It is of concern to the Board that the under-scoping of this project was because the nondestructive testing (NOT) did not detect the full extent of the required work. NSPI may want to consider reviewing its NOT protocols to see if the accu...
AI summary The Board is concerned about the under-scoping of a project due to nondestructive testing (NOT) not detecting the full extent of required work. It approves an increase of $1,157,009 in the cost of the Work Order, deeming the over-expenditure warranted.