Matter: Nova Scotia Power Inc. - CI C0068718 – IT - DERMS Solution Project - $2,965,414
2 passages 2 documents

Cost Recovery across all matters →

N-1CI C0068718 IT – DERMS Solution Project - Application - Redacted 1 passage
Execution Year: 2025-2027
Execution Year: 2025-2027 Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour Project Manager PD 270 $ 420 $ 113,400 OT BSA PD 229 $ 420 $ 96,180 IT Integration Sp...

AI summary This document outlines a cost estimate for a project spanning 2025-2027, detailing labor, contracts, planning, and capital contributions. It includes breakdowns of labor costs, contract expenses, and other financial considerations such as contingency and administrative overhead.

N-2NSPI (NSEB) RIR 1 to 5 1 passage
Qualitative Assessment Criteria p. p. 78
Qualitative Assessment Criteria To prioritize the strategies and initiatives, each was qualitatively assessed across four dimensions: - • Strategic Fit: Alignment with stakeholder mandates, directives, goals and objectives, and there is cl...

AI summary The document outlines qualitative assessment criteria for prioritizing strategies and initiatives, focusing on strategic fit, benefits, cost favourability, and risk management. Each criterion evaluates alignment with goals, benefits to the system and society, cost considerations, and risk mitigation.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →