By E-mail and Courier Ms. Lee Thomson-Lutz Capital Manager Nova Scotia Power Inc. 14 th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI – Request for final cost approval for Work Order CI# 28866 - TRE Unit #6 Low NO...
AI summary The Board approves Nova Scotia Power Inc.'s request to reduce the final cost of Work Order CI#28866 for the TRE Unit #6 Low NOx Combustion Firing System from $5,607,640 to $4,106,621, citing lower-than-estimated material, contract, labour, and overhead costs.