HomeCost RecoveryM12696Evidence
Topic/Matter Intersection

Topic:"Cost Recovery" in M12696

Matter: NSP Maritime Link Inc. (NSPML) - Application to Review the Holdback Mechanism
56 passages 28 documents

Cost Recovery across all matters →

N-1Application 4 passages
1 Q11. WHAT ARE YOUR OVERALL CONCLUSIONS? p. p. 42
1 Q11. WHAT ARE YOUR OVERALL CONCLUSIONS? 2 A11. Good utility practice is critical to ensure that the bulk power system is able to generate and 3 deliver energy to customers and should be encouraged. NSPML should not be penalized 4 for pla...

AI summary NSPML qualifies for relief from the holdback mechanism as conditions for termination are met, with Nova Scotians receiving 140% of contractual energy volumes. The Maritime Link delivered $495MM in renewable energy, exceeding NSPML's costs. The Board's traditional oversight mechanisms are deemed sufficient for asset management and energy procurement.

25 Q12. PLEASE DESCRIBE THE HOLDBACK MECHANISM. p. pp. 42-43
25 Q12. PLEASE DESCRIBE THE HOLDBACK MECHANISM. 26 A12. The holdback mechanism was implemented by the Board in a September 11, 2017, decision 27 regarding the application of NSPML for approval of an interim cost assessment and 1 approval t...

AI summary The holdback mechanism, established in 2017 by the Board, ensures ratepayer protection by withholding funds from NSPML/NS Power until 90% of energy delivery targets are met. Adjusted in 2022 to $2 million monthly, it funds replacement energy costs if targets are unmet, with a review planned for 2023. This mechanism addresses uncertainty in energy deliveries from the Labrador-Island Link.

13 Q13. DID THE BOARD PROVIDE A STATED PURPOSE FOR THE HOLDBACK 14 MECHANISM? p. pp. 43-44
13 Q13. DID THE BOARD PROVIDE A STATED PURPOSE FOR THE HOLDBACK 14 MECHANISM? 15 A13. Yes. In 2019, the Board noted that the holdback was put in place "to provide an incentive 16 to ensure that NSPML and NS Power achieved the promised bene...

AI summary The Board established the holdback mechanism in 2019 to incentivize NSPML and NS Power to deliver promised benefits of the Maritime Link before the NS Block. Subsequent 2022-2023 proceedings emphasized addressing imbalances between NSPML and ratepayers, who faced replacement energy costs due to poor deliveries, while addressing intergenerational equity concerns.

11 Q17. HAVE DELIVERIES OVER THE MARITIME LINK IMPROVED SINCE THE 12 HOLDBACK MECHANISM WAS IMPLEMENTED? p. pp. 46-47
itment to 17 maintaining its assets in a proactive and preventative manner in accordance with good 18 utility practice. In fact, the Maritime Link has exceeded 99% monopole availability since 19 2020. 20 Without an allowance for planned ou...

AI summary The Maritime Link has achieved over 99% monopole availability since 2020. NSPML argues that without accounting for planned outages, it cannot meet termination criteria for the Holdback Mechanism, leading to ongoing under-recovery of prudently incurred costs, while customers receive energy on time under the ECA terms.

N-3NSPML (CA) RIRs 1-4 - Redacted 2 passages
NSPML Responses to Consumer Advocate Information Requests
NSPML Responses to Consumer Advocate Information Requests 1 month that resulted in excessive icing). Additional details to support the request for relief 10 (f) Please provide the WACC calculations in a workbook, with formulas intact. 11 1...

AI summary NSPML provides responses to information requests from the consumer advocate, including details on WACC calculations, holdback retention, replacement costs for deferred energy, and the impact on customers. The responses reference attachments and audit processes by Bates White.

NSPML Responses to Consumer Advocate Information Requests
NSPML Responses to Consumer Advocate Information Requests 1 2 3 4 5 accordance with the 30-day outage coordination period previously established by the system operators for outages affecting the delivery of the NS Block, including planned...

AI summary The document contains a request from the Consumer Advocate to NSPML regarding the distribution of a retained holdback and the recovery of an additional $1.1 million in 'updated WACC consideration.' The request also inquires about the delay in applying for a review of the holdback mechanism and its impact on intergenerational equity.

N-4NSPML (IG) RIRs 1-26 - Redacted 8 passages
PARTIALLY CONFIDENTIAL p. pp. 20-25
PARTIALLY CONFIDENTIAL 1 Importantly, the Board's past decisions have been very consistent in terms of disallowances 2 matching harm to customers. At the start of the Holdback process, there was little question 3 that the extent of delays...

AI summary The Board's past decisions consistently disallowed customer harm from delays, with Make-up Energy deliveries post-LIL commissioning showing negligible or slightly positive impacts. NSPML asserts that Make-up Energy has provided customer benefits, supported by a Similar Value Analysis and replacement cost reviews, with no negative impact from contractual remedies.

PARTIALLY CONFIDENTIAL p. p. 42
PARTIALLY CONFIDENTIAL 1 While NSPML does not consider Holdback issues while planning outages, the design of 26 Application, NSPML has requested termination of the holdback mechanism and, in the 27 alternative if the Board determines that...

AI summary NSPML has requested the termination of the holdback mechanism and, if it continues, a separate mitigation process. The application seeks approximately $16.5 million, including deferred interest and WACC calculations. The Board is asking for explanations regarding the interest claim and verification of the figures in Appendix B.

NSPML Responses to Industrial Group Information Requests p. p. 42
NSPML Responses to Industrial Group Information Requests 1 exists for specific reasons, and those reasons no longer existed. NSPML submits that 24 a) The ~$15 million in holdback has been recorded as a revenue by NSPML in the applicable 25...

AI summary NSPML explains that the release of a holdback would not affect its income statement, revenue requirement, return on equity, or WACC calculation. The holdback is treated as a return of equity, reducing average equity thickness slightly. It also notes that the release would not impact debt service coverage ratios, loan covenants, or FAM reporting.

5.17 Taxes. p. p. 108
stions from Interconnection Customer about the conduct of the contest, and shall reasonably permit Interconnection Customer or an Interconnection Customer representative to attend contest proceedings. Interconnection Customer shall pay to...

AI summary The text outlines obligations between an Interconnection Customer and Transmission Provider regarding cost recovery for legal contests. The Interconnection Customer must reimburse documented costs incurred by the Transmission Provider during appeals or protests. Settlements require either customer consent or approval from tax counsel, with liability relief if settlements occur without consent.

5.19 Modification. p. pp. 111-112
5.19 Modification. 5.19.1 General. Either Party may undertake modifications to its facilities. If a Party plans to undertake a modification that reasonably may be expected to affect the other Party's facilities, that Party shall provide to...

AI summary Section 5.19 outlines procedures for facility modifications under a JOA, requiring advance notice, confidentiality, and cost allocation rules. Modifications must comply with LGIA and Good Utility Practice. Interconnection Customer is not liable for Transmission Provider's modification costs but must cover their own necessary upgrades.

9.7.1 Outages. p. p. 123
ion Customer to reschedule its maintenance as necessary to maintain the reliability of the Transmission System; provided, however, adequacy of generation supply shall not be a criterion in determining Transmission System reliability. Trans...

AI summary The Transmission Provider may require an Interconnection Customer to reschedule maintenance to ensure Transmission System reliability, excluding generation supply adequacy as a reliability criterion. Compensation is mandated for additional costs incurred by the customer, excluding cases where the customer modified maintenance schedules within the prior 12 months.

11.4 Transmission Credits. p. p. 130
11.4 Transmission Credits. 11.4.1 Repayment of Amounts Advanced for Network Upgrades. Interconnection Customer shall be entitled to a cash repayment, equal to the total amount paid to Transmission Provider and Affected System Operator, if...

AI summary The section outlines a repayment mechanism for Interconnection Customers who paid for Network Upgrades. Repayment equals payments made to Transmission Providers and Affected System Operators, excluding refunds under Article 5.17.8. Interest is calculated per FERC regulations (18 C.F.R. § 35.19a(a)(2)(iii)) from payment dates until repayment. Rights may be assigned to third parties.

Article 12. Invoice p. pp. 133-134
Article 12. Invoice 12.1 General. Each Party shall submit to the other Party, on a monthly basis, invoices of amounts due for the preceding month. Each invoice shall state the month to which the invoice applies and fully describe the servi...

AI summary Article 12 outlines invoicing procedures between parties under the LGIA, including monthly billing, netting of mutual debts, final invoices post-construction, payment timelines, and dispute resolution mechanisms. Transmission Provider must issue detailed final invoices and refund overpayments, while disputes require escrow arrangements and interest calculations per FERC regulations.

N-5NSPML (NSEB) RIRs 1-19 - Redacted 2 passages
NSPML Responses to NSEB Information Requests p. p. 4
NSPML Responses to NSEB Information Requests 1 Request IR-01: 17 18 [38] NSPML's Compliance Filing calculations of the released holdback funds included WACC on balances owing. The Industrial Group opposed this aspect 19 of the calculations...

AI summary NSPML included WACC in the calculation of released holdback funds, which the Industrial Group opposed. The Board agreed that WACC should be applied to funds owing or receivable, recognizing the reciprocal nature of financing costs. NSPML also emphasized balancing obligations to provide the most benefit to Nova Scotians, particularly in maintaining the Maritime Link.

NSPML Application to Review the Holdback Mechanism (NSEB M12696) NSPML Responses to NSEB Information Requests p. p. 4
NSPML Application to Review the Holdback Mechanism (NSEB M12696) NSPML Responses to NSEB Information Requests

AI summary NSPML has submitted an application to review the holdback mechanism (NSEB M12696) and provided responses to NSEB information requests. The proceeding involves evaluating the mechanism's structure and implications for cost recovery and regulatory compliance.

N-7Evidence - BW 2 passages
Q. What is the purpose of your evidence in this proceeding? p. p. 2
Q. What is the purpose of your evidence in this proceeding? - A. On February 3, 2026, NSP Maritime Link, Inc. ("NSPML") filed an Application with the - Nova Scotia Energy Board ("Board") requesting the end of a revenue holdback mechanism -...

AI summary NSPML seeks to end a revenue holdback mechanism related to cost recovery from NSPI for the Maritime Link project. Bates White, the Board's consultant, is reviewing the application. The proceeding involves NSPML, NSPI, and the Nova Scotia Energy Board.

Q. When did NSPML receive approval for recovery of the Maritime Link costs? p. pp. 3-5
Q. When did NSPML receive approval for recovery of the Maritime Link costs? - A. On December 16, 2016, NSPML applied to the Board for approval of an "interim cost - assessment and approval to commence recovery" of those interim costs from...

AI summary NSPML applied for interim cost recovery approval on December 16, 2016, which the Board granted in September 2017 (M07718). The Board approved recovery but imposed a $10M annual holdback until 2018–2019 benefits were proven. The Maritime Link was commissioned in January 2018, with further cost recovery requests in 2019 due to delays in NLH projects.

N-8Evidence - CA 5 passages
IV. Ratepayer Responsibility for Paying Accrued WACC p. pp. 7-8
IV. Ratepayer Responsibility for Paying Accrued WACC - Q: Please summarize NSPML's request to recover accrued WACC. - A: NSPML requests "updated WACC consideration to the date of the Board's Decision."[29](#page-8-1) The - total amount dep...

AI summary NSPML requests recovery of accrued WACC up to the Board's decision date, citing $1.1M by 2025. It argues WACC is a standard financing mechanism and that customers would not pay it twice. The delay in filing was due to staffing constraints and reliance on third-party data from NLH and NS Power.

Q: Why might the Board wish to consider a different approach? p. pp. 8-9
Q: Why might the Board wish to consider a different approach? - A: The Board may wish to consider whether NSPML recovering full WACC on deferred balances reflects risk-appropriate compensation. Where a utility's regulatory receivable is es...

AI summary The Board may consider using a debt-only carrying charge instead of WACC for NSPML's deferred balances, as the regulatory receivable is a risk-free asset. This approach is common in North American jurisdictions and aligns with recent financing arrangements involving Nova Scotia Power. The 21-month delay in recovery is seen as unusual, and the Board has discretion to apply this alternative method.

Q: What is your recommendation? p. p. 10
Q: What is your recommendation? - A: I recommend that the Board direct release of the Holdback as discussed in Section III plus a carrying charge calculated at NSPML's approved cost of debt through the date of the Board Decision on this ma...

AI summary The respondent recommends releasing the Holdback with a carrying charge calculated at NSPML's approved cost of debt, reduced by $270,000 due to a 21-month delay. This adjustment aims to reflect the deferred costs associated with the delayed application.

SUMMARY OF PROFESSIONAL EXPERIENCE p. p. 10
SUMMARY OF PROFESSIONAL EXPERIENCE - 2023– Present Vice President, Grid Strategies, LLC . Provides research, technical assistance, and expert testimony on electric- and gas-utility planning, economics, and regulation. Reviews electric util...

AI summary The individual has extensive experience in utility regulation, energy efficiency, and renewable energy, including roles at Grid Strategies, Southern Alliance for Clean Energy, and Resource Insight. They have provided expert testimony, designed programs, and evaluated resource planning and procurement strategies for regulated and competitive markets.

EXPERT TESTIMONY p. p. 10
EXPERT TESTIMONY - 2008 South Carolina PSC Docket No. 2007-358-E, surrebuttal testimony on behalf of Environmental Defense, the South Carolina Coastal Conservation League, Southern Alliance for Clean Energy and the Southern Environmental L...

AI summary Expert testimony from 2008–2010 details advocacy for energy efficiency cost recovery mechanisms (shareholder incentives, lost revenue adjustments) and evaluation of integrated resource plans by SACE, Environmental Defense, and allied organizations in South Carolina, North Carolina, and Georgia regulatory proceedings.

N-9BW (IG) RIR 1 to 5 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act and the Maritime Link Act and the Maritime Link Cost Recovery Process Regulations -and- IN THE MATTER OF: An Application by NSP Maritime Link Inc. to end the holdback mech...

AI summary The Nova Scotia Energy Board addresses two matters: the Public Utilities Act and Maritime Link Act, and an application by NSP Maritime Link Inc. to terminate a holdback mechanism under parameters set by the Nova Scotia Utility and Review Board in Matter 11009.

N-10CA (IG) RIR 1 to 4 1 passage
1 M12696 p. p. 2
Date Filed: June 11, 2026 CA (IG) Page 1 of 5 1 M12696 2 3 NOVA SCOTIA ENERGY BOARD 4 5 6 IN THE MATTER OF: The Public Utilities Act and the Maritime Link Act and the Maritime Link Cost Recovery Process Regulations 7 8 9 -and 10 11 12 IN T...

AI summary This document is an information request filed in a regulatory proceeding related to the Public Utilities Act, the Maritime Link Act, and the Maritime Link Cost Recovery Process Regulations. It involves NSP Maritime Link Inc. and requests information from various entities, including the Nova Scotia Consumer Advocate and legal counsel.

100872Hearing Order 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF the PUBLIC UTILITIES ACT and the MARITIME LINK ACT and the MARITIME LINK COST RECOVERY PROCESS REGULATIONS – and – IN THE MATTER OF AN APPLICATION by NSP MARITIME LINK INC. to end the holdback mech...

AI summary The Nova Scotia Energy Board is considering an application by NSP Maritime Link Inc. to terminate the holdback mechanism under the Public Utilities Act and Maritime Link Cost Recovery Process Regulations, referencing parameters set in Matter M11009. The proceeding involves the Maritime Link Act and regulatory compliance.

100901Notice of Intervention - SBA 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act and the Maritime Link Act and the Maritime Link Cost Recovery Process Regulations - and - IN THE MATTER OF: An Application by NSP Maritime Link Inc. to end the holdback me...

AI summary The Nova Scotia Energy Board is addressing an application by NSP Maritime Link Inc. to terminate the holdback mechanism under the Public Utilities Act and Maritime Link Cost Recovery Process Regulations, referencing parameters set by the Nova Scotia Utility and Review Board in Matter Ml1009.

100932Notice of Intervention - CA 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act and the Maritime Link Act and the Maritime Link Cost Recovery Process Regulations -and- IN THE MATTER OF: An Application by NSP Maritime Link Inc. to end the holdback mech...

AI summary The Nova Scotia Energy Board is considering an application by NSP Maritime Link Inc. to terminate a holdback mechanism under the Public Utilities Act and Maritime Link Act, as outlined in Matter 11009. The proceeding involves regulatory approval for ending cost recovery processes tied to the Maritime Link project.

101084Notice of Intervention - DOE 1 passage
NOVA SCOTIA ENERGY BOARD p. p. 1
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act, and the Maritime Link Act and the Maritime Link Cost Recovery Process Regulations. - and – IN THE MATTER OF: An Application by NSP Maritime Link Inc. to end the holdback...

AI summary The Nova Scotia Energy Board addresses two matters: the Public Utilities Act and Maritime Link Act, and an application by NSP Maritime Link Inc. to terminate a holdback mechanism under Matter M11009. The application seeks to end the mechanism based on parameters set by the Nova Scotia Utility and Review Board.

101152Participant List 1 passage
IN THE MATTER OF the PUBLIC UTILITIES ACT and the MARITIME LINK ACT and the MARITIME LINK COST RECOVERY PROCESS REGULATIONS
IN THE MATTER OF the PUBLIC UTILITIES ACT and the MARITIME LINK ACT and the MARITIME LINK COST RECOVERY PROCESS REGULATIONS – and – IN THE MATTER OF AN APPLICATION by NSP MARITIME LINK INC. to end the holdback mechanism in accordance with...

AI summary NSP Maritime Link Inc. seeks to terminate the holdback mechanism under parameters established by the Nova Scotia Utility and Review Board in Matter M11009, relating to the Maritime Link Cost Recovery Process Regulations and the Public Utilities Act.

101306NSEB (NSPML) IR 1 to 19 - PDF 2 passages
30 Request IR-3:
30 Request IR-3: 32 31 With respect to Exhibit N-1, Appendix B, 36 33 (a) Please explain the reason(s) for under delivery in each month in which the holdback was 34 retained, including the start and end date for each reason and the total u...

AI summary The document requests explanations for under delivery and holdback calculations related to the LIL's performance, including outage causes and WACC computations. It seeks detailed breakdowns of under delivery reasons, holdback estimates, and WACC calculations with formulas intact.

22 Request IR-4:
22 Request IR-4: 3 11 19 21 27 30 33 36 43 23 On p. 6 of Exhibit N-1, NSPML requests that in addition to distributing $15.4 million in retained 24 holdback (see Appendix B), the Board also require that NS Power distribute $1.1 Million in 2...

AI summary NSPML requests the Board to distribute $1.1 million in 'updated WACC consideration' alongside a $15.4 million holdback. However, Exhibit N-1 does not justify this request beyond Appendix B. The Board is asked to confirm the request, explain the delay in reviewing the holdback mechanism, and assess if the 'updated WACC consideration' impacts intergenerational equity, referencing a prior decision (M10206).

101307NSEB (NSPML) IR 1 to 19 - Word 1 passage
Section 4
le switching” 3. July – October 2024 4. January 2025 5. April 2025 6. September 2025 6. Please provide the WACC calculations in a workbook, with formulas intact. Request IR-4: On p. 6 of Exhibit N-1, NSPML requests that in addition to dist...

AI summary The document requests confirmation and explanation regarding NSPML's request for an additional $1.1 million in 'updated WACC consideration' and its delay in applying for a review of the holdback mechanism. It also asks for NSPML's view on whether the accumulation of this amount affects intergenerational equity concerns, referencing a prior Board decision.

101308CA (NSPML) IR 1 to 4 - PDF 2 passages
1 M12696
1 M12696 2 3 4 NOVA SCOTIA UTILITY AND REVIEW BOARD 5 6 IN THE MATTER OF: The Public Utilities Act and the MARITIME LINK ACT and 7 8 the MARITIME LINK COST RECOVERY PROCESS REGULATIONS 9 10 11 – and – 12 13 IN THE MATTER OF: AN APPLICATION...

AI summary The document outlines a regulatory proceeding (M12696) involving NSP Maritime Link Inc.'s application to terminate a holdback mechanism under the Public Utilities Act and Maritime Link Act, referencing prior matter M11009. The Consumer Advocate has issued an information request to Shellie Woolham, with responses due by April 9, 2026.

22 Request IR-4:
22 Request IR-4: 3 11 19 21 27 30 33 36 43 23 On p. 6 of Exhibit N-1, NSPML requests that in addition to distributing $15.4 million in retained 24 holdback (see Appendix B), the Board also require that NS Power distribute $1.1 Million in 2...

AI summary NSPML requests the Board to distribute $1.1 million in 'updated WACC consideration' alongside retained holdback funds, but inconsistencies exist in their exhibit. The Board is asked to confirm the request, identify justification, explain the two-year delay in reviewing the holdback mechanism, and assess intergenerational equity impacts.

101309CA (NSPML) IR 1 to 4 - Word 2 passages
Section 3
ths NSPML has met the requirements in provision (2) and provide a workbook with the data included in the graph shown in Exhibit N-1, p. 14. Request IR-3: With respect to Exhibit N-1, Appendix B, 1. Please explain the reason(s) for under de...

AI summary The document outlines specific requests related to the NSPML's compliance with provision (2), including explanations for under delivery, calculations of holdback amounts, and analysis of LIL outages. It also requests WACC calculations in a workbook.

Section 4
le switching” 3. July – October 2024 4. January 2025 5. April 2025 6. September 2025 6. Please provide the WACC calculations in a workbook, with formulas intact. Request IR-4: On p. 6 of Exhibit N-1, NSPML requests that in addition to dist...

AI summary The document requests clarification on NSPML's request for an additional $1.1 million in 'updated WACC consideration' and seeks justification for the delay in applying for a review of the holdback mechanism. It also asks for NSPML’s view on whether this accumulation affects intergenerational equity concerns.

101310SBA (NSPML) IR 1 to 6 - PDF 2 passages
Request IR-2:
Request IR-2: Refer to the Application, Section 1. Introduction, page 6 of 37, lines 15-21, which states: NSPML therefore requests that: - the Board deem the Holdback to have ended effective May 1, 2024; and - the Board order that all Hold...

AI summary NSPML requests the Board to end the Holdback effective May 1, 2024, and distribute retained amounts with updated WACC. The Board questions the timing amid 2025 unplanned outages, reliability concerns for the Maritime Link, and LIL's climate resilience. NSPML's response to LIL design risks and responsibility for long-term solutions is queried.

Request IR-5:
Request IR-5: Refer to the Application, Section 5. Future Asset Management Expectations, pages 23-25 of 37, that described unplanned outages during 2024 that were followed by deliveries of "Deferred Energy". - a) NSPML states on page 24, l...

AI summary The document requests clarification on NSPML's management of Deferred Energy from unplanned outages in 2024 and 2025, including replacement costs, NLH's role in redelivery, and measures to prevent future outages. It questions cost differences between redelivery periods, NLH's demand impact, and NSPML's compliance with Good Utility Practice.

101312IG (NSPML) IR 1 to 26 - Redacted 2 passages
12 Request IR-13:
12 Request IR-13: - 13 Reference: N-01 Application, Section 5.0 and Section 6.0, pages 23-27. - 14 Preamble: The Application states that as of the end of 2025, approximately $15.3 million 15 in holdback funds relates to the post-Compliance...

AI summary The text raises questions about NSPML's holdback funds related to planned outages between July 2024 and October 2024, including whether all outages were planned, if forced outages were excluded, and how outage timing affected holdback calculations. It references a $15.3 million holdback fund and a $4 million holdback tied to an extended outage.

1 Request IR-14:
- 1 Request IR-15: - 2 Reference: N-01 Application, Section 6.0; and Appendix B. - 3 And Reference: Matter M11773, N-01 NSPML Holdback Mechanism Letter (June 28, - 4 2024). - 5 Preamble: Appendix B sets out holdback amounts since the Compl...

AI summary NSPML requests interest on deferred holdback funds, verification of financial figures, and a separate proceeding to design a continuing holdback mechanism. The Board questions NSPML's entitlement to interest, data sources, and calculation details, citing prior compliance period data and WACC rates.

101315Bates White (NSPML) IR 1 to 22 - PDF 1 passage
NOVA SCOTIA ENERGY BOARD p. p. 8
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT and the MARITIME LINK ACT and the MARITIME LINK COST RECOVERY PROCESS REGULATIONS - and - IN THE MATTER OF: AN APPLICATION by NSP MARITIME LINK INC. to end the holdback me...

AI summary The Nova Scotia Energy Board is reviewing NSP Maritime Link Inc.'s application to terminate a holdback mechanism, referencing Matter M11009. Bates White LLC has issued information requests regarding financial data in appendices, including Supplemental Block volumes and calculations of outstanding balances under the Maritime Link Cost Recovery Process.

101398Letter from NSPML providing further justification for extension request 1 passage
Section 1 p. p. 0
March 27, 2026 ƌLJƐƚĂů͘,ĞŶǁŽŽĚΛŶŽǀĂƐĐŽƚŝĂ͘ĐĂ DƐ͘ƌLJƐƚĂů,ĞŶǁŽŽĚ ůĞƌŬŽĨƚŚĞŽĂƌĚ Nova Scotia ŶĞƌŐLJŽĂƌĚ ϭϲϬϭ>ŽǁĞƌtĂƚĞƌ^ƚƌĞĞƚ͕ϯƌĚ&ůŽŽƌ Halifax, Nova Scotia B3J 3P6 ĞĂƌDƐ͘,ĞŶǁŽŽĚ: RE: NSP Maritime Link Inc. (NSPML) – Application to end the Holdb...

AI summary NSP Maritime Link Inc. (NSPML) applies to terminate the Holdback Mechanism (M12696) under the EPCOR Western Division (EWD) agreement, citing project completion and the need to adjust the mechanism to reflect current conditions. The mechanism was designed to ensure cost recovery for the Maritime Link project, but NSPML argues it should now be ended.

101452Amended Hearing Order - timeline has been amended 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF the PUBLIC UTILITIES ACT and the MARITIME LINK ACT and the MARITIME LINK COST RECOVERY PROCESS REGULATIONS – and – IN THE MATTER OF AN APPLICATION by NSP MARITIME LINK INC. to end the holdback mech...

AI summary NSP Maritime Link Inc. seeks to terminate a holdback mechanism under the Maritime Link Cost Recovery Process Regulations, referencing parameters set by the Nova Scotia Utility and Review Board in Matter M11009. The proceeding involves the Public Utilities Act and Maritime Link Act.

101681Confidential Undertaking 1 passage
NSPML Application to Review the Holdback Mechanism
NSPML Application to Review the Holdback Mechanism

AI summary NSPML seeks to review the holdback mechanism, a regulatory process component affecting cost recovery and rate design. The application highlights concerns over its effectiveness and alignment with current energy efficiency and affordability goals.

101682Letter from NSPML re: RIRs / confidentiality 1 passage
Section 1 p. p. 0
April 21, 2026 [[email protected]](mailto:[email protected]) Ms. Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, Nova Scotia B3J 3P6 Dear Ms. Henwood: RE: M126...

AI summary NSP Maritime Link Inc. (NSPML) submitted responses to information requests in M12696, seeking confidential treatment for documents containing commercially sensitive data, third-party information, and performance data from Newfoundland and Labrador Hydro (NLH). The request emphasizes protecting negotiation capabilities and adhering to third-party distribution restrictions.

102697Submission - CA 1 passage
Submissions p. p. 3
ACC is paid to the utility when customers owe money. Should the Board agree with NSPML's request in this Application, the $15.3 million should have been paid to NSPML in 2024 and 2025.[14](#page-3-6) Although the Board has previously allow...

AI summary The document discusses a request by NSPML for ACC payments, with a recommendation by Mr. Wilson to adjust the carrying charge due to a 21-month delay in the application. The CA supports this recommendation, and the Consumer Advocate submits their comments to the Board.

102698Submission - NSPML 2 passages
Section 24 p. p. 16
1 this aspect of the calculations because the payment of WACC was not 2 explicit in the Board's prior holdback decisions. 3 4 [39] Where funds are owed but not yet paid, either between utilities, or 5 between a utility and its customers, t...

AI summary The document discusses the recovery of financing costs (WACC) for holdback funds owed to NSPML, emphasizing that the Board historically allowed for WACC recovery when funds were owed to customers. NSPML agrees with this approach, noting that the timing of the holdback filing did not prejudice the regulatory process.

Section 25 p. p. 16
f WACC 32 on customers is the same as if the funds were provided to NSPML in the first 33 place. 34 35 John Wilson proposed that holdback funds be released to NSPML since the end of the 36 Compliance Period, but with a carrying charge to b...

AI summary The document discusses the recommendation to release holdback funds to NSPML with a carrying charge calculated at NSPML's approved cost of debt, rather than using WACC. John Wilson suggests this approach, while NSPML agrees but prefers WACC. The discussion references past imbalances in Nova Scotia and cites a Board decision (M11009) supporting the use of WACC.

102699Submission - IG 6 passages
LEGISLATIVE FRAMEWORK p. p. 0
LEGISLATIVE FRAMEWORK The Maritime Link Act , SNS 2012, c 9 (the " ML Act "), and the Maritime Link Cost Recovery Process Regulations , NS Reg 189/2012 (the " ML Regulations "), establish an approval mechanism by which NSPML recovers its c...

AI summary The legislative framework outlines the Maritime Link Act and ML Regulations , establishing how NSPML recovers costs from NSPI and ratepayers. The Board has broad jurisdiction and imposed conditions on cost recovery to ensure fairness and consistency, including the Holdback as a customer-protection measure.

HISTORY OF HOLDBACK p. p. 2
d to pay for replacement cost energy would be paid over to NSPML. This holdback mechanism will continue in each and every month during 2022 and then will be reviewed by the Board in January of 2023. [32] The fact that today's customers are...

AI summary The document discusses the holdback mechanism implemented by Nova Scotia Power Maritime Link (NSPML) to address intergenerational equity concerns related to the Maritime Link project. The holdback is intended to ensure that current customers contribute to the replacement cost of energy, with the mechanism being reviewed by the Board in 2023. The Board believes this approach will not jeopardize NSPML's ability to service its federal loan-guaranteed debt.

[Emphasis added] p. pp. 2-3
[Emphasis added] The $2 million holdback continued following the 2023 cost assessment proceeding.[5](#page-3-0) Separately, the Board initiated a proceeding, Matter M11009, to consider the disposition of the Holdback in all months during 2...

AI summary The document discusses the $2 million holdback following the 2023 cost assessment proceeding and the Board's initiation of Matter M11009 to address the disposition of the holdback. The Board directed the crediting of $12 million to ratepayers, increased the monthly holdback, and established conditions for termination, including consistent performance and relief provisions under exceptional circumstances.

CONSISTENT PERFORMANCE HAS NOT BEEN ACHIEVED OVER THE COMPLIANCE PERIOD p. p. 12
CONSISTENT PERFORMANCE HAS NOT BEEN ACHIEVED OVER THE COMPLIANCE PERIOD The Industrial Group notes the importance of examining the full picture of the 12-month Compliance Period in determining whether the multiple failures in delivery, inc...

AI summary The Industrial Group argues that NSPML has not consistently met delivery performance thresholds over the 12-month Compliance Period, with significant underdeliveries, and that terminating the Holdback would be unreasonable given ongoing performance issues and the financial burden on ratepayers. They emphasize the need for continued compliance before removing protections.

NO INTEREST ON POST-COMPLIANCE PERIOD HOLDBACK AMOUNTS p. pp. 12-13
NO INTEREST ON POST-COMPLIANCE PERIOD HOLDBACK AMOUNTS In the alternative, should the Board find that the evidence supports termination of the Holdback effective May 1, 2024, the Industrial Group submits that NSPML should not be entitled t...

AI summary The Industrial Group argues that NSPML should not recover interest on post-compliance holdback funds due to its delayed application. NSPML delayed filing its application for over 20 months, leading to over $15.3 million in withheld funds and over $1 million in accumulated interest. The Industrial Group claims this delay is unreasonable and should not be compensated by ratepayers.

CONCLUSION p. p. 13
CONCLUSION The Industrial Group respectfully requests that the Board: - 1. Reject NSPML's request to terminate the Holdback retroactively to May 2024 on the basis that: - (a) NSPML has not demonstrated full compliance with the Board's hold...

AI summary The Industrial Group requests the Board to reject NSPML's retroactive termination of the Holdback due to non-compliance with conditions and lack of justification for relief. Alternatively, if termination is granted, they argue that NSPML should not receive WACC on post-Compliance Period holdback amounts due to delays in the application.

102909Reply Submission - NSPML 1 passage
2.5 WACC p. pp. 27-28
2.5 WACC NSPML maintains that WACC should be recovered on all holdback funds withheld since May 1, 2024, when the Holdback cessation conditions were satisfied. This reflects the true carrying cost of the capital and as already submitted, i...

AI summary NSPML argues that the Weighted Average Cost of Capital (WACC) should be recovered on all holdback funds withheld since May 1, 2024, citing the true carrying cost of capital and established mechanisms. They also explain the delay in filing the Application due to resource constraints and the need for evidence from NLH and NS Power.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →