Topic:"Cost Recovery" in M13127

Matter: Nova Scotia Power Inc. - CI C0086325 – Maritime Launch Services - $0 (U&U)
1 passage 1 document

Cost Recovery across all matters →

N-1CI C0086325 – Maritime Launch Services - Application - Redacted 1 passage
Preamble p. p. 8
This project is being filed as a Class 3 estimate. The defined deliverables for this project indicate that 85% of Class 3 deliverables are completed. A contingency value of 0% was selected as this project is customer contributed and any po...

AI summary The project is being filed as a Class 3 estimate, with 85% of deliverables completed. A 0% contingency was selected because the project is customer-contributed, and any additional costs will be recovered from the customer.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →