SUMMARY This study was initiated to determine the requirements and conditions for the proposed interconnection of 2.2 MW of solar generation with inverters by the Interconnection Customer (IC) at the West Petpeswick Road, Musquodoboit Harb...
AI summary This report outlines the interconnection requirements for a 2.2 MW solar farm in Musquodoboit Harbour, Nova Scotia. Alternative C was selected after evaluation, requiring a gang-operated switch and NSPI to upgrade distribution facilities at the Interconnection Customer's expense. Key responsibilities include the IC covering line extensions, right-of-way acquisition, and maintenance costs.
REDACTED CI C0083591 Attachment 1 Page 3 of 39 REDACTED (CONFIDENTIAL INFORMATION REMOVED) guy replacements, and customer owned equipment such as the gang-operated switch is not included in these estimates. - The cost estimate to complete...
AI summary The document outlines interconnection requirements for a solar project, including a $1,062,874 cost estimate, compliance with NSPI standards, flicker emission management, power factor specifications, and electrical safety protocols. NSPI retains operational control over high-voltage equipment and may disconnect the facility if flicker issues persist. The Interconnection Customer must adhere to electrical codes and obtain permits.
6.0 INTERCONNECTION FACILITIES REQUIREMENTS The following subsections outline the Interconnection Facility requirements and the responsibilities of the Interconnection Customer and NSPI for procurement and installation. All costs incurred...
AI summary The section outlines interconnection facility requirements, specifying that the Interconnection Customer bears all costs incurred by NSPI. NSPI owns distribution spans up to the gang-operated disconnect switch and controls the recloser at the POI, while the customer owns equipment beyond the gang switch. Compliance with the Standard Protection Code is mandated for safety.