach differs from the legislated direction and context. Mr. Bowman recommends - that "[t]he primary energy efficiency test should be the PAC test, applied at the measure and program...

AI summary The Industrial Group (IG) proposes using the Program Administrator Cost (PAC) test as the primary energy efficiency metric, alongside supplementary tests for electrification, societal impacts, and rate impacts. This approach contrasts with EfficiencyOne's (E1) broader 'societal test' framework. The IG emphasizes narrower criteria and specific cost-effectiveness metrics for DSM reviews.

6.4.2 IG'S PROPOSED APPROACH p. pp. 35-36
6.4.2 IG'S PROPOSED APPROACH E1 notes that Mr. Bowman's proposed cost-effectiveness test is insufficient to address E1's legislated DSM mandate, in particular its expanded strategic electrification mandate. Mr. Bowman's proposal is to use...

AI summary E1 argues that the PAC test is insufficient for evaluating strategic electrification under its DSM mandate, as it only considers costs. E1 proposes the BCA as a more effective primary test, citing flaws in the PAC approach and complexity from using multiple tests. Experts like Dr. Hill (EFG) and Mr. Neme support this, emphasizing legislative requirements for electrification.

6.5.1 E1'S PROPOSED BCA p. p. 37
6.5.1 E1'S PROPOSED BCA Fourth, E1 submits that its Proposed BCA allows the Board to give appropriate consideration to the extent to which a cost-effectiveness test can support the goals (including sustainability goals) set out by the Legi...

AI summary E1 argues its proposed BCA aligns with legislative goals, unlike the IG's tests. The Energy Reform Act (2024) mandates cost-effectiveness considerations in Board decisions. Section 6(2) of the Energy and Regulatory Boards Act requires the Board to evaluate cost-effectiveness when approving rates or other matters.

6.5.2 IG'S PROPOSED APPROACH p. pp. 39-41
6.5.2 IG'S PROPOSED APPROACH The evidence presented to the Board supports the finding that the Proposed BCA is the test which best addresses these policy concerns. In fact, the IG's expert, Mr. Bowman, indicates that in order to address br...

AI summary The IG's expert, Mr. Bowman, advocates for the Proposed BCA as a societal test to address sustainable development and GHG reductions. However, his primary PAC test fails to incorporate legislative policy goals outlined in the NSPM, which mandates integrating DER-related policy considerations into cost-effectiveness analyses. The Proposed BCA allows the Board to consider societal factors within a cost-effective framework.

9 7. REQUESTED BOARD ORDER p. pp. 41-42
9 7. REQUESTED BOARD ORDER - Based the evidence and analysis before the Board in this matter, including as set out in this Closing - Submission, E1 respectfully requests the Board approve the Proposed BCA as supplemented by the PCA, - spec...

AI summary E1 requests the NSUARB to approve the Proposed BCA with PCA modifications, including a 2% discount rate and evergreen process. It aligns with PUA, supports decarbonization goals, and reflects stakeholder input via DSMAG. The BCA is deemed evidence-based, consistent with legislation, and in the public interest.

99640Closing Submission - IG 15 passages
Delivered by E-mail p. p. 0
Delivered by E-mail Crystal Henwood Regulatory Affairs Officer/Clerk Nova Scotia Energy Board 3rd Floor, 1601 Lower Water Street PO Box 1692, Unit "M" Halifax NS B3J 3S3 Dear Ms. Henwood: Re: M12282 - E1- New Benefit Cost Analysis Test for...

AI summary Efficiency One (E1) proposes a new benefit-cost analysis (BCA) test for demand-side management (DSM) plans, incorporating non-energy impacts like social cost of carbon. The Industrial Group opposes this, arguing the Board should not consider non-energy benefits and instead adopt a Program Administrator Cost (PAC) test. The proceeding addresses whether the Board can/should use the Proposed BCA under the Public Utilities Act.

Background and Principles of Statutory Interpretation p. pp. 0-2
Background and Principles of Statutory Interpretation This application arose out of the Board's direction to undertake a "thorough assessment of the relative merits of both the PAC test and a jurisdiction-specific test,["](#page-1-0) 2 as...

AI summary The Board directed an assessment of PAC test vs. jurisdiction-specific test for DSM. E1 engaged EFG and DSMAG, but omitted comparative analysis with PAC. Province amended PUA, and E1 argues these changes expanded the Board's jurisdiction over DSM, contrary to prior rulings limiting non-energy impact considerations.

Applicable Legislative Provisions for Cost Effectiveness Testing p. pp. 2-6
Applicable Legislative Provisions for Cost Effectiveness Testing The issue before the Board now, is what costs and what benefits should be weighed when evaluating DSM. Energy efficiency and conservation activities are contained within thei...

AI summary The Board considers legislative provisions under the PUA governing DSM cost-effectiveness testing. NSPI and E1 have statutory obligations under ss 79A-79W of the PUA , with E1 serving as NSPI's franchisee for energy efficiency. The PUA mandates NSPI to contract with E1 for DSM activities, emphasizing alignment with regulatory objectives.

Prior Interpretation of the Board's Jurisdiction p. pp. 6-7
Prior Interpretation of the Board's Jurisdiction Up until this application, the predecessor Board made clear that it did "not have the jurisdiction to take into account non-energy impacts in cost-effectiveness testing" in relation to DSM.[...

AI summary The Board clarified its jurisdiction excludes non-energy impacts in DSM cost-effectiveness testing, focusing solely on energy-based costs and benefits. EfficiencyOne argued for broader environmental considerations under the PUA, but the Board rejected this, citing statutory definitions. The Board emphasized 'cost-effective' means evaluating electricity efficiency activities for affordability and long-term cost reduction, acknowledging limited environmental benefits.

The Board Still Cannot Account for Non-energy Benefits p. pp. 8-9
The Board Still Cannot Account for Non-energy Benefits The Industrial Group recognizes that certain recent legislative amendments may impact the ongoing interpretation of the PUA provisions. However, the additional factors provide guidance...

AI summary The Industrial Group acknowledges recent legislative changes but argues they don't alter the PUA's focus on reducing electricity costs. E1's environmental goals must align with PUA provisions, not override them. The Board must adhere to statutory mandates, and non-energy benefits aren't within the legislative framework for cost-effectiveness evaluation.

Negative implications of Broad interpretation p. pp. 9-10
Negative implications of Broad interpretation When interpreting the PUA, this Board should recall Sullivan's third question: what are the consequences of adopting a proposed interpretation? Approving a broad ranging costeffectiveness test...

AI summary The document warns that a broad interpretation of the PUA's cost-effectiveness testing could undermine existing practices, expand E1's mandate beyond legislative intent, and misapply the social cost of carbon (SC-GHG) as a ratepayer tool. It emphasizes that SC-GHG, derived from federal guidelines, is intended for legislative cost-benefit analyses, not utility rate-making.

2. THE BOARD SHOULD NOT TAKE INTO CONSIDERATION NON-ENERGY AND BROAD SOCIETAL IMPACTS p. pp. 10-12
2. THE BOARD SHOULD NOT TAKE INTO CONSIDERATION NON-ENERGY AND BROAD SOCIETAL IMPACTS In the alternative, if the Board determines it has the jurisdiction to incorporate non-energy and broad societal impacts into the cost-effectiveness test...

AI summary The Industrial Group argues that the Board should not consider non-energy and broad societal impacts in evaluating Demand-Side Management (DSM). They claim this would expand Benefit-Cost Analysis (BCA) beyond ratepayer-focused tests, introducing unquantifiable factors. E1's proposed BCA includes non-energy benefits and carbon costs, which the Small Business Advocate's consultant opposes, aligning with the Program Administrator Cost (PAC) test instead.

Host Customer Non-Energy Benefits p. pp. 12-14
Host Customer Non-Energy Benefits The proposed BCA test suggests that the Board should weigh a number of unquantifiable proposed benefits, including customer pride, empowerment, economic well-being, comfort, amenity, and health and safety....

AI summary The proposed BCA test includes subjective non-energy benefits like customer pride and health, valued via proxy percentages of energy benefits. Critics argue these are vague and unsupported, conflicting with PUA's DSM definition. E1 clarified non-energy impacts, but the Industrial Group opposes proxy adders for intangible benefits. Synapse's consultant Courtney Lane raised concerns about proxy value arbitrariness.

Broad Societal Impacts p. pp. 14-15
Broad Societal Impacts E1 also proposes to include broad societal impacts within its cost-effectiveness testing. This goes well beyond the approach taken by any other Canadian jurisdiction. The global cost of carbon as a percentage of the...

AI summary E1 proposes including global carbon costs in its BCA for energy efficiency programs, a unique approach in Canada. Critics argue this is inappropriate as Nova Scotia does not tax carbon, and the PUA mandates cost reduction, not broad societal impacts. The Industrial Group opposes integrating societal impacts into DSM cost-effectiveness tests.

Inconsistency across DERs p. pp. 15-16
Inconsistency across DERs The Industrial Group takes no issue with the use of the National Standard Practice Manual (" NSPM ") for Distributed Energy Resources (" DERs" ) as a guiding framework in formulating an appropriate cost-effectiven...

AI summary The Industrial Group supports using the NSPM for DERs but highlights inconsistent application of its principles. Concerns include E1's proposed 2% discount rate, which is deemed too low and not aligned with standard practices. The need for non-green energy investments to meet net-zero goals is acknowledged, but the BCA's consistency across NSPI and IESO remains unexplored. The Industrial Group disputes the discount rate's justification and cites legislative gaps.

ALTERNATIVE COST-EFFECTIVENESS TEST p. p. 16
ALTERNATIVE COST-EFFECTIVENESS TEST If DERs are to be treated consistently, the proposed societal test should not be approved. The Proposed BCA is inconsistent with the current IRP, and NSPI capital asset treatment. The cost effectiveness...

AI summary The text argues against approving a proposed societal test for DERs, citing inconsistencies with the current IRP and NSPI's capital asset treatment. It advocates for aligning E1's cost-effectiveness testing with NSPI's methods and recommends using the utility cost test (PAC) instead.

Evidence of Patrick Bowman p. pp. 16-18
Evidence of Patrick Bowman The Industrial Group relies on the evidence filed by Mr. Bowman, and his oral evidence at the hearing, and specifically supports his recommendation to use the PAC as the primary costeffectiveness test. This appro...

AI summary The Industrial Group supports Patrick Bowman's recommendation to use PAC as the primary cost-effectiveness test for DSM programs, aligning E1 with Canadian utilities and PUA goals of reducing electricity costs. Bowman notes PAC's widespread use across Canada and its alignment with customer interests.

Modified PAC test for Electrification p. pp. 18-19
Modified PAC test for Electrification The PAC need not be rigid or "ruthlessly applied".[73](#page-19-0) It can be applied or modified as needed, like a jurisdictional test. As suggested by Mr. Bowman, this can be done with respect to stra...

AI summary The document discusses modifying the PAC test for electrification, proposing inclusion of increased revenues from electrification to better assess system costs. Mr. Bowman's approach aligns with Posterity Group's hybrid heating recommendations, reducing utility costs and passing PAC tests. This aligns with the PUA and E1's mandate to lower electricity costs for NSPI customers.

DSMAG CONSULTATION p. p. 19
DSMAG CONSULTATION While the purpose and role for the DSMAG is not currently an issue before the Board, the Industrial Group wishes to reiterate its concerns with respect to E1's overreliance on the DSMAG consultations within E1's and EFG'...

AI summary The Industrial Group criticizes E1's reliance on DSMAG consultations as implicit support for the Proposed BCA, emphasizing that DSMAG discussions do not endorse the BCA or its non-energy benefits. They note DSMAG's confidentiality and lack of consensus on the BCA, while welcoming Eastward Energy's potential DSMAG membership.

CONCLUSION p. p. 19
CONCLUSION The Industrial Group respectfully requests that the Board: - 1. Direct E1 to use the PAC as its primary test for further DSM Plan applications, and a modified version of the PAC in relation to the strategic electrification progr...

AI summary The Industrial Group requests the Board to direct E1 to use the Program Administrator Cost (PAC) as the primary test for DSM Plan applications, apply primary testing at multiple levels, confirm secondary testing, modify the BCA test if accepted, and reject a 2% social discount rate for cost-effectiveness evaluations.

99641Closing Submission - EE 7 passages
NOVA SCOTIA ENERGY BOARD p. p. 2
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act, RSNS 1989, c. 380 as amended IN THE MATTER OF: An Application by EfficiencyOne for Approval of a New Benefit Cost Analysis Test for Evaluating Demand Side Management (DSM...

AI summary The Nova Scotia Energy Board is considering an application by EfficiencyOne for approval of a new Benefit Cost Analysis Test to evaluate Demand Side Management (DSM) Plans under the Public Utilities Act. The proceeding is designated as Matter M12282.

MEMBERSHIP IN THE DSMAG p. pp. 2-3
advocate and advance a differing position. There is simply no legitimate reason to keep Eastward out of the DSMAG and there is significant value having it as a fully participating member of the DSMAG. From the pre-filed evidence and oral t...

AI summary Eastward Energy argues for full DSMAG membership, asserting its exclusion caused oversights in E1's evidence and policy reviews. It highlights E1's reliance on DSMAG for input and the omission of the Gas Distribution Act and hybrid heating savings in E1's application. The request cites section 79(G)(1) of the Public Utilities Act.

STRATEGIC ELECTRIFICATION p. pp. 3-4
STRATEGIC ELECTRIFICATION With respect to the recently added definition of strategic electrification in section 79A(b)(iv) of the Public Utilities Act , Ms. Thompson confirmed that strategic electrification requires both a reduction in ove...

AI summary The definition of strategic electrification under the Public Utilities Act requires reducing both greenhouse gas emissions and electricity costs. Ms. Thompson notes E1 has not advanced work on demonstrating cost reductions. Mr. Bowman argues the PAC test must include revenue benefits for electrification to pass, emphasizing that avoiding peak demand increases makes the test mathematically feasible.

And similarly. Bowman stated: p. p. 5
n. And if you consider the revenue they're going to get from selling that power, it's more than 13 million. So that would pass a PAC test and lower net cost to customers. It would pass 79I of the Act. We've run an electrification program,...

AI summary The text discusses revenue from power sales passing a PAC test and lowering customer costs, aligning with 79I of the Act. Electrification programs, while incurring costs, generate more revenue. Bowman argues E1 (EfficiencyOne) must consider broader cost savings beyond BCA metrics. Eastward highlights the value of Eastward's potential DSMAG involvement in advising E1's 2027-2031 plan.

RELIABILITY IMPACTS p. p. 10
RELIABILITY IMPACTS In its Rebuttal Evidence E1 stated that "NS Power's avoided cost of capacity implicitly includes reliability impacts through a planning reserve margin adjustment" 44 , and "If reliability differs between modelled scenar...

AI summary The document discusses reliability impacts in energy planning, noting that E1 claims avoided costs include reliability adjustments. Experts confirm adding capacity increases reserve margins and system impacts should be considered. EFG assumes ancillary service costs are embedded in avoided costs. Eastward argues reliability differences must be assessed explicitly, opposing deferral to future reviews and requesting NS Power to clarify ancillary service inclusion.

SUSTAINABLE DEVELOPMENT AND SUSTAINABLE PROSPERITY CONSIDERATIONS p. p. 12
ic growth, environmental stewardship and social responsibility are integrated and recognized as being interconnected.[59](#page-13-1) In this regard there is a balancing act required. [60](#page-13-2) E1 and EFG have taken these provisions...

AI summary The document discusses balancing economic growth with environmental and social responsibilities. E1 and EFG argue for incorporating the social cost of carbon into benefit-cost analyses, while Mr. Bowman contends that existing regulations like PAC already address environmental factors, risking double-counting if social cost of carbon is added.

CONCLUSION p. pp. 13-14
CONCLUSION In conclusion Eastward respectfully requests that the Board: - 1. make a preliminary and final order that Eastward be added as a full member of the DSMAG in accordance with the Board's general supervision of E1 pursuant to secti...

AI summary Eastward requests the Board to add it as a DSMAG member, prioritize hybrid heating in E1's DSM plan, use marginal emissions in modelling, guide benefit-cost thresholds, assess natural gas reliability impacts, confirm ancillary costs from Nova Scotia Power, adjust electrification values, balance legislative requirements in BCA tests, and consider EFG's sustainable development emphasis.

99642Closing Submission - ECEL 2 passages
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act, RSNS 1989, c 380, as amended – and – IN THE MATTER OF: An Application by EfficiencyOne for Approval of a New Benefit Cost Analysis Test for Evaluating Demand-side Managem...

AI summary East Coast Environmental Law submits a closing statement supporting EfficiencyOne's proposed new Benefit-Cost Analysis test for evaluating DSM plans, emphasizing the inclusion of avoided social costs of carbon and the Board's responsibility under the Energy and Regulatory Boards Act to consider non-energy impacts in cost-effectiveness testing.

The Board's Jurisdiction to Take Non-energy Impacts into Account in Cost-effectiveness Testing for Demand-side Management Plans
The Board's Jurisdiction to Take Non-energy Impacts into Account in Cost-effectiveness Testing for Demand-side Management Plans The second issue concerns the Board's jurisdiction to take non-energy impacts into account in cost-effectivenes...

AI summary The document addresses whether the Nova Scotia Utility and Review Board (UARB) can consider non-energy impacts in cost-effectiveness testing for Demand-side Management (DSM) plans. It references the Energy Reform (2024) Act and the EfficiencyOne (Re) case, where the UARB previously ruled against considering non-energy impacts. ECEL supports EfficiencyOne's argument that the new Act expanded the Board's jurisdiction to include non-energy benefits in DSM cost-effectiveness analyses.

99643Closing Submission - NSPI 9 passages
Preamble p. p. 0
October 14, 2025 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: 2025 M12282 Demand Side Management (DSM) Benefit Cost Analysis Test (BCAT) Closing Submission Dear Ms....

AI summary Nova Scotia Power Incorporated (NS Power) submits closing arguments in the 2025 M12282 Demand Side Management (DSM) Benefit Cost Analysis Test (BCAT) proceeding before the Nova Scotia Energy Board. The submission addresses DSM program evaluations and cost-benefit analyses.

INTRODUCTION p. p. 0
INTRODUCTION NS Power acknowledges the significant effort and collaboration that took place through the Demand Side Management Advisory Group (DSMAG) process to arrive at the proposal now before the Nova Scotia Energy Board (NSEB, Board) f...

AI summary NS Power submits a proposal for a new Benefit Cost Analysis (BCA) Test, emphasizing cost-effective demand-side management (DSM) under section 79I of the Public Utilities Act. The submission outlines NS Power's and EfficiencyOne's (E1) positions, legal review, and recommendations to the Nova Scotia Energy Board (NSEB). The focus is on affordability and cost reduction obligations.

EFFICIENCYONE'S PROPOSAL p. pp. 0-1
EFFICIENCYONE'S PROPOSAL E1's DSM Plan is currently subject to the application of the Total Resource Cost ("TRC") Test, as the M03669 Board approved cost effectiveness test applied at the program level. The TRC Test compares benefits and c...

AI summary EfficiencyOne's DSM Plan uses the modified TRC Test post-M10473, which considers host costs but not benefits, creating imbalance. E1 proposes a jurisdiction-specific BCA including non-energy benefits, aligning with societal impact perspectives. Legislative changes reflecting Nova Scotia's policy goals are highlighted as critical for the new BCA framework.

LEGISLATIVE AND REGULATORY FRAMEWORK AND ANALYSIS p. pp. 2-4
LEGISLATIVE AND REGULATORY FRAMEWORK AND ANALYSIS Though there have been legislative changes in Nova Scotia, the Board's decision in M08888 issued April 15, 2020 holds. There, the Board found that it did not have the jurisdiction to consid...

AI summary The Nova Scotia Energy Board's 2020 decision (M08888) reaffirms its jurisdictional limits, emphasizing cost-effectiveness, safe service, and reasonable rates over non-energy benefits. Sections 79H and 79I of the PUA mandate NSP to implement cost-effective DSM programs, with cost-effectiveness defined to include E1's efficiency activities. Current legislation does not empower the Board to consider non-energy impacts except for greenhouse gas reduction through electrification.

The More Access to Energy Act p. pp. 6-7
The More Access to Energy Act Bill 404 created the More Access to Energy Act (MAEA) which carriesthe following purpose: The purpose of this Act is to - (a) increase competition and innovation in the Province's energy sector; - (b) ensure t...

AI summary The MAEA aims to boost energy sector competition, ensure reliable energy supply, and integrate sustainability goals from the EGCCRA and EA. E1 emphasizes these goals, but the text notes ambiguity in applying sustainable development principles to the JST and distinguishes policy language from prescriptive BCA requirements.

NS POWER'S POSITION p. p. 7
NS POWER'S POSITION This initiative overall has made great progress throughout the DSMAG; however, more work is required to eliminate the potential for unintended consequences and to ensure alignment with the current and existing legislati...

AI summary NS Power emphasizes the need for careful evaluation of DSM programs to avoid increasing customer costs and align with legislative frameworks. It recommends modifying the TRC test to include greenhouse gas emissions reductions, electricity cost savings, and displaced fuel impacts. The NSEB's regulatory regime and strategic electrification under the PUA are highlighted as key considerations.

Mechanics of the BCA p. p. 7
Mechanics of the BCA

AI summary The section outlines the mechanics of the Benefit Cost Analysis (BCA) process, likely detailing its application in regulatory proceedings. Key entities involved include Nova Scotia Power, the Nova Scotia Energy Board, and related legislation such as the Public Utilities Act and Energy Reform (2024) Act.

Avoided Cost Series p. p. 7
Avoided Cost Series NS Power submits that the current avoided cost series is primarily intended to inform analysis of traditional energy efficiency measures that reduce both energy and peak demand, or contribute to demand response. In the...

AI summary NS Power proposes updating the avoided cost series for DSM and Demand Response to reflect new programming, including strategic electrification. They emphasize the need for tailored cost curves and collaboration with E1 and DSMAG. The BCA test focuses on demand-side resources, not supply-side.

CONCLUSION p. p. 7
CONCLUSION DSM remains a vital tool for managing system costs, advancing electrification, and supporting the energy transition. However, its primary purpose must remain clear: to deliver measurable, economically sound benefits to customers...

AI summary DSM is essential for managing costs and energy transition but must prioritize customer benefits without unnecessary burdens. NS Power's recommendations are seen as balanced and transparent, allowing the Board to incorporate evolving policy considerations while maintaining cost-effectiveness and affordability.

99644Closing Submission - CA 5 passages
13 i. EfficiencyOne p. pp. 2-5
13 i. EfficiencyOne 14 15 E1 filed evidence in support of its application from Dr. David Hill, a Consultant with Energy 16 Futures Group ("EFG"). Dr. Hill's evidence was that in 2024 EFG worked with the DSMAG "to review and develop a new j...

AI summary EfficiencyOne (E1) submitted evidence from Dr. David Hill of Energy Futures Group (EFG), detailing work with the DSM Advisory Group (DSMAG) to develop a jurisdiction-specific benefit-cost analysis (BCA) test for Nova Scotia. EFG's 2025 report outlines a framework requiring consideration of both utility and non-utility system impacts. The methodology references the National Energy Screening Project's National Standards Practice Manual Reports.

20 iii. Board Counsel p. pp. 5-6
20 iii. Board Counsel 22 Counsel to the Nova Scotia Energy Board filed evidence from Courtney Lane of Synapse Energy 23 Economics. 25 Ms. Lane's conclusions in her evidence were as follows: - 27 E1's approach to developing the Nova Scotia...

AI summary Board Counsel submitted evidence from Courtney Lane of Synapse Energy Economics, supporting E1's Nova Scotia Test as an improvement over the TRC test by incorporating energy policy goals and non-energy impacts. Lane recommended approving the BCA test with modifications but noted E1's insufficient justification for NEB proxy values. The Partial Consensus Agreement's zero quantification of certain impacts was also mentioned.

15 iv. Small Business Advocate p. p. 6
15 iv. Small Business Advocate 16 17 The Small Business Advocate filed evidence in this matter from Consultant Melissa Whitten of 18 Daymark Energy Advisors, Inc. In her evidence, Ms. Whitten presented concerns regarding E1's 19 proposed B...

AI summary The Small Business Advocate raised concerns about E1's proposed BCA test, citing difficulties in quantifying non-energy benefits like amenity, empowerment, and pride. Melissa Whitten of Daymark Energy Advisors supported the Partial Consensus Agreement's zero quantification for these benefits but expressed ongoing concerns about their inclusion in future proceedings.

23 C. Submissions p. p. 7
23 C. Submissions 24 25 As noted above, the Consumer Advocate has executed a Partial Consensus Agreement with E1 26 and other Parties regarding the new proposed BCA Test. The Consumer Advocate supports the 27 adoption of the terms of the A...

AI summary The Consumer Advocate supports the adoption of a new BCA Test as outlined in a Partial Consensus Agreement with E1 and other parties. The discussion highlights the need to assess whether recent legislative amendments in 2024 allow for the inclusion of non-energy impacts in cost-effectiveness testing, following a previous decision in EfficiencyOne (Re) , 2020 NSUARB 56.

Preamble p. pp. 11-14
onsidered the public 23 interest in rendering past awards, and had interpreted the public interest to mean more than a pure cost-benefit analysis. 40 24 The Board's comments are noted below:

AI summary The Board emphasized that public interest considerations in past awards extend beyond pure cost-benefit analysis, highlighting a broader interpretation of public interest in regulatory decisions.

99645Closing Submission - SBA 5 passages
Section 1
1 2 3 BEFORE THE NOVA SCOTIA ENERGY BOARD 4 IN THE MATTER OF AN APPLICATION BY EFFICIENCYONE for approval of a New 5 Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans - Ml2282 6 CLOSING ARGUMENT OF THE SMALL BUSINESS A...

AI summary EfficiencyOne seeks approval for a new Benefit-Cost Analysis (BCA) Test to evaluate Demand Side Management (DSM) plans, following stakeholder consultations. The Small Business Advocate (SBA) emphasizes cost-effectiveness and inclusion of low-income programs despite potential cost inefficiencies. The SBA supports proposed Utility System impacts but highlights ongoing discussions about Non-Utility System impacts.

Section 2
mpacts, 24 which are grouped together as Non-Utility System impacts3. These impacts generated a lot of 25 discussion, as they are, in many cases, new additions from the previous tests used by EfficiencyOne 26 and are not consistently used...

AI summary The document discusses Non-Utility System impacts from EfficiencyOne's new Benefit-Cost Analysis (BCA) test for Demand Side Management (DSM) plans, which have sparked debate due to their novelty compared to previous tests. Melissa Whitten of Daymark Energy Advisors raised concerns about proxy values for non-energy benefits and challenges in measuring/verifying them.

Section 4
- 1 energy benefits. She identified the non-energy benefits of amenity, empowerment and pride as - 2 being of the most concern and recommended more work be done to quantify them, with the results - 3 of that work being presented to the mem...

AI summary Ms. Whitten recommends quantifying non-energy benefits (amenity, empowerment, pride) or setting their value to Nil until approved by the Board. She prefers the PAC test over quantifying these benefits. The SBA expresses concerns about unquantified non-energy benefits impacting ratepayers. The discussion involves Benefit-Cost Analysis (BCA) and Demand Side Management (DSM).

Section 5
nquantified and difficult to quantify - 21 non-energy benefits with EfficiencyOne on several occasions. The SBA's concern stems from the - 22 fact that ratepayers are required to pay for a DSM plan on the basis that there will be benefits...

AI summary The Service Board of Appeals (SBA) raises concerns about quantifying non-energy benefits in Demand Side Management (DSM) plans, emphasizing the need for benefits to be broadly beneficial to ratepayers, not just participants. Melissa Whitten's evidence and exhibits highlight challenges in ensuring fair cost allocation and proper Benefit-Cost Analysis (BCA) framework application.

Section 6
RIR 1 (a) and 1(a)(i}, page 2 of 2, at lines 4-9. 11 M12282, Exhibit E-16, SBA (IG) RIR 2(a}, page 1 of 2. 12 M12282, Exhibit E-17, SBA {IG) RIR 2(b), page 2 of 2, at lines 4-9. - 1 In the interest of obtaining access to the measures and b...

AI summary The Small Business Advocate (SBA) agrees to the Consensus Agreement, which reduces proxy values for certain measures and commits EfficiencyOne to an Evergreen process for reviewing the BCA framework. The SBA recommends adopting the amended BCA Test for 2027-2031, emphasizing progress on DSM while addressing concerns about quantifying non-monetary benefits like empowerment.

99729Reply Submission - CA 1 passage
3 NOVA SCOTIA ENERGY BOARD p. p. 0
3 NOVA SCOTIA ENERGY BOARD 4 5 IN THE MATTER OF: The Public Utilities Act 6 7 and 8 9 IN THE MATTER OF: An Application by EfficiencyOne for approval of a new 10 Benefit-Cost Analysis Test for Evaluating Demand-Side 11 Management Plans 12

AI summary The Nova Scotia Energy Board is considering an application by EfficiencyOne under the Public Utilities Act to approve a new Benefit-Cost Analysis Test for evaluating Demand-Side Management Plans. The proceeding involves assessing the methodology for evaluating energy efficiency initiatives.

99730Reply Submission - IG 7 passages
Delivered by E-mail p. p. 0
Delivered by E-mail Crystal Henwood Regulatory Affairs Officer/Clerk Nova Scotia Energy Board 3rd Floor, 1601 Lower Water Street PO Box 1692, Unit "M" Halifax NS B3J 3S3 Dear Ms. Henwood: Re: M12282 - E1- New Benefit Cost Analysis Test for...

AI summary The Industrial Group submits reply comments opposing Nova Scotia Power (NSPI) and EfficiencyOne (E1)'s closing brief in M12282, maintaining its statutory interpretation position regarding a new benefit-cost analysis test for evaluating demand-side management (DSM) plans.

i. PAC vs TRC p. pp. 0-1
i. PAC vs TRC Where the Industrial Group diverges from NSPI is with respect to the proposed primary test to be adopted for DSM going forward. In contrast to NSPI, the Industrial Group does not view the Total Resource Cost (" TRC ") test as...

AI summary The Industrial Group opposes NSPI's proposed use of the Total Resource Cost (TRC) test for demand-side management (DSM), arguing it inaccurately measures costs and benefits for utilities and customers. They advocate for the PAC test, which accounts for customer incentives and aligns with Nova Scotia's high electricity prices, aiming to lower ratepayer costs. The Public Utilities Act (section 79L(4)) mandates consideration of customer interests.

ii. PAC Does Reflect GHG Impacts p. p. 1
ii. PAC Does Reflect GHG Impacts The Industrial Group also refers to Appendix A to NSPI's submissions, where it sets out what NSPI states is a side-by-side comparison of the Program Administrator Cost (" PAC ") test, the TRC test, and E1's...

AI summary The Industrial Group argues that the Program Administrator Cost (PAC) test accurately reflects GHG impacts, countering claims in Appendix A of NSPI's submissions. They reference Exhibit E-33's Venn Diagram, which shows 'Generation Energy' and 'Society Factors' include GHG charges and social costs, respectively, confirming GHG impacts are accounted for in PAC.

i. PAC is Not "Too Narrow" and Suite of Tests is not "Cumbersome" and "Complex" p. pp. 1-2
i. PAC is Not "Too Narrow" and Suite of Tests is not "Cumbersome" and "Complex" E1 claims the PAC test "is too narrow to serve as the main assessment for portfolio-level decisionmaking["](#page-2-0) 5 . The Industrial Group emphasizes that...

AI summary E1 argues the PAC test is too narrow and the proposed tests are complex, while the Industrial Group counters that PAC is foundational and targeted. E1 focuses on environmental goals, whereas PUA mandates cost reduction for NSPI customers. The combination of tests proposed by Mr. Bowman is deemed balanced and not overly burdensome.

ii. Misstatement of Approach to Evaluation of Strategic Electrification p. pp. 2-3
ii. Misstatement of Approach to Evaluation of Strategic Electrification While misstating the evidence of Mr. Bowman, E1 again pleads "complexity" to argue against the use of different tests to be applied to different resources. Its submiss...

AI summary E1 argues against using different cost-effectiveness tests for DSM resources, claiming complexity and misrepresenting Mr. Bowman's evidence. The Industrial Group supports Mr. Bowman's proposal to use the PAC test for all DSM, with adjustments for strategic electrification. Critics argue E1's uniform test fails to address electrification's unique benefits and costs, while the Proposed BCA overlooks utility revenue impacts and inadequate evaluation criteria.

iii. The Proposed BCA Could Be Used as a Supplementary Test but is Not Supported in its Current Form and is Not Required p. p. 3
iii. The Proposed BCA Could Be Used as a Supplementary Test but is Not Supported in its Current Form and is Not Required E1's submissions imply endorsement of the Proposed BCA by Mr. Bowman: In fact, the IG's expert, Mr. Bowman, indicates...

AI summary E1 argues the Proposed BCA is necessary for addressing societal concerns, but Mr. Bowman clarifies it is not required and should only be a supplementary tool. The Industrial Group supports using the PAC as the primary cost-effectiveness test, with BCA serving as a secondary, non-essential complement. Broader societal costs are deemed unnecessary for lowering electricity costs.

Conclusion p. p. 3
Conclusion The Industrial Group maintains its position that the legislation, as currently drafted, does not allow for a broad societal test to be used for primary cost-effectiveness testing of DSM, and that the PAC should be used as the pr...

AI summary The Industrial Group argues that current legislation does not permit a broad societal test for DSM cost-effectiveness, advocating for PAC as the primary test. Mr. Bowman's proposed tests are deemed manageable for E1 and should guide the DSM Plan application. The submission is signed by Nancy G. Rubin and Brianne Rudderham, with a carbon copy to participants.

99731Reply Submission - EE 5 passages
NOVA SCOTIA ENERGY BOARD p. p. 2
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act, RSNS 1989, c. 380 as amended IN THE MATTER OF: An Application by EfficiencyOne for Approval of a New Benefit Cost Analysis Test for Evaluating Demand Side Management (DSM...

AI summary The Nova Scotia Energy Board is considering EfficiencyOne's application for a new Benefit Cost Analysis Test for Demand Side Management (DSM) plans under the Public Utilities Act. Eastward Energy Inc. submitted a rebuttal argument opposing the approval of this test as part of Matter M12282.

DEMAND SIDE MANAGENMENT ADVISORY GROUP ("DSMAG") p. p. 2
DEMAND SIDE MANAGENMENT ADVISORY GROUP ("DSMAG") It remains clear from the Closing Submissions of E1 that the DSMAG is intended to continue as the principle vehicle by which E1 will gain input on its DSM plans and programs, and that E1's p...

AI summary Eastward seeks DSMAG membership to contribute to E1's 2027-2031 DSM plan. E1 opposes this without providing reasons, while NSPI rejects E1's BCA test, proposing an alternative. Other DSMAG members, including the IG, support Eastward's inclusion. Eastward argues there is no valid reason to exclude it from DSMAG.

HYBRID HEATING p. pp. 2-3
HYBRID HEATING With respect to the significant issue of hybrid heating, E1 simply states that, "At the hearing, Ms. Thompson confirmed hybrid heating measures are currently being considered by E1 for the 2027- 2031 DSM Plan".[6](#page-3-2)...

AI summary The document discusses E1's consideration of hybrid heating in its 2027-2031 DSM Plan, with Eastward and the Industrial Group advocating for stronger focus on hybrid heating due to cost-effectiveness and policy alignment. E1's approach is criticized for prioritizing greenhouse gas reductions over electricity cost reductions and omitting key policy guidance from the Gas Distribution Act.

SUSTAINABLE DEVELOPMENT AND SUSTAINABLE PROSPERITY p. pp. 3-5
SUSTAINABLE DEVELOPMENT AND SUSTAINABLE PROSPERITY E1 has continued in its Closing Submissions to put considerable emphasis on the Board's requirement at section 6(2)(d) of the Energy and Regulatory Boards Act to give "appropriate consider...

AI summary E1 emphasizes the Board's duty under the Energy and Regulatory Boards Act to consider sustainable development and prosperity in DSM plans. E1's BCA proposal is framed as aligning with these goals, though NSPI and East Coast Environmental Law caution against overriding other legislative priorities like affordable energy rates. The Board's decision may set a precedent for future cases, with Mr. Bowman's approach avoiding global carbon cost methodologies.

AVOIDED COSTS p. p. 5
AVOIDED COSTS NSPI states that it intends to "update the avoided cost series of DSM and Demand Response ("DR") to reflect an updated planning scenario"[21](#page-6-0) , and that in its view "some types of DSM programming may require altern...

AI summary NSPI plans to update avoided cost data for DSM and DR programs, collaborating with E1 and DSMAG. Eastward offers expertise on hybrid heating technologies and emphasizes the need for DSMAG participation to ensure accurate avoided cost valuations.

99732Reply Submission - E1 14 passages
EfficiencyOne p. p. 0
EfficiencyOne IN THE MATTER OF The Public Utilities Act , RSNS 1989, c. 380, as amended -and- IN THE MATTER OF An Application for Approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans

AI summary The document outlines a regulatory proceeding under the Public Utilities Act, involving an application for approval of a new benefit-cost analysis test to evaluate demand side management plans.

2.1 LEGISLATIVE INTERPRETATION & JURISDICTIONAL LIMITS p. pp. 2-5
2.1 LEGISLATIVE INTERPRETATION & JURISDICTIONAL LIMITS The IG contends that the Board, under the Public Utilities Act (" PUA "), is not empowered to consider broad societal impacts or non-energy benefits when evaluating the cost-effectiven...

AI summary The Industrial Group (IG) argues that the Board under the Public Utilities Act (PUA) cannot consider societal impacts or non-energy benefits when evaluating demand-side management (DSM) cost-effectiveness, emphasizing ratepayer cost reduction. They claim the new strategic electrification provision in the Energy Efficiency and Renewable Energy Act (ERBA) allows EfficiencyOne (E1) to expand programs but still requires adherence to cost-effectiveness, with sustainability limited to specific proposals.

2.3 RECOMMENDATION FOR THE PROGRAM ADMINISTRATOR COST (PAC) TEST p. pp. 6-7
2.3 RECOMMENDATION FOR THE PROGRAM ADMINISTRATOR COST (PAC) TEST The IG recommends the Program Administrator Cost (PAC) test as the primary cost-effectiveness test, citing its alignment with other Canadian jurisdictions and its focus on ut...

AI summary The IG recommends the Program Administrator Cost (PAC) test for its alignment with other Canadian jurisdictions and utility cost focus. E1 counters that the test must align with Nova Scotia's legislation, not other provinces, and notes that key stakeholders like NS Power, CA, and SBA do not support PAC. E1 emphasizes NSPM guidance and jurisdiction-specific approaches.

2.5 CONSISTENCY p. p. 8
2.5 CONSISTENCY - The submission also highlights concerns about inconsistency across distributed energy resources (DERs), - suggesting that the BCA test would require expansion to other areas and create regulatory challenges. The - IG stat...

AI summary The Industrial Group (IG) argues that the Proposed BCA test is inconsistent with Nova Scotia Power's Integrated Resource Plan (IRP) and capital asset treatment, advocating for the utility cost test (PAC). EfficiencyOne (E1) counters that the NSPM is tailored for DERs, the TRC test isn't linked to IRP, and NS Power opposes the PAC test. The debate centers on cost-effectiveness testing for DSM and DERs.

2.6 ALTERNATIVE APPROACH FOR ELECTRIFICATION PROGRAMS p. pp. 8-9
2.6 ALTERNATIVE APPROACH FOR ELECTRIFICATION PROGRAMS - Regarding electrification programs, the IG proposes a modified PAC test that includes increased revenues - from electrification as a benefit, aiming to better assess true system costs...

AI summary The IG proposes a modified PAC test for electrification programs, incorporating revenue benefits. E1 argues the PAC test has a 'fundamental flaw' as noted by Dr. Hill. The IG's approach is criticized as a rate-impact test, not cost-effectiveness, conflicting with NSPM and PUA definitions. References to M12282 and evidence from Bowman and E1 are cited.

2.7 SUPPORT FOR PRIMARY AND SECONDARY TESTING p. pp. 9-10
2.7 SUPPORT FOR PRIMARY AND SECONDARY TESTING - 2 The IG supports both primary (PAC) and secondary tests for DSM cost-effectiveness specifically the - 3 Proposed BCA and relevant information on the host customer or Participant Cost test ("...

AI summary The Industrial Group (IG) supports both primary and secondary tests for demand-side management (DSM) cost-effectiveness, including the Proposed BCA and Participant Cost Test (PCT). EfficiencyOne (E1) maintains that cost-effectiveness screening must occur at the portfolio level under the Public Utilities Act (PUA), as outlined in section 79H(2), and clarifies it has not retreated from its original position.

3.2 HYBRID PEAKING RESOURCES p. pp. 10-11
3.2 HYBRID PEAKING RESOURCES Eastward Energy expresses the following concern[:26](#page-11-4) There simply does not appear to be the level of acknowledgement of the significant value hybrid heating can bring to the integrated electricity s...

AI summary Eastward Energy argues that E1 (EfficiencyOne) has not adequately acknowledged the value of hybrid heating in the electricity system. However, E1's representative, Ms. Thompson, confirmed during the hearing that E1 recognizes hybrid heating's potential value. The text clarifies hybrid heating is not central to the current application's focus on DSM cost-effectiveness methodology.

3.4 NATURAL GAS TO ELECTRIC CONVERSIONS p. pp. 11-12
3.4 NATURAL GAS TO ELECTRIC CONVERSIONS With respect to natural gas to electric conversions, Eastward Energy raises concerns with regard to an illustrative example regarding conversion of gas heating systems to electric heat pumps, noting...

AI summary Eastward Energy expresses concern over E1's illustrative example of natural gas-to-electric conversions, citing a negative benefit and benefit-cost ratio below 1.0. E1 clarifies the example is hypothetical and reaffirms that justification would be required under existing Board directives if the example were accurate. The Board has already provided guidance on this issue.

3.5 RELIABILITY IMPACTS p. p. 12
3.5 RELIABILITY IMPACTS - Eastward insists that benefit-cost analyses must fully account for the reliability advantages of natural gas - systems, and that any loss of reliability from electrification should be explicitly considered. - The...

AI summary Eastward Energy argues that reliability impacts of electrification must be explicitly considered in benefit-cost analyses, while E1 agrees in principle under specific conditions, such as full electrification without backup gas. E1 proposes addressing these issues via the proposed BCA test and the evergreen process. Eastward seeks immediate action, but lacks evidence of imminent impacts. E1 trusts NS Power's avoided costs include ancillary service costs, pending further confirmation.

6 3.7 SUSTAINABLE DEVELOPMENT AND PROSPERITY CONSIDERATIONS p. pp. 13-14
6 3.7 SUSTAINABLE DEVELOPMENT AND PROSPERITY CONSIDERATIONS - Eastward cautions against overemphasizing sustainable development and prosperity in benefit-cost tests, - advocating for a balanced approach that considers all legislative requi...

AI summary Eastward cautions against overemphasizing sustainable development in benefit-cost tests, advocating for balance. E1 argues its Proposed BCA test appropriately considers societal impacts as one factor. Eastward Energy warns against applying social cost of carbon to other matters. E1 emphasizes the Board's specific focus on approving the BCA test as a replacement for the TRC test in DSM Plan evaluations.

4. RESPONSE TO NS POWER p. p. 14
4. RESPONSE TO NS POWER - NS Power's position regarding the Proposed BCA was first communicated to E1 and the DSMAG in its - Closing Submission. - The Closing Submission invites the Board to narrow Nova Scotia's DSM cost-effectiveness fram...

AI summary NS Power proposes revising the BCA framework to use its WACC and exclude certain benefits, conflicting with post-2022 legislation, the proceeding's record, and NSPM methodology. E1 argues for maintaining the current cost-effectiveness framework, including a 2% discount rate and portfolio-level screening under PUA.

4.1.2 WHY M08888 IS NO LONGER DETERMINATIVE p. pp. 17-18
greenhouse gas emissions has been added, as well as the introduction of the required "appropriate consideration" requirements of Energy And Regulatory Boards Act and the More Access To Energy Act . The Board's consideration of the Proposed...

AI summary The Board must apply legislative amendments, including 'appropriate consideration' requirements from the Energy And Regulatory Boards Act and More Access To Energy Act , when evaluating the Proposed BCA. These amendments reflect clear legislative intent, not mere policy objectives, and any methodology failing to comply, such as NS Power's TRC test, must be rejected.

4.2 CONFLATING DSM PLAN CONSIDERATIONS WITH COST-EFFECTIVENESS SCREENING p. pp. 18-19
4.2 CONFLATING DSM PLAN CONSIDERATIONS WITH COST-EFFECTIVENESS SCREENING E1 takes no issue with the "operational requirements" interpretation of NS Power with respect to the approval of DSM programs. However, this Application is not a broa...

AI summary E1 supports aligning DSM cost-effectiveness screening with PUA statutory requirements, opposing NS Power's integration of affordability into the screening test. Affordability should be addressed separately through mechanisms like the Balanced Plan Approach, not via cost-effectiveness criteria. The application focuses on statutory compliance under s. 79H(2) PUA, distinguishing screening from broader DSM plan approval processes.

4.3 APPROPRIATE DISCOUNT RATE p. pp. 19-20
4.3 APPROPRIATE DISCOUNT RATE NS Power asserts that the WACC should be the discount rate for DSM cost-effectiveness screening. NS Power's reliance on WACC as the appropriate discount rate is both legally and conceptually flawed for several...

AI summary NS Power argues for using WACC as the discount rate for DSM cost-effectiveness screening, but opponents claim it is legally and conceptually flawed. They argue WACC misapplies NSPM principles, ignores sustainability and long-term GHG benefits, and undervalues DSM programs. A 2% social discount rate is recommended, aligning with federal guidance and legislative mandates.

99733Letter E1 re: Reply submission 1 passage
Section 1 p. p. 0
James R. Gogan Direct +1 (902) 563 5920 [[email protected]](mailto:[email protected]) 1969 Upper Water St., Suite 1300 McInnes Cooper Tower - Purdy's Wharf Halifax, NS B3J 3R7 TEL: 902.425.6500 FAX: 902.425.6350 Our...

AI summary EfficiencyOne submits reply submissions to the Nova Scotia Energy Board regarding a new Benefit-Cost Analysis Test for evaluating Demand Side Management Plans in regulatory proceeding M12282.

99735Reply submission - NSPI 6 passages
Preamble p. p. 0
October 21, 2025 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: M12282 Demand Side Management (DSM) Benefit Cost Analysis Test (BCAT) Rebuttal Submission Dear Ms. Henw...

AI summary Nova Scotia Power Incorporated (NS Power) submits a rebuttal to EfficiencyOne's (E1) proposed Benefit Cost Analysis Test (BCAT) for Demand Side Management (DSM) Plans, emphasizing the need for consensus aligned with legislative intent and cost-effectiveness frameworks. NS Power argues the Nova Scotia Energy Board (NSEB) cannot consider host customer non-energy impacts or societal impacts post- Energy Reform Act (ERA) enactment, citing the Public Utilities Act (PUA) as the governing legislation.

Response to the Closing Arguments of E1, the Consumer Advocate (CA), the Small Business Advocate (SBA), and East Coast Environmental Law (ECEL) p. pp. 0-1
oes not dictate the proper interpretation of legislation and there remains fundamental disagreement on the impact of the relevant legislative changes since the Board's decision in M08888 on E1's BCAT. First, the PUA remains the governing s...

AI summary The document argues that the PUA governs DSM in Nova Scotia, prioritizing cost-effectiveness over sustainability. It disputes E1's claim that the ERA requires balancing factors, emphasizing the ERBA's directive to 'give consideration' to sustainability without overriding cost-effectiveness. References to Board decision M08888 and ERBA section 6(2) are cited.

Discount Rate p. pp. 3-4
Discount Rate 11 ECEL Closing Submission, page 1. 12 CA Closing Submission, pdf page 12/14. 13 CA Closing Submission, pdf page 9/14. E1 submits that the 2 percent discount rate is not only appropriate and prudent, but also in the best inte...

AI summary E1 argues a 2% discount rate is appropriate and in ratepayers' best interest, while NS Power contends that using their cost of capital provides a more accurate reflection of current affordability challenges and aligns with immediate financial benefits. Both parties emphasize the importance of comparing demand and supply resource options.

Response to the Industrial Group's (IG) Closing Submissions p. pp. 4-5
Response to the Industrial Group's (IG) Closing Submissions Similarly to the above, NS Power does not intend to summarize the entirety of the IG's closing submissions but will address differences in the IG's proposed PAC and Modified PAC t...

AI summary NS Power agrees with the Industrial Group (IG) on the need for alternative cost-effectiveness tests for demand-side management (DSM) and strategic electrification under the PUA. Both parties emphasize evaluating greenhouse gas reductions and electricity cost savings, though NS Power insists on measure-level proof for strategic electrification. NS Power also supports IG's stance on primary and secondary testing for DSM analyses.

The Modified PAC test for Electrification p. p. 5
The Modified PAC test for Electrification The IG presents a secondary test called the "Modified PAC test for Electrification" for consideration to address this requirement which accounts for increased utility revenues as a benefit with res...

AI summary The IG proposes a 'Modified PAC test for Electrification' that includes increased utility revenues as a benefit of electrification. NS Power supports this but argues for incorporating 'other fuel impacts' to align with a Total Resource Cost (TRC) test. Both agree that a 2% discount rate is inappropriate, advocating for NS Power's cost of capital instead.

CONCLUSION p. p. 6
CONCLUSION E1's proposed test leaves the Board with no transparent evidentiary pathway to assess whether the proposed non-energy benefits or their associated values are reasonable, reproducible, or consistent with statutory intentions. As...

AI summary E1's proposed test lacks transparency in assessing non-energy benefits, per NS Power's submission. NS Power emphasizes the need for revisions to align with legislative frameworks like the PUA and advocates for collaborative efforts to refine cost-effectiveness testing. The conclusion underscores the necessity of further alignment between statutory intentions and practical implementation.

100256Board Decision 32 passages
IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 3
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF AN APPLICATION by EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans BEFORE: Stephen T. McGrath, K.C., Chair Steven...

AI summary EfficiencyOne applied for approval of a new benefit-cost analysis test for demand-side management plans. The Board denied the application, directing instead a focus on reducing electricity costs for customers. Multiple intervenors, including consumer advocates, industry groups, and environmental organizations, participated in the proceeding.

Preamble p. p. 3
- [1] In the course of addressing EfficiencyOne's (E1) application to the Nova Scotia Utility and Review Board (NSUARB) for approval of its supply agreement with Nova Scotia Power Incorporated (NS Power) and demand-side management (DSM) re...

AI summary The NSUARB's cost-effectiveness test for DSM plans was questioned for excluding non-energy benefits, leading to potential skewed results. Synapse recommended using the PAC test instead, which focuses on utility costs but ignores participant costs and benefits. This issue arose during the review of EfficiencyOne's application.

2.0 PROPOSED BENEFIT-COST ANALYSIS TEST p. pp. 3-5
2.0 PROPOSED BENEFIT-COST ANALYSIS TEST - [8] E1 is the holder of a franchise issued by the Minister of Energy to provide demand-side management activities to NS Power. Under the Public Utilities Act , E1 must develop a demand-side managem...

AI summary E1, a franchise holder under the Public Utilities Act, must develop demand-side management (DSM) plans for NS Power, structured in tiers (measure, program, portfolio). The NSUARB evaluates these plans using cost-effectiveness testing, ensuring measurable benefits for ratepayers and aligning with Nova Scotia's regulatory practices.

3.1 Consumer Advocate p. p. 14
3.1 Consumer Advocate [28] The Consumer Advocate is a signatory to the Consensus Agreement. The Consumer Advocate argues that recent amendments to the Public Utilities Act altered the criteria the Board is to apply in evaluating E1's propo...

AI summary The Consumer Advocate argues that recent amendments to the Public Utilities Act require evaluating demand-side management programs at the portfolio level, including strategic electrification. They emphasize incorporating sustainability factors in the BCA test, preferring E1's approach over the PAC test, and support a 2% social discount rate for long-term impacts. They also maintain the 10% proxy value for electrification and acknowledge the PAC test as a potential secondary measure.

3.2 Industrial Group p. pp. 14-16
3.2 Industrial Group [34] The Industrial Group is not a party to the Consensus Agreement. It objects to the use of the proposed BCA test as the new primary cost-effectiveness test. It recommends the Board approve the PAC test as the primar...

AI summary The Industrial Group opposes using the BCA test as the primary cost-effectiveness standard, advocating instead for the PAC test for DSM Plan applications and a modified PAC test for strategic electrification. It argues that programs failing the PAC test require justification and that non-energy impacts, like carbon social effects, should not be considered. The group emphasizes complementary use of the PAC test with secondary evaluations and notes the Public Utilities Act amendment adding strategic electrification to DSM's definition.

3.3 Small Business Advocate p. pp. 16-20
3.3 Small Business Advocate [45] The Small Business Advocate agreed to the Consensus Agreement and recommends the Board adopt the proposed BCA test as amended by the Consensus Agreement. In closing submissions, the Small Business Advocate...

AI summary The Small Business Advocate agreed to the Consensus Agreement, recommending the Board adopt the amended BCA test. Concerns were raised about quantifying non-energy benefits like amenity and empowerment, with suggestions to set unquantified benefits to zero or adopt the PAC test instead. The Advocate emphasized the need for further analysis on non-energy benefits.

3.4 Nova Scotia Power p. p. 21
tes" and that the "listed factors in section 6(2)(a-e) [of the Energy and Regulatory Boards Act ] supplement, but do not replace, the Board's primary mandate." In its closing submissions, it states: The operative phrase of section 6(2) is...

AI summary NS Power argues that section 6(2) of the Energy and Regulatory Boards Act requires 'appropriate consideration' of factors without prescribing their weight, and that 'sustainable development' in the BCA test lacks clear linkage to non-utility impacts. It contends E1's approach misinterprets legislative intent by transforming policy language into prescriptive requirements.

3.5 East Coast Environmental Law p. pp. 21-23
3.5 East Coast Environmental Law [56] East Coast Environmental Law (ECEL) is a party to the Consensus Agreement and supports E1's proposed new BCA test as amended by the contents of the agreement. It states in its closing submissions: … We...

AI summary East Coast Environmental Law (ECEL) supports E1's revised BCA test, emphasizing inclusion of carbon social costs in DSM evaluations. It argues that the Energy Reform (2024) Act expands the Board's environmental mandate, requiring alignment with sustainability goals under multiple acts. ECEL stresses that sustainable development and prosperity must be considered alongside affordability and reliability in energy regulation.

3.6 Eastward Energy p. pp. 23-24
3.6 Eastward Energy [61] In its submissions, Eastward Energy asked the Board to make a preliminary and final order that Eastward be added as a full member of DSMAG. On November 4, 2025, the Board noted that Eastward has a valuable perspect...

AI summary Eastward Energy requested DSMAG membership, which the Board approved. They supported strategic electrification testing via PAC with NS Power revenue inclusion, aligned with Posterity Group's advice. Eastward emphasized hybrid heating's economic benefits and urged E1 to prioritize it in the 2027-2031 DSM Plan, citing the Public Utilities Act's cost-reduction mandate.

4.1.1 Introduction p. p. 27
4.1.1 Introduction [69] The Public Utilities Act requires NS Power to engage E1 to undertake "costeffective demand-side management". The Board must approve these agreements and "determine the cost-effective demand-side management that must...

AI summary The NSUARB must determine the cost-effectiveness test for demand-side management under the Public Utilities Act, with parties disagreeing on whether non-energy impacts should be considered. Post-2020 jurisdictional changes and the 2024 Energy Reform Act split NSUARB into two boards, expanding the Energy Board's consideration scope. E1 argues the Board now has jurisdiction to include non-energy impacts, while some intervenors oppose this. The Board will assess statutory interpretation and decide on BCA approval if jurisdiction is confirmed.

4.1.3 Board Approval of Demand-side Management p. p. 30
Incorporated, and Nova Scotia Power Incorporated may rely upon the expertise of the franchise holder in respect of the delivery of demand-side management. - (4) The Energy Board shall approve an application pursuant to this Section if, in...

AI summary The Energy Board (NSUARB) must approve demand-side management (DSM) applications if they serve customers' interests and meet PUA requirements. Evaluations occur at the portfolio level, emphasizing cost-effectiveness. Nova Scotia Power may leverage franchise holders' expertise for DSM delivery.

4.1.4 The 2020 Non-energy Benefits Decision p. pp. 30-33
4.1.4 The 2020 Non-energy Benefits Decision - [83] The NSUARB determined it did not have the jurisdiction to consider nonenergy benefits in the cost-effectiveness testing for demand-side management in Re EfficiencyOne , 2020 NSUARB 56. In...

AI summary The NSUARB ruled in Re EfficiencyOne (2020 NSUARB 56) that it lacked jurisdiction to consider non-energy benefits in cost-effectiveness testing for demand-side management. E1 argued that the NSUARB's duty to act in customers' best interests, under the Public Utilities Act , allowed consideration of factors like thermal comfort and property value impacts beyond electricity savings.

4.1.6 The Meaning of "Cost-effective" under the Public Utilities Act p. pp. 36-40
4.1.6 The Meaning of "Cost-effective" under the Public Utilities Act [96] From the text used by the Legislature in s. 79I(1) of the Public Utilities Act , it follows that NS Power's statutory duty relates to demand-side management (as defi...

AI summary The Public Utilities Act (PUA) mandates NS Power to implement cost-effective demand-side management, with the NSUARB ensuring compliance. The Act does not explicitly define 'cost-effective,' leaving interpretation to the Board. The Board must evaluate proposals at the portfolio level and ensure they align with s. 79I's requirements.

(2) A franchise p. p. 40
(2) A franchise (a) gives the franchise holder the exclusive right to supply Nova Scotia Power Incorporated with reasonably available, cost-effective demand-side management for the purpose of this Act; … - 79K (1) Nova Scotia Power Incorpo...

AI summary The franchise grants exclusive rights to Nova Scotia Power Incorporated (NSPI) for cost-effective demand-side management. NSPI must share customer data with franchise holders and cooperate with the IESO on integrated resource planning. Provisions emphasize cost-effectiveness and 'reasonably available' demand-side management, with E1 arguing for a broader benefits-costs test beyond utility impacts.

The current version is: p. p. 40
The current version is: (iv) strategic electrification of energy end uses currently powered by fossil fuels in a manner that reduces overall greenhouse gas emissions and electricity costs [108] E1 submits that strategic electrification can...

AI summary E1 argues that strategic electrification cannot be evaluated using traditional PAC or TRC tests, as utility impacts are primary costs and non-utility impacts (e.g., fuel savings, GHG reductions) are primary benefits. The 2022 PUA amendment defines strategic electrification as reducing GHG emissions and electricity costs, requiring expanded cost-effectiveness analysis to include non-utility benefits.

[124] Eastward expressed similar comments in its reply submissions: p. p. 40
[124] Eastward expressed similar comments in its reply submissions: E1 has continued in its Closing Submissions to put considerable emphasis on the Board's requirement at section 6(2)(d) of the Energy and Regulatory Boards Act to give "app...

AI summary Eastward's reply submissions emphasize E1's focus on the Board's duty under the Energy and Regulatory Boards Act to prioritize sustainable development in DSM plans. E1 argues that the Board must explicitly address sustainable development, while East Coast Environmental Law notes this responsibility does not override other statutory considerations like affordable energy rates. NSPI aligns with E1's BCA approach, and E1 disputes the Industrial Group's interpretation of legislative changes.

4.1.6.1 Findings p. p. 52
osts. As noted already, strategic electrification may only be undertaken if, in addition to reducing greenhouse gas emissions, it reduces electricity costs. This is explicitly stated in s. 79A(b)(iv). [130] While the NSUARB's 2020 decision...

AI summary The NSUARB examines legislative requirements for demand-side management, emphasizing cost reduction and alignment with sections 79A(b)(iv), 79I(1), and 79H(2) of the PUA. The Board agrees with the Industrial Group and NS Power that cost reduction remains central, rejecting broader interpretations of sustainable development overriding specific cost mandates. References to Matter M12171 highlight tensions between general and specific legislative provisions.

4.2 Benefit-Cost Test Alternatives p. pp. 52-57
4.2 Benefit-Cost Test Alternatives [143] No party in this proceeding argued that the existing TRC test should be maintained in its present form. [144] As discussed in more detail previously, E1's proposed BCA test includes utility system a...

AI summary No party supports maintaining the current TRC test. E1's proposed BCA test includes utility and non-utility system impacts, informed by Nova Scotia's legislative changes, with objectives of sustainability, GHG reduction, and equitable access. Table 5 compares the existing TRC test and the proposed BCA test.

[146] In its closing submissions, the Industrial Group said: p. p. 57
[146] In its closing submissions, the Industrial Group said: Where the PUA has clearly mandated the focus of DSM to be on the reduction of costs, the PAC is able to demonstrate that as a primary test; the Proposed BCA cannot. As confirmed...

AI summary The Industrial Group advocates for the PAC test over the Proposed BCA, emphasizing cost reduction alignment with the PUA. NS Power proposes a modified TRC test incorporating fuel impacts and GHG reductions. E1 criticizes both approaches, arguing they conflict with post-2022 statutory mandates and fail to balance utility and customer costs.

4.2.1 Findings p. pp. 57-60
4.2.1 Findings [151] E1 and its consultants purported to follow guidance in the NSPM in determining the proposed BCA test. However, a process that simply takes account of an inventory of energy and climate change policy goals and objective...

AI summary The Board rejects the proposed BCA test for DSM cost-effectiveness due to misalignment with the PUA's focus on reducing customer electricity costs. The TRC test is criticized for asymmetrical application. The Industrial Group supports the PAC test, which aligns with PUA's statutory requirements. The Board directs E1 to use PAC for future DSM plans.

4.3 Strategic Electrification p. pp. 60-62
4.3 Strategic Electrification [158] Strategic electrification that reduces overall GHG emissions and electricity costs is included in the definition of "demand-side management" in s. 79A(b)(iv) of the Public Utilities Act . The PAC test, a...

AI summary The text discusses the challenges of applying the traditional PAC test to strategic electrification programs under the Public Utilities Act. It highlights Mr. Bowman's proposal to modify the PAC test by including increased revenues from electrification as a benefit, ensuring cost-effective programs. The Industrial Group supports this approach, emphasizing alignment with the PUA's mandate to reduce electricity costs for NSPI customers through hybrid heating and other measures.

[160] Eastward made similar comments in its submissions: p. p. 62
[160] Eastward made similar comments in its submissions: In this regard the IG has noted that the approach proposed by Mr. Bowman to costeffectiveness testing for E1 for strategic electrification – running the PAC test with the additional...

AI summary Eastward argues that modifying the PAC test to include NSPI's revenue aligns with Posterity Group's recommendations, emphasizing cost-effective hybrid heating programs. E1 counters that this approach assesses rate impacts, not cost-effectiveness, and criticizes E1's BCA focus on GHG reductions over electricity cost savings.

4.3.1 Findings p. pp. 62-63
4.3.1 Findings [162] The Board accepts the Industrial Group's suggestion that traditional cost effectiveness tests may be modified to suit specific jurisdictional requirements. The means of assessing strategic electrification in Nova Scoti...

AI summary The Board accepts modifying traditional cost-effectiveness tests for strategic electrification in Nova Scotia. It endorses Mr. Bowman's PAC test approach for E1 but notes E1's incomplete work on demonstrating cost reductions. The Board requires E1 to meet both GHG reduction and cost-effectiveness criteria, allowing future alternative proposals in its 2027-2031 DSM Plan.

4.4 Portfolio Level Assessment p. pp. 63-64
4.4 Portfolio Level Assessment [164] Section 79H(2) requires the Board to evaluate the proposed cost-effective demand-side management at the portfolio level. In its submissions, the Industrial Group urged that it was particularly important...

AI summary Section 79H(2) mandates portfolio-level evaluation of demand-side management cost-effectiveness. The Industrial Group and NS Power argue tests must apply at portfolio, program, and measure levels with E1 justifying failures. E1 insists screening should occur only at the portfolio level.

4.4.1 Findings p. p. 64
4.4.1 Findings [166] There is no ambiguity in s. 79H(2): the Board must evaluate the proposed cost-effective demand-side management at the portfolio level. As noted previously in this decision, the Board agrees with E1 that there is a diff...

AI summary The NSUARB mandates evaluating cost-effective demand-side management (DSM) at the portfolio level, not individual measures. The Board allows alternative cost-effectiveness tests, including BCA, and requires E1 to justify measures failing primary tests. NS Power's WACC must be compared if a social discount rate is used in BCA. The Energy and Regulatory Boards Act (ERBA) permits justification based on factors under s. 6(2).

4.5 Discount Rate p. pp. 64-65
4.5 Discount Rate [169] Benefit-cost analysis involves comparing all the costs and benefits of a program over a period of time. There will be a stream of costs and benefits that are usually spread over several years, and in some cases, dec...

AI summary The section explains the role of discount rates in Benefit-Cost Analysis (BCA), emphasizing their importance in reflecting time preference and opportunity costs. It outlines three categories of discount rates from the National Standard Practice Manual (NSPM): WACC, customer-focused rates, and societal discount rates, each serving different purposes in evaluating distributed energy resources.

4.5.1 Findings p. pp. 65-71
4.5.1 Findings [192] Discounting is a fundamental component of BCA. Applying a social discount rate places greater emphasis on future benefits than a standard discount rate typically would. Environment and Climate Change Canada's SC – GHGs...

AI summary The text discusses the use of social discount rates in Benefit-Cost Analysis (BCA), noting that Environment and Climate Change Canada's SC-GHG guidance employs a lower discount rate to prioritize future benefits. It criticizes E1 for not following the Treasury Board's policy on when to apply a social discount rate, as outlined in the Policy on Cost-Benefit Analysis .

s. 7.1 about the discount rate to be used: p. p. 71
s. 7.1 about the discount rate to be used: The discount rate is the rate at which future costs and benefits are converted to their present equivalents. Discounting accounts for the fact that: - there is a time preference for current consum...

AI summary The document establishes that the discount rate for regulatory analyses should be based on the opportunity cost of capital (WACC), as per Treasury Board guidelines. It emphasizes alignment with NS Power's IRP and the Public Utilities Act, rejecting social discount rates except for specific long-term cases. The NSUARB mandates WACC for cost-effectiveness testing of DSM programs, citing NS Power's funding source and the need for comparable evaluations.

[201] In its response, E1 stated: p. p. 73
[201] In its response, E1 stated: The approach E1 is proposing in the 'evergreen' process for calculating the emissions intensity of DSM savings for the purposes of benefit cost analyses is the Difference in Carbon Emissions (DICE) method....

AI summary E1 proposes using the Difference in Carbon Emissions (DICE) method for calculating emissions intensity in benefit-cost analyses, aligning with NSPM guidance and IRP modeling. This method considers long-term generation resource mix impacts, contrasting with short-term marginal emissions approaches. E1 also notes average emissions rates are used for illustrative BCA examples.

4.8 Avoided Costs p. pp. 77-78
4.8 Avoided Costs [212] Eastward raised concern about NS Power's avoided cost values and requested confirmation that ancillary service costs, peak costs and system reliability are embedded in the avoided cost values. Eastward also requeste...

AI summary Eastward questioned NS Power's avoided cost values, specifically regarding ancillary services, peak costs, and reliability. NS Power responded that these factors are included in their avoided cost modeling, particularly with DSM programs like electrification of transportation, and referenced the IRP model and DSMAG. The Board accepted NS Power's response.

4.9 Natural Gas System Reliability p. p. 78
4.9 Natural Gas System Reliability [215] In its evidence [Exhibit E-11], Eastward raised concerns about the potential for E1 to propose natural gas to electricity conversion as a strategic electrification project in its upcoming DSM portfo...

AI summary Eastward raised concerns about E1's proposed natural gas-to-electricity conversion project, citing a negative net benefit and low benefit-cost ratio. E1 clarified its example was illustrative and agreed to consider reliability impacts in future proposals. The Board accepted E1's response to address reliability concerns in such projects.

5.0 SUMMARY OF BOARD FINDINGS p. pp. 78-79
5.0 SUMMARY OF BOARD FINDINGS [217] The Board finds it does not have the authority to approve E1's proposed BCA because the Public Utilities Act restricts the Board's ability to consider non-energy and societal benefits in assessing the co...

AI summary The Board rejects E1's proposed BCA due to the Public Utilities Act's restrictions on non-energy benefits. E1 must use PAC test and NS Power's WACC for DSM plan assessments. Strategic electrification requires GHG reduction and cost savings. Eastward is added to DSMAG. Portfolio-level cost-effectiveness evaluations are mandated.

100257Board Order 2 passages
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF AN APPLICATION by EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans BEFORE : Stephen T. McGrath, K.C., Chair Steven...

AI summary EfficiencyOne seeks approval for a new benefit-cost analysis test to evaluate demand side management plans under the Public Utilities Act. The proceeding is before a panel including Stephen T. McGrath, Steven M. Murphy, and Darlene Willcott.

ORDER
ORDER EfficiencyOne (E1) applied to the Nova Scotia Energy Board on May 16, 2025, for approval of a New Benefit-Cost Analysis (BCA) Test for Evaluating Demand Side Management (DSM) Plans. The Board issued its Decision on December 10, 2025....

AI summary EfficiencyOne (E1) sought approval for a new BCA test for DSM plans, but the Nova Scotia Energy Board rejected it, directing E1 to use the PAC test instead. The Board mandated NS Power's WACC as the discount rate, required strategic electrification to reduce emissions and costs, and included Eastward in the DSM advisory group. E1 must comply with the Public Utilities Act and provide specific data for DSM plan assessments.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →