Matter: Nova Scotia Power Inc. - CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester - $6,957,058 (ATO)
1 passage 1 document

Cost Recovery across all matters →

103025NSEB (NSPI) IR-1 to IR-10 1 passage
Request IR-7:
Request IR-7: - With regard to the "Capital Project Detailed Estimate" provided on Page 4 of 6 of the current application: - a) Please provide a comparison of the materials unit costs for wood poles, insulators and O/H conductors to the un...

AI summary The document requests detailed comparisons and explanations regarding material and contract cost estimates for wood poles, insulators, and overhead conductors in NS Power's current ATO application versus the 2024 ACE Plan. It also seeks clarification on cost variances, CU rates, and the reasons for increased material and contract costs.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →