Reason for Variance - FIN The decrease of $632,853 compared to the approved 2024 ACE Plan budget of $1,460,062 is due to cost minimization opportunities identified during detailed design to reduce project costs while still achieving all pr...
AI summary The project's budget decreased by $632,853 due to cost-saving measures like reusing existing reactor pedestals and using smaller reactors than initially estimated. These savings were partially offset by higher crane and relocation costs and an external insulation study. The project was completed in December 2024, with the final cost date set for August 2026 to allow for financial reconciliation after a cyber event.