NS Power's contractor performed a test to assess the poles' condition and administered retreatment when necessary. Since the testing is done at the time of retreatment, the full scope of poles requiring treatment was not known in advance....
AI summary NS Power's pole retreatment project faced delays due to remote locations, adverse terrain, and a cyber incident. The project was completed a year late, and the Board approved the final cost of $791,054, finding the project reasonable and justified.