Preamble
p. p. 0
June 3. 2010 Ms. Nancy McNeil Clerk of the Board Nova Scotia Utility and Review Board 1601 Lower Water Street. 3 rd Floor P.O. Box 1692, Unit "M" Halifax, NS B3J-3S3 Re: NSPI's Relay Testing Report 2009 Dear Ms McNeil: In the Board's lette...
AI summary NSPI submitted its 2009 Annual Report on the Electromechanical Relay Test Program, fulfilling the Board's 2006 directive to test relays on 69kV and 138kV systems and report results, costs, and actions required. The report covers 2007-2009 data and compliance with a three-year testing cycle.