Matter: Nova Scotia Power Inc. - 2027 Annually Adjusted Rates (AARs)
81 passages 1 document

Cost Recovery across all matters →

N-1Application - Redacted 81 passages
1 3.0 LOAD FOLLOWING PORTION OF THE GRLF TARIFF p. pp. 14-15
1 3.0 LOAD FOLLOWING PORTION OF THE GRLF TARIFF 2 - 3 The GRLF Tariff is available to customers who have their own generation of continuous capability, - 4 normally used to support the customer's own load, where the customer has signed an...

AI summary The text describes the Grid Reliability Levy Fee (GRLF) Tariff, which is available to customers with their own continuous generation capabilities who have operating agreements with NS Power. The tariff consists of three components: Generation Replacement (GR), which provides backup power during outages or maintenance at incremental cost plus a fixed adder; Optional Load Following (LF), an energy-only charge for customers with process limitations; and Spill Service, which involves NS Power receiving surplus generation from the customer. Currently, two customers utilize these services.

1 4.0 ONE-PART REAL-TIME PRICING TARIFFS p. pp. 15-17
1 4.0 ONE-PART REAL-TIME PRICING TARIFFS 2 - 3 There are two 1P-RTP Tariffs: One Part Transmission RTP Tariff and One Part Distribution - 4 Voltage RTP Tariff. Each of these tariffs include energy charges with two components: hourly - 5 ma...

AI summary The document describes the structure of two One-Part Real-Time Pricing (1P-RTP) tariffs: One Part Transmission RTP and One Part Distribution Voltage RTP. These tariffs feature energy charges composed of two elements: hourly marginal costs, which are forecasted 20 minutes ahead and determined in real time without Board approval, and fixed cost adders. The fixed cost adders are updated annually and are designed to recover non-fuel-related costs incurred by Nova Scotia Power in serving eligible customers.

Preamble p. pp. 17-37
- 14 The calculations for the 2026 Fixed Cost adder are provided in Partially Confidential Appendix - 15 B2 . Please also refer to Partially Confidential Appendix D for usage determinants used in rate - 16 calculations in Partially Confide...

AI summary The document provides references to confidential appendices containing calculations for the 2026 Fixed Cost adder, usage determinants for rate calculations, and proposed 1P-RTP Tariffs. It also notes that since August 2014, Nova Scotia Power has provided service under the 1P-RTP Tariff to a transmission-connected customer who migrated a portion of its interruptible load from the Large Industrial Interruptible Rider, while maintaining the interruptible nature of that load per tariff requirements.

22 Figure 5: Shore Power Tariff Charges by Voltage and Cost Components in Cents per kWh p. p. 18
22 Figure 5: Shore Power Tariff Charges by Voltage and Cost Components in Cents per kWh 2026 2027 Variance Transmission Fuel Cost 6.900 6.406 (0.494) Fixed Cost Adder 2.507 2.576 0.069 Total 9.408 8.983 (0.425) Distribution Fuel Cost 7.062...

AI summary The document presents a data table outlining the Shore Power (SP) tariff charges for the years 2026 and 2027, broken down by transmission and distribution categories. It details the specific costs for fuel and fixed cost adders per kWh. The data shows a projected decrease in total fuel costs for both transmission and distribution between 2026 and 2027, while fixed cost adders are expected to see slight increases.

Section 39 p. p. 18
- 1 The calculations for the SP rates are provided in Appendix C2 . The proposed SP Tariff is provided - 2 as Appendix C1 . A redline version is provided in Appendix G . Please also refer to Partially - 3 Confidential Appendix D for energy...

AI summary The document provides references to various appendices containing the rate calculations and the proposed tariff for Shore Power (SP). It directs the reader to Appendix C2 for specific rate calculations, Appendix C1 for the proposed SP Tariff, and Appendix G for a redline version. It also notes that energy requirement figures used in the rate calculations are located in a confidential appendix.

21 6.2 Spill Tariff p. p. 23
21 6.2 Spill Tariff 22 23 The Spill Tariff has two components: an Administration Charge and an Energy Credit. 24 - 25 The Administration Charge is proposed to increase from the currently approved $2,487.77 to - 26 $2,562.40 per supplier, p...

AI summary The document outlines the proposed structure and adjustments for the Spill Tariff, which consists of an Administration Charge and an Energy Credit. Nova Scotia Power (NS Power) proposes increasing the monthly Administration Charge from $2,487.77 to $2,562.40 per supplier for the year 2027. This increase is based on a 3 percent escalator applied to the currently approved charge.

2027 Annually Adjusted Rates Application REDACTED p. p. 23
2027 Annually Adjusted Rates Application REDACTED - 1 for the supporting calculations. The Energy Credit is the Company's forecast average marginal - 2 energy cost as approved for use with the GRLF rate. 3 - 4 The proposed rates for 2027 a...

AI summary The document snippet pertains to the 2027 Annually Adjusted Rates Application, specifically discussing the supporting calculations for the Energy Credit. It notes that the Energy Credit is based on the Company's forecast average marginal energy cost as approved for the Grid Reliability Levy Fee (GRLF). Additionally, the text refers to the proposed rates for 2027 in comparison to 2026 charges and mentions the provision of a proposed Spill Tariff in the appendices.

7 Figure 7: Spill Tariff Charges p. pp. 23-24
7 Figure 7: Spill Tariff Charges 2026 2027 Variance Administration Charge ($/supplier/month) $2,487.77 $2,562.40 $74.63 Energy Credit (cents per kWh) 6.736 6.254 (0.482) 8

AI summary The document presents Figure 7, which outlines the projected Spill Tariff Charges for the years 2026 and 2027. It specifically details the Administration Charge per supplier per month, which is projected to increase from $2,487.77 in 2026 to $2,562.40 in 2027. Conversely, the Energy Credit per kWh is projected to decrease from 6.736 cents in 2026 to 6.254 cents in 2027.

2 3 The proposed EBS and SS tariff administration charges include the recovery of retail costs forecast 4 to be incurred in 2027 and mark the commencement of a long-term recovery of deferred costs associated with the development of the RtR market and implementation of RtR billing systems.[17](#page-26-1) 5 6 Specifically, the proposed EBS and SS Administration Charges recover costs associated with the 7 implementation and operation of the RtR market, including: 8 9 (1) recovery of approximately $5.7 million in RtR implementation capital investments over a 10 ten-year period with the inclusion of the cost of financing at the Company's Weighted 11 Average Cost of Capital (WACC); 12 p. pp. 24-26
2 3 The proposed EBS and SS tariff administration charges include the recovery of retail costs forecast 4 to be incurred in 2027 and mark the commencement of a long-term recovery of deferred costs associated with the development of the RtR...

AI summary The document outlines the proposed EBS and SS tariff administration charges, which are designed to recover retail costs forecast for 2027. These charges initiate a long-term recovery of deferred costs related to the development of the Real-Time (RtR) market and its billing systems. Specific costs include approximately $5.7 million in capital investments over ten years (including financing), $1.5 million in deferred regulatory costs from proceeding M06214, ongoing market support costs, software licensing, and dedicated operational and customer support resources.

2027 Annually Adjusted Rates Application REDACTED p. p. 27
2027 Annually Adjusted Rates Application REDACTED 1 (1) Annually adjusted average annual marginal fuel cost. 2 3 (2) Fixed Cost Adder reflective of fixed energy-related generation costs updated concurrent 4 with changes in base cost rates...

AI summary The document snippet discusses the 2027 Annually Adjusted Rates Application, specifically focusing on the average annual marginal fuel cost and the Fixed Cost Adder. It notes that the Fixed Cost Adder is updated concurrently with base cost rate changes from General Rate Applications (GRAs). Additionally, it addresses the Energy Credit applied to spilled energy, noting that its rate for 2027 is consistent with the Fuel Cost component used under the Energy Charge, with specific rates and credits compared to 2026 provided in the application's figures.

10 Figure 8: Energy Balancing Service Tariff Charges p. p. 27
10 Figure 8: Energy Balancing Service Tariff Charges 2026 2027 Variance Administration Charge ($/LRS/month) $414.63 $67,734.00 67,319.37 Energy Charge (cents per kWh) Fuel Cost (cents per kWh) 6.736 6.254 (0.482) Fixed Cost Adder (cents pe...

AI summary The document presents a comparative table of Energy Balancing Service Tariff Charges for the years 2026 and 2027. It details the Administration Charge per Load Resource System (LRS) month and breaks down the Total Energy Charge into Fuel Cost, Fixed Cost Adder, and Energy Credit components. The data shows a projected decrease in the total energy charge from 8.891 cents per kWh in 2026 to 8.507 cents per kWh in 2027.

16 7.3 Standby Service Tariff p. pp. 27-29
16 7.3 Standby Service Tariff 17 18 The Standby Service (SS) Tariff is a mandatory tariff applicable to LRSs for supplemental standby 19 generation capacity service provided in combination with EBS under the EBS Tariff. The SS Tariff 20 ha...

AI summary The text introduces the Standby Service (SS) Tariff, which is a mandatory tariff for Load Resource Systems (LRSs) providing supplemental standby generation capacity in conjunction with Electricity Bulk Supply (EBS). The tariff consists of two primary rate components: the Administration Charge and the Demand Charge. The Administration Charge is applied to each LRS account and is established annually based on anticipated administration costs and the forecasted number of LRS accounts.

2027 Annually Adjusted Rates Application REDACTED p. p. 29
2027 Annually Adjusted Rates Application REDACTED - 1 accounts. The charge is set at par with the Administration Charge under the EBS Tariff discussed - 2 above. The proposed Administration Charge for 2027 is therefore $67,734 per month. 3...

AI summary The document details proposed rate charges for 2027 as part of the Annually Adjusted Rates Application. It specifies an Administration Charge of $67,734 per month, aligned with the EBS Tariff. Additionally, it establishes a Demand Charge of $6.200 per month per kilowatt of monthly standby contract demand, which is derived from demand-related generation costs identified in the 2027 COSS. The text also references proposed System Services (SS) rate charges for 2027 relative to 2026.

17 7.4 Distribution-connected Aggregation Service Tariff p. pp. 29-30
17 7.4 Distribution-connected Aggregation Service Tariff 18 - 19 The DAS Tariff Administration Charge is intended to recover the incremental administrative costs - 20 associated with the aggregation of Distribution-Connected Generation and...

AI summary The text describes the purpose of the Distribution-connected Aggregation Service (DAS) Tariff Administration Charge. This charge is designed to recover the incremental administrative costs incurred from aggregating Distribution-Connected Generation and Net Billing Surplus. These resources are treated as additional generation sources for Licensed Retail Suppliers in the RtR market, necessitating continuous administrative oversight, including monitoring, troubleshooting, and settlement support.

Section 65 p. p. 30
19 Consistent with the approach discussed in M13008 and the broader review of RtR market elements 20 contemplated following a period of operational experience, the Company will continue to monitor 21 actual costs and participation levels a...

AI summary Nova Scotia Power (the Company) states it will continue to monitor actual costs and participation levels regarding Real-Time (RtR) market elements following a period of operational experience. The Company intends to propose refinements through future Anchor Anchor Rate (AAR) proceedings, consistent with the approach in M13008. It clarifies that the approval of the proposed Administration Charge does not provide immediate cost recovery from Renewall Energy Inc. (REI) or other market participants.

6 7.5.1.2 Annually Adjusted Energy Savings Credit p. p. 30
6 7.5.1.2 Annually Adjusted Energy Savings Credit 7 - 8 The Annually Adjusted Energy Savings Credit is designed to credit the LRS with any non-fuel - 9 energy-related cost savings arising from freed-up capacity on NS Power's system as a re...

AI summary The text discusses the Annually Adjusted Energy Savings Credit, which is intended to credit the Load Resource System (LRS) for non-fuel energy-related cost savings when bundled service loads depart for the Real-Time (RtR) market. However, Nova Scotia Power argues that these savings are limited because it must maintain generation capacity to accommodate potential customer returns. Consequently, the Company does not project any savings in this category and proposes maintaining the current value of zero for 2027.

15 7.5.1.3 Annual Energy Cost Adjustment p. p. 30
15 7.5.1.3 Annual Energy Cost Adjustment 16 - 17 The Annual Energy Cost Adjustment is designed to ensure that FAM customers are not affected - 18 by changes in system fuel costs as a result of a reduction in NS Power's generation due to th...

AI summary The Annual Energy Cost Adjustment is a mechanism designed to protect Fuel Adjustment Mechanism (FAM) customers from fuel cost fluctuations resulting from the migration of bundled service customers to the Real-Time (RtR) market. The adjustment acts as a credit or debit depending on whether the average avoided cost of departing load exceeds the average system fuel cost paid by FAM customers. For 2026 and 2027, the adjustment resulted in debits of 2.171 cents/kWh and 3.812 cents/kWh, respectively, due to specific marginal fuel cost forecasts relative to average system unit fuel costs.

1 7.5.2 RTT Demand Charge p. pp. 30-35
1 7.5.2 RTT Demand Charge 2 - 3 The Demand Charge is made up of two components: the Demand Charge from the SS Tariff and - 4 the Annually Adjusted Demand Savings Credit. 5 - 6 As discussed in Section 7.3, the proposed 2027 SS Tariff Demand...

AI summary The text describes the components of the Real-Time Pricing (RTT) Demand Charge, which consists of the System Services (SS) Tariff Demand Charge and the Annually Adjusted Demand Savings Credit. The proposed 2027 SS Tariff Demand Charge is $6.200 per month per kilowatt of monthly standby contract demand. The Company proposes that the Annually Adjusted Demand Savings Credit remains at zero for 2027, as it does not project savings from freed-up capacity due to the customer's departure to the RtR market.

23 Figure 11: Renewable to Retail Transition Tariff Charges by Cost Components p. p. 35
23 Figure 11: Renewable to Retail Transition Tariff Charges by Cost Components Energy Charge by Components (cents per kWh) 2026 2027 Variance Fixed Cost Adder from EBS Tariff 2.155 2.253 0.098 Annually Adjusted Energy Savings Credit 0.000...

AI summary The document presents a table illustrating the projected 'Renewable to Retail Transition Tariff Charges' by cost components for the years 2026 and 2027. It breaks down the energy charges into a Fixed Cost Adder from the EBS Tariff and an Annually Adjusted Energy Savings Credit. The data shows a significant increase in the Annual Energy Cost Adjustment, rising from 2.171 cents per kWh in 2026 to 3.812 cents per kWh in 2027, contributing to a total charge variance of 1.739 cents per kWh.

Backup Service p. p. 37
Backup Service The actual or estimated average time coincident incremental cost of generation including transmission losses for the period service is provided plus 0.500 cents per kWh for additional Operating and Maintenance costs, service...

AI summary The document defines the pricing structure for the Backup Service. The cost is calculated based on the actual or estimated average time coincident incremental cost of generation, which includes transmission losses for the specific service period. Additionally, a fixed amount of 0.500 cents per kWh is added to cover operating and maintenance costs, service charges, and Administration & General compensation.

STORM COST RECOVERY RIDER p. p. 37
STORM COST RECOVERY RIDER Storm Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Storm Cost Recovery Rider, shall apply, in addition to the energy charge.

AI summary The document specifies that Storm Cost Recovery charges or credits, measured in cents per kilowatt-hour, are applicable to the Tariff for the current rate year. These charges or credits are to be applied in addition to the standard energy charge as outlined in the Storm Cost Recovery Rider.

SECURITIZATION COST RECOVERY RIDER p. p. 37
SECURITIZATION COST RECOVERY RIDER Securitization Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Securitization Cost Recovery Rider, shall apply, in addition t...

AI summary The document specifies that Securitization Cost Recovery charges or credits, expressed in cents per kilowatt-hour, will be applied to the Tariff for the current rate year. These charges or credits are explicitly stated to be applicable in addition to the standard energy charge.

AVAILABILITY p. p. 37
AVAILABILITY This tariff is available to: - (a) Customers who have their own qualifying generating facility of not less than 2,000 kW of aggregate capacity, as defined under Special Condition 8, normally used to support their own load; - (...

AI summary The text outlines the availability and terms for specific electricity services, including Generation Replacement and Load Following. These services are available to customers with qualifying generating facilities of at least 2,000 kW or for Non-Utility Owned Generation sites. It specifies pricing mechanisms based on estimated or actual costs depending on notice periods and establishes that these customers will be the first prioritized for load shedding during supply shortfalls to maintain grid reliability.

SPECIAL CONDITIONS p. p. 37
SPECIAL CONDITIONS - (1) The Company reserves the right to have a separate service agreement, if in the opinion of the Company issues not specifically set out herein, must be addressed for the ongoing benefit of the Company and its custome...

AI summary The document outlines special conditions for power supply service, emphasizing the customer's responsibility to maintain grid integrity and bear costs for specialized infrastructure. It specifies that customers must ensure their load does not negatively impact the power supply system's reliability, voltage, or stability. Additionally, it defines cost responsibilities for services beyond standard step-down transformation, establishes the Company's right to determine metering locations, and sets a minimum power factor requirement of 90% lagging to avoid adjustment factors.

GENERATION LOAD FOLLOWING CRITERIA p. p. 37
GENERATION LOAD FOLLOWING CRITERIA - (1) Two months preceding each tariff year the customer-generator, in conjunction with the Company, shall establish the aggregate net operating capability of its generation equipment for the billing purp...

AI summary The text outlines the procedures for establishing 'Generation Load Following' criteria between the Company (Nova Scotia Power) and customer-generators. It requires customers to establish their aggregate net operating capability two months before each tariff year based on equipment tests or records. The Company will load follow to a 100% load factor of this capability. Provisions are included for adjusting these capabilities during periods of significant generation reduction and for the Board's approval of forecasted incremental generation costs to determine the load following rate.

ENERGY CHARGE p. p. 37
ENERGY CHARGE NSPI's actual hourly marginal energy costs, plus the following fixed cost adders for on-peak and offpeak usage: On-peak (7:00 am – 11:00 pm, non-holiday weekdays): 6.156¢/kWh Off-peak (11:00 pm – 7:00am, non-holiday weekdays)...

AI summary The text outlines the structure of the energy charge, which is based on NSPI's actual hourly marginal energy costs supplemented by specific fixed cost adders. On-peak usage (7:00 am – 11:00 pm on non-holiday weekdays) incurs an adder of 6.156¢/kWh, while off-peak usage incurs 0.918¢/kWh. Weekend and holiday hours are charged at the off-peak rate. Additionally, a credit of 32 cents per peak kilovolt-ampere is provided for customer-owned transformers. These adders are subject to annual development based on budgeted costs and require Nova Scotia Energy Board approval.

STORM COST RECOVERY RIDER p. p. 37
STORM COST RECOVERY RIDER Storm Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Storm Cost Recovery Rider, shall apply, in addition to the energy charge.

AI summary The text specifies the application of Storm Cost Recovery charges or credits to the current rate year's Tariff. These adjustments, measured in cents per kilowatt-hour, are applied in addition to the standard energy charge as outlined in the Storm Cost Recovery Rider.

SECURITIZATION COST RECOVERY RIDER p. p. 37
SECURITIZATION COST RECOVERY RIDER Securitization Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Securitization Cost Recovery Rider, shall apply, in addition t...

AI summary The document specifies that Securitization Cost Recovery charges or credits, measured in cents per kilowatt-hour, are applicable to the Tariff for the current rate year. These costs are to be applied in addition to the standard energy charge as part of the Securitization Cost Recovery Rider.

ONE PART TRANSMISSION REAL TIME PRICING TARIFF Page 2 of 3 p. p. 37
ONE PART TRANSMISSION REAL TIME PRICING TARIFF Page 2 of 3 - o By midnight each business day, hourly price forecasts for each hour of the next five days shall be provided to the customer. - o Major changes to the hourly price forecasts wil...

AI summary This section outlines the terms and conditions for the One Part Transmission Real Time Pricing Tariff. Key provisions include the requirement for hourly price forecasts to be provided to customers, rules for metering (including capital contributions for primary metering), and a mandatory twelve-month minimum service term. It also specifies conditions for customers transitioning from interruptible to firm service, including potential reimbursement requirements for capacity commitments. Finally, it establishes a minimum power factor requirement of 90% lagging.

ENERGY CHARGE p. p. 37
ENERGY CHARGE NSPI's actual hourly marginal energy costs, plus the following fixed cost adders for on-peak and offpeak usage: On-peak (7:00 am – 11:00 pm, non-holiday weekdays): 8.513¢/kWh Off-peak (11:00 pm – 7:00am, non-holiday weekdays)...

AI summary The text outlines the structure of the Energy Charge, which consists of NSPI's actual hourly marginal energy costs plus specific fixed cost adders. On-peak adders are set at 8.513¢/kWh, while off-peak adders are 3.091¢/kWh. Weekend and holiday hours utilize the off-peak rate. These adders are subject to annual budget-based submissions for Board approval. Additionally, a credit of 32 cents per peak kilovolt-ampere is provided for customers who own their transformers.

STORM COST RECOVERY RIDER p. p. 37
STORM COST RECOVERY RIDER Storm Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Storm Cost Recovery Rider, shall apply, in addition to the energy charge.

AI summary The text introduces the Storm Cost Recovery Rider, which specifies the storm cost recovery charges or credits applicable to the Tariff for the current rate year. These charges or credits are expressed in cents per kilowatt-hour and are applied in addition to the standard energy charge.

SECURITIZATION COST RECOVERY RIDER p. p. 37
SECURITIZATION COST RECOVERY RIDER Securitization Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Securitization Cost Recovery Rider, shall apply, in addition t...

AI summary The document specifies that Securitization Cost Recovery charges or credits, measured in cents per kilowatt-hour, are applicable to the Tariff for the current rate year. These charges or credits are to be applied in addition to the standard energy charge as outlined in the Securitization Cost Recovery Rider.

ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF Page 2 of 3 p. p. 37
ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF Page 2 of 3 - o By midnight each business day, hourly price forecasts for each hour of the next five days shall be provided to the customer. - o Major changes to the hourly price forec...

AI summary This section outlines the operational requirements and conditions for the Voltage Real Time Pricing Tariff. Key provisions include the requirement for the Company to provide hourly price forecasts for the next five days, rules for primary vs. secondary metering and associated capital contributions, and a minimum twelve-month service term. It also specifies conditions for transitioning from an Interruptible Rider to firm service and establishes a minimum power factor requirement of 90% lagging to avoid adjustment factors.

ENERGY CHARGE p. p. 37
ENERGY CHARGE Energy charges will vary by voltage level of the point of delivery and will be made up of two components. - (1) Annually adjusted fuel cost component which shall be the Company's forecast average annual marginal energy cost a...

AI summary The document describes the structure of energy charges, which vary based on the voltage level of the delivery point. These charges consist of two components, the first of which is an annually adjusted fuel cost component. This component is based on the Company's forecast average annual marginal energy cost, as approved for the GR&LF tariff, and is further adjusted to account for line losses at the specific delivery voltage level.

STORM COST RECOVERY RIDER p. p. 37
STORM COST RECOVERY RIDER Storm Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Storm Cost Recovery Rider, shall apply, in addition to the energy charge.

AI summary The text specifies the application of Storm Cost Recovery charges or credits to the current rate year's Tariff. These charges, measured in cents per kilowatt-hour, are applied in addition to the standard energy charge as part of the Storm Cost Recovery Rider.

SECURITIZATION COST RECOVERY RIDER p. p. 37
SECURITIZATION COST RECOVERY RIDER Securitization Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Securitization Cost Recovery Rider, shall apply, in addition t...

AI summary The document specifies that Securitization Cost Recovery charges or credits, expressed in cents per kilowatt-hour, are applicable to the Tariff for the current rate year. These costs are to be applied in addition to the standard energy charge as part of the Securitization Cost Recovery Rider.

SUPPLY INTERRUPTIONS p. p. 37
SUPPLY INTERRUPTIONS This is an interruptible service. Before connecting the ship to the shore supply the port authority will request permission from NSPI indicating the expected load and duration for which the power is needed. The custome...

AI summary The text outlines the requirements and procedures for interruptible power service provided to cruise ships via a port authority. Customers must provide written notice, maintain a dedicated telephone system with a designated staff member available at all times, and disconnect their load within ten minutes of a request from NSPI. The service is subject to specific conditions regarding load reduction, restoration approval, and the imposition of penalty charges for non-compliance with interruption requests.

CLASS : TOTAL COMPANY p. p. 37
CLASS : TOTAL COMPANY RATE BASE COSTS (Source Exh 6) Variable Fixed Unit Cost Fuel Operating Capital Return Total Total Cost Units Sold Demand Energy Customer Generation (1) Usage (Energy) $1,467,999 $646,117 $72,066 $111,286 $51,027 $234,...

AI summary The document provides a detailed cost breakdown for the 'Total Company' class, outlining the rate base, costs, and unit costs associated with generation, transmission, distribution, and retail services. It categorizes variable and fixed costs (including fuel, operating, capital, and return) across various service components like usage, reliability, and customer services. The data establishes unit costs for different delivery methods and retail categories, concluding with a total cost and unit cost calculation for the 2027 Annual Adjustment Rate (AAR) period.

DEMAND CHARGE p. p. 37
DEMAND CHARGE The demand charge for this service is made up of the following two components: - (1) Annually adjusted demand-related purchased power cost, coming into effect as a result of a Base Cost of Fuel, Fuel Adjustment Mechanism, or...

AI summary The document defines the composition of the demand charge for the specific service under review. It specifies that the demand charge consists of two components, the first of which is the annually adjusted demand-related purchased power cost. This component is influenced by various regulatory and market mechanisms, including the Base Cost of Fuel, the Fuel Adjustment Mechanism, and the General Rate Application.

- (2) Demand-related fixed generation cost, coming into effect as a result of a General Rate Application. p. p. 37
- (2) Demand-related fixed generation cost, coming into effect as a result of a General Rate Application. Demand Charge Components $ per kW of billing demand Demand-related Purchased Power Cost $8.142 Demand-related Fixed Generation Cost $...

AI summary The document outlines the demand-related fixed generation costs resulting from a General Rate Application. It provides a breakdown of demand charge components, specifically identifying the Demand-related Purchased Power Cost ($8.142 per kW) and the Demand-related Fixed Generation Cost ($6.200 per kW), totaling $14.341 per kW of billing demand. It further defines 'Contract Demand' as the firm demand requested by wholesale customers and agreed upon by Nova Scotia Power Inc. (NSPI).

SPECIAL CONDITIONS p. p. 37
SPECIAL CONDITIONS - (1) This tariff is designed for customers supplied and metered at the high side of the transformer at transmission voltage of 69 kV or higher. For customers metered at the low side of the transformer, or at a distribut...

AI summary The text outlines special conditions for customers served at transmission voltages of 69 kV or higher. It specifies meter reading adjustments for low-side customers, clarifies that transmission service costs are excluded (requiring the OATT), and grants Nova Scotia Power Inc. (NSPI) the discretion to deny service to new customers for system reasons. Additionally, it mandates that customers ensure load integrity, defines technical criteria for system impact, and establishes conditions for attributing capacity contribution factor (CCF) values for third-party generation resources.

WHOLESALE MARKET BACKUP/TOP-UP SERVICE TARIFF Page 6 of 6 p. p. 37
WHOLESALE MARKET BACKUP/TOP-UP SERVICE TARIFF Page 6 of 6 - (d) The capacity derived based on the CCF is procured and available to the wholesale customer on a minimum three-year forward basis, unless this requirement is waived by NSPI. - (...

AI summary This section of the Wholesale Market Backup/Top-Up Service Tariff outlines the procurement and delivery obligations for wholesale customers. It specifies that capacity based on the capacity contribution factor (CCF) is generally procured on a minimum three-year forward basis. It also establishes a penalty mechanism where wholesale customers must compensate Nova Scotia Power Inc. (NSPI) for the costs of procuring replacement energy or capacity in the event of a resource failure. Furthermore, it provides a process for negotiating CCF adjustments if a resource's performance is inconsistent with provided documentation, with the option for expedited Board adjudication.

ADMINISTRATION CHARGE p. p. 37
ADMINISTRATION CHARGE The monthly administration charge under this tariff is calculated according to the following formula: Monthly customer charge = forecast annual administration costs forecast number of suppliers supplying wholesale cus...

AI summary The document specifies the methodology and the resulting value for the monthly administration charge under the current tariff. The charge is calculated by multiplying the forecast annual administration costs by the forecast number of suppliers supplying wholesale customers, then dividing by 12. Based on these calculations, the monthly customer charge is established at $2,562.40.

ENERGY CREDIT p. p. 37
ENERGY CREDIT Compensation for spill energy delivered to NSPI will be at the Company's forecast average annual marginal energy costs of 6.254 cents per kilowatt hour as approved for use with the GRLF rate.

AI summary The document specifies the compensation rate for spill energy delivered to Nova Scotia Power Inc. (NSPI). The rate is set at the Company's forecast average annual marginal energy costs of 6.254 cents per kilowatt-hour, which was previously approved for use within the Generation, Resource & Load Forecasting (GRLF) rate.

2027 AAR Appendix E2 has been filed electronically. p. p. 37
2027 AAR Appendix E2 has been filed electronically. Base Cost of Fuel Cost of Service Allocation of Fuel Expenses among Rate Classes FOR THE YEAR ENDING DECEMBER 31, 2027 COLUMN A В С D E F G н 1 J к . м N 0 Р Q R : з т U v w x Υ z AA AB ....

AI summary The document provides a data table for the 2027 Annual Adjustment Rate (AAR) regarding the allocation of fuel-related costs among different rate classes. It outlines cost allocation factors, including fuel costs for FAM purposes, purchased power, biomass, and Maritime Link costs. The table differentiates between demand-related and energy-related costs, adjustments for R/C ratios, and specific cost classifications like those from COS and CA IR-001.

REDACTED 2027 AAR Appendix E3 Page 7 of 8 REDACTED (CONFIDENTIAL INFORMATION REMOVED) p. p. 37
REDACTED 2027 AAR Appendix E3 Page 7 of 8 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Wind Purchases Purchased Power Wind - NRIS Purchased Power Wind - ERIS Purchased Power Wind $ $10,554,584 $2,609,660 13,164,243.69 $ $11,025,307 $3,258,4...

AI summary The document provides a detailed financial table regarding the 2027 Annual Adjustment Rate (AAR) calculations. It breaks down costs and revenues associated with various energy sources, including wind purchases (NRIS and ERIS), COMFIT wind generation, biomass/biogas, and imports. The table also accounts for export revenues from solid fuel handling. The data serves as a component of the revenue requirement and cost recovery analysis for the upcoming adjustment period.

ADMINISTRATION CHARGE p. p. 37
ADMINISTRATION CHARGE The monthly administration charge is applicable to each LRS and is set annually according to the following formula: Monthly charge = forecast annual administration costs forecast number of LRS' subscribed \ 12 This ch...

AI summary The document defines the calculation and current value of the monthly administration charge applicable to Licensed Retail Suppliers (LRS). The charge is determined annually based on a formula that multiplies the forecast annual administration costs by the forecast number of LRS subscribers and divides by 12. The current established monthly charge is $67,734.

ENERGY CHARGE p. p. 37
ENERGY CHARGE Energy charge for top-up service is made up of the following two components: - (1) Annually adjusted fuel cost component based on NS Power's incremental cost of serving the LRS' forecasted incremental top-up load.

AI summary The text defines the components of the energy charge for top-up service. It specifies that this charge is composed of two parts, the first of which is an annually adjusted fuel cost component. This component is determined by Nova Scotia Power's incremental cost of serving the forecasted incremental top-up load provided by Licensed Retail Suppliers (LRS).

- (2) Fixed cost adder reflective of fixed cost energy-related generation costs. p. p. 37
- (2) Fixed cost adder reflective of fixed cost energy-related generation costs. Energy Charge Components cents per kWh Fuel Cost 6.254 Fixed Cost Adder 2.253 Total 8.507 The charge is applicable to top-up energy consumed in each hour.

AI summary The document specifies a tariff structure for top-up energy consumption, identifying the components of the energy charge. It outlines a Fuel Cost of 6.254 cents per kWh and a Fixed Cost Adder of 2.253 cents per kWh, resulting in a total charge of 8.507 cents per kWh. The Fixed Cost Adder is specifically designed to reflect energy-related generation costs.

ENERGY CREDIT p. p. 37
ENERGY CREDIT 6.254 cents per kilowatt-hour. The Energy Credit for spill service is set annually and is applicable to spilled energy in each hour.

AI summary The document specifies the Energy Credit rate for spill service, which is established at 6.254 cents per kilowatt-hour. This credit is determined on an annual basis and is applied to energy that is spilled during each hour of operation.

ADMINISTRATION CHARGE p. p. 37
ADMINISTRATION CHARGE The monthly administration charge is applicable to each LRS and is set annually according to the following formula: Monthly charge = forecast annual administration costs forecast number of LRS' subscribed \ 12 This ch...

AI summary The document defines the calculation and amount of the monthly administration charge applicable to Licensed Retail Suppliers (LRS). The charge is determined annually using a formula that multiplies the forecast annual administration costs by the forecast number of LRS subscribers, then divides by 12. The specific monthly charge is set at $67,734.

PURPOSE p. p. 37
PURPOSE Pursuant to Section 3G(2) of the Electricity Act (Nova Scotia), this Renewable to Retail Market Transition Tariff (RTT) is designed to recover from Licenced Retail Suppliers (LRS) NS Power's embedded fixed costs and deferred costs,...

AI summary The document outlines the purpose of the Renewable to Retail Market Transition Tariff (RTT). This tariff is established under the Electricity Act (Nova Scotia) to recover NS Power's embedded fixed costs and deferred costs from Licensed Retail Suppliers (LRS). These costs, which include generation-related expenses such as depreciation, financing costs, and income taxes, are not recovered through other applicable tariffs. The RTT specifically addresses costs previously recovered through the Bundled Service for Renewable to Retail customers.

APPLICABILITY p. p. 37
APPLICABILITY - (1) The RTT is applicable to the LRS, and is in addition to (and not in substitution of) any charges owing by the LRS to NS Power under the Open Access Transmission Tariff (OATT), the Standby Service Tariff, or the Energy B...

AI summary The text outlines the applicability and structure of the Renewable to Retail Market Transition Tariff (RTT). It specifies that the RTT is an additional charge for Licensed Retail Suppliers (LRS) and does not replace existing tariffs like the Open Access Transmission Tariff (OATT). The RTT includes provisions for savings credits based on forecasted NS Power savings from LRS electricity supply. Furthermore, it establishes an annual adjustment mechanism for Energy Charges based on the difference between average avoided costs and average system fuel costs.

ADMINISTRATION CHARGE p. p. 37
ADMINISTRATION CHARGE As a new service offering, the cost of providing this service is uncertain and the applicable regulatory practice remains to be determined. Until reviewed and, if necessary, revised at some point in the future, it is...

AI summary The document establishes the initial pricing structure for the Distribution-connected Aggregation Service (DAS), a new service offering. Because the cost of providing this service is currently uncertain, the DAS Tariff charge is limited to an Administration Charge based on forecast incremental costs. This charge is applied to each Licensed Retail Supplier (LRS) and is calculated by dividing the forecast annual administration costs by the forecast number of subscribed LRSs, resulting in an initial monthly fee of $277.71.

Backup Service p. p. 37
Backup Service The actual or estimated average time coincident incremental cost of generation including transmission losses for the period service is provided plus 0.500 cents per kWh for additional Operating and Maintenance costs, service...

AI summary The document defines the cost structure for the Backup Service. The rate is calculated based on the actual or estimated average time coincident incremental cost of generation, which includes transmission losses for the period service. Additionally, a fixed amount of 0.500 cents per kWh is added to cover Operating and Maintenance costs, service charges, and Administration & General compensation.

STORM COST RECOVERY RIDER p. p. 37
STORM COST RECOVERY RIDER Storm Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Storm Cost Recovery Rider, shall apply, in addition to the energy charge.

AI summary The text specifies the application of the Storm Cost Recovery Rider, which provides charges or credits in cents per kilowatt-hour. These amounts are applicable to the Tariff for the current rate year and are intended to be applied in addition to the standard energy charge.

SECURITIZATION COST RECOVERY RIDER p. p. 37
SECURITIZATION COST RECOVERY RIDER Securitization Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Securitization Cost Recovery Rider, shall apply, in addition t...

AI summary The text establishes the application of the Securitization Cost Recovery Rider to the Tariff for the current rate year. It specifies that the charges or credits, expressed in cents per kilowatt-hour, are to be applied in addition to the standard energy charge.

SPECIAL CONDITIONS p. p. 37
SPECIAL CONDITIONS - (1) The Company reserves the right to have a separate service agreement, if in the opinion of the Company issues not specifically set out herein, must be addressed for the ongoing benefit of the Company and its custome...

AI summary This section outlines special conditions for customers under the tariff, emphasizing customer responsibilities regarding power supply integrity, load management, and infrastructure costs. It specifies that customers must ensure their operations do not negatively impact the system's reliability or stability (e.g., harmonics, voltage flicker). Additionally, it establishes that costs for special metering, communication systems, or service requirements beyond a single step-down transformation are the customer's responsibility, while defining rules for transformer losses and power factor requirements.

ENERGY CHARGE p. p. 37
ENERGY CHARGE NSPI's actual hourly marginal energy costs, plus the following fixed cost adders for on-peak and offpeak usage: On-peak (7:00 am – 11:00 pm, non-holiday weekdays): 5.274 6.156¢/kWh Off-peak (11:00 pm – 7:00am, non-holiday wee...

AI summary The text outlines the structure of the ENERGY CHARGE, which is composed of NSPI's actual hourly marginal energy costs combined with fixed cost adders for on-peak and off-peak periods. On-peak adders are set between 5.274¢ and 6.156¢/kWh, while off-peak adders range from 0.713¢ to 0.918¢/kWh. Weekend and holiday rates align with off-peak pricing. Additionally, a credit of 32 cents per peak kilovolt-ampere is provided to customers who own their transformers. These adders are subject to annual submission and approval by the Nova Scotia Energy Board.

STORM COST RECOVERY RIDER p. p. 37
STORM COST RECOVERY RIDER Storm Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Storm Cost Recovery Rider, shall apply, in addition to the energy charge.

AI summary The text defines the application of Storm Cost Recovery charges or credits to the electricity Tariff. These costs, measured in cents per kilowatt-hour, are applicable to the current rate year and are added to the standard energy charge as part of the Storm Cost Recovery Rider.

SECURITIZATION COST RECOVERY RIDER p. p. 37
SECURITIZATION COST RECOVERY RIDER Securitization Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Securitization Cost Recovery Rider, shall apply, in addition t...

AI summary The text specifies that Securitization Cost Recovery charges or credits, expressed in cents per kilowatt-hour, are applicable to the Tariff for the current rate year. These charges or credits are to be applied in addition to the standard energy charge as outlined in the Securitization Cost Recovery Rider.

ONE PART TRANSMISSION REAL TIME PRICING TARIFF Page 2 of 3 p. p. 37
ONE PART TRANSMISSION REAL TIME PRICING TARIFF Page 2 of 3 - o By midnight each business day, hourly price forecasts for each hour of the next five days shall be provided to the customer. - o Major changes to the hourly price forecasts wil...

AI summary This section outlines the operational and contractual requirements for the One Part Transmission Real Time Pricing Tariff. Key provisions include the requirement for the Company to provide five-day hourly price forecasts, the finalization of prices twenty minutes before each hour, and the treatment of metering costs as customer capital contributions. It also specifies a minimum twelve-month contract term, rules for transitioning from interruptible to firm service for large industrial customers, and minimum power factor requirements of 90% lagging.

ENERGY CHARGE p. p. 37
ENERGY CHARGE NSPI's actual hourly marginal energy costs, plus the following fixed cost adders for on-peak and offpeak usage: On-peak (7:00 am – 11:00 pm, non-holiday weekdays): 9.925 8.513¢/kWh Off-peak (11:00 pm – 7:00am, non-holiday wee...

AI summary The document specifies the structure of the Energy Charge, which consists of NSPI's actual hourly marginal energy costs plus fixed cost adders for on-peak and off-peak usage. On-peak adders are set at 9.925 8.513¢/kWh, while off-peak adders are 3.516 3.091¢/kWh. Weekend and holiday hours are billed at off-peak rates. Additionally, a demand credit of 32 cents per peak kilovolt-ampere is provided for customer-owned transformers, with adders to be updated annually based on budgeted costs.

STORM COST RECOVERY RIDER p. p. 37
STORM COST RECOVERY RIDER Storm Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Storm Cost Recovery Rider, shall apply, in addition to the energy charge.

AI summary The document specifies the application of the Storm Cost Recovery Rider to the Tariff for the current rate year. It clarifies that Storm Cost Recovery charges or credits, expressed in cents per kilowatt-hour, are to be applied in addition to the standard energy charge.

SECURITIZATION COST RECOVERY RIDER p. p. 37
SECURITIZATION COST RECOVERY RIDER Securitization Cost Recovery charges or credits (in cents per kilowatt-hour) applicable to the Tariff for the current rate year, shown in the Securitization Cost Recovery Rider, shall apply, in addition t...

AI summary The document specifies the application of Securitization Cost Recovery charges or credits to the utility's Tariff. These costs, expressed in cents per kilowatt-hour, are applied in addition to the standard energy charge for the current rate year as defined in the Securitization Cost Recovery Rider.

ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF Page 2 of 3 p. p. 37
ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF Page 2 of 3 - o By midnight each business day, hourly price forecasts for each hour of the next five days shall be provided to the customer. - o Major changes to the hourly price forec...

AI summary This text outlines the terms and conditions for the One Part Distribution Voltage Real Time Pricing Tariff. Key provisions include the requirement for the Company to provide five-day hourly price forecasts, the finalization of hourly prices 20 minutes prior to the hour, and the treatment of metering costs as capital contributions for the customer. It specifies a minimum 12-month service term, rules for transitioning from interruptible to firm service for large industrial customers, and power factor requirements with associated adjustment factors.

- (2) A fixed cost adder adjusted concurrent with changes in base cost rates coming into effect as a result of a General Rate Case application. p. p. 37
- (2) A fixed cost adder adjusted concurrent with changes in base cost rates coming into effect as a result of a General Rate Case application. Base Energy Charge Components Transmission Voltage of 69 kV or Higher (cents per kWh) Distribut...

AI summary The document provides a breakdown of the Base Energy Charge components for different transmission and distribution voltages. It specifies the Fuel Cost and a Fixed Cost Adder, which is adjusted concurrently with base cost rate changes resulting from a General Rate Case application. The provided table quantifies these costs in cents per kWh for voltages of 69 kV or higher and for distribution voltage.

SPECIAL CONDITIONS p. p. 37
SPECIAL CONDITIONS - (1) The Port Authority owns and is responsible for the maintenance and operation of all electrical equipment required for the supply of port electricity to docked ships other than the meters and metering transformers s...

AI summary The document outlines special conditions for electricity supply to docked ships at the Port Authority. It defines ownership and maintenance responsibilities for electrical equipment and meters between the Port Authority and NSPI. Key requirements include the Port Authority's obligation to provide trained staff for interconnection, the submission of a two-year vessel demand schedule, and the customer's responsibility for capital costs associated with special metering or primary metering. It also specifies technical requirements for power factor maintenance and transformer loss adjustments.

CUSTOMER CHARGE p. p. 37
CUSTOMER CHARGE The monthly customer charge under this tariff is calculated according to the following formula: Monthly customer charge = \frac{\text{forecast annual administration costs}}{\text{forecast number of customers subscribed \ 12...

AI summary The document specifies the calculation method for the monthly customer charge under the tariff. It defines the charge as the forecast annual administration costs divided by the forecast number of customers subscribed multiplied by 12. The resulting monthly customer charge is set at $414.6342707.

DEMAND CHARGE p. p. 37
DEMAND CHARGE The demand charge for this service is made up of the following two components: - (1) Annually adjusted demand-related purchased power cost, coming into effect as a result of a Base Cost of Fuel, Fuel Adjustment Mechanism, or...

AI summary The text defines the composition of the demand charge for the service, specifying that it consists of two components. The first component is the annually adjusted demand-related purchased power cost, which is influenced by factors such as the Base Cost of Fuel, the Fuel Adjustment Mechanism, or a General Rate Application.

- (2) Energy-related fixed generation cost, coming into effect as a result of a General Rate Application. p. p. 37
- (2) Energy-related fixed generation cost, coming into effect as a result of a General Rate Application. Energy Charge Components cents per kWh Energy-related Purchased Power and Fuel Cost 6.9746.430 Energy-related Fixed Generation Cost 2...

AI summary The document presents a breakdown of energy charge components resulting from a General Rate Application. It specifies the costs for energy-related purchased power and fuel, alongside the energy-related fixed generation cost, totaling 9.1298.683 cents per kWh. The text also introduces the Fuel Adjustment Mechanism (FAM) as a component of the rate structure.

WHOLESALE MARKET BACKUP/TOP-UP SERVICE TARIFF Page 6 of 6 p. p. 37
WHOLESALE MARKET BACKUP/TOP-UP SERVICE TARIFF Page 6 of 6 - (d) The capacity derived based on the CCF is procured and available to the wholesale customer on a minimum three-year forward basis, unless this requirement is waived by NSPI. - (...

AI summary This section outlines the contractual terms for the Wholesale Market Backup/Top-Up Service Tariff. It specifies that capacity based on the Customer Capacity Factor (CCF) must be procured and available to wholesale customers on a minimum three-year forward basis unless waived by NSPI. It also establishes a penalty mechanism where customers must compensate NSPI for costs incurred due to delivery failures by Internal or External Resources, while providing a process for negotiating CCF adjustments if delivery issues arise from inconsistent documentation.

ENERGY CREDIT p. p. 37
ENERGY CREDIT Compensation for spill energy delivered to NSPI will be at the Company's forecast average annual marginal energy costs of 6.7366.254 cents per kilowatt hour as approved for use with the GRLF rate.

AI summary The document specifies the compensation rate for spill energy delivered to Nova Scotia Power Inc. (NSPI). The rate is established at the Company's forecast average annual marginal energy costs, which is set at 6.7366.254 cents per kilowatt hour. This specific rate is approved for application alongside the GRLF rate.

ADMINISTRATION CHARGE p. p. 37
ADMINISTRATION CHARGE The monthly administration charge is applicable to each LRS and is set annually according to the following formula: Monthly charge = forecast annual administration costs forecast number of LRS' subscribed \ 12 This ch...

AI summary The document specifies the calculation and amount for the monthly administration charge applicable to Licensed Retail Suppliers (LRS). The charge is determined annually based on a formula that multiplies the forecast annual administration costs by the forecast number of LRS subscribers, then divides by 12. For the current period, the monthly charge is established at $414.6367,734.

ENERGY CHARGE p. p. 37
ENERGY CHARGE Energy charge for top-up service is made up of the following two components: - (1) Annually adjusted fuel cost component based on NS Power's incremental cost of serving the LRS' forecasted incremental top-up load.

AI summary The text defines the components of the energy charge for top-up service. It specifies that the charge consists of two parts, the first of which is an annually adjusted fuel cost component. This component is calculated based on the incremental cost incurred by Nova Scotia Power to serve the forecasted incremental top-up load of Licensed Retail Suppliers (LRS).

ADMINISTRATION CHARGE p. p. 37
ADMINISTRATION CHARGE The monthly administration charge is applicable to each LRS and is set annually according to the following formula: Monthly charge = forecast annual administration costs forecast number of LRS' subscribed \ 12 This ch...

AI summary The document specifies the calculation and amount of the monthly administration charge applicable to Licensed Retail Suppliers (LRS). The charge is determined annually based on a formula that multiplies the forecast annual administration costs by the forecast number of LRS subscribers, then divides by 12. The resulting monthly charge is established at $414.6367,734.

PURPOSE p. p. 37
PURPOSE Pursuant to Section 3G(2) of the Electricity Act (Nova Scotia), this Renewable to Retail Market Transition Tariff (RTT) is designed to recover from Licenced Retail Suppliers (LRS) NS Power's embedded fixed costs and deferred costs,...

AI summary The document outlines the purpose of the Renewable to Retail Market Transition Tariff (RTT). This tariff is designed to recover NS Power's embedded fixed costs—including generation-related depreciation, financing costs, income tax, and OM&G—as well as approved deferred costs from Licensed Retail Suppliers (LRS). These costs are specifically those not recovered through other tariffs applicable to LRS or its Renewable to Retail (RtR) customers, ensuring a mechanism for cost recovery from bundled services.

APPLICABILITY p. p. 37
APPLICABILITY - (1) The RTT is applicable to the LRS, and is in addition to (and not in substitution of) any charges owing by the LRS to NS Power under the Open Access Transmission Tariff (OATT), the Standby Service Tariff, or the Energy B...

AI summary This section outlines the applicability and structural components of the Renewable to Retail Market Transition Tariff (RTT). It specifies that the RTT applies to Load Resource Suppliers (LRS) in addition to existing tariffs like the OATT, Standby Service Tariff, and Energy Balancing Service Tariff. Key provisions include usage determinants, provisions for mitigating forecasted NS Power savings via credits, and an annual adjustment mechanism to align the Energy Charge with the difference between avoided costs and average system fuel costs.

The Energy Charge is made up of the following components: p. p. 37
The Energy Charge is made up of the following components: Energy Charge Components cents per kWh Fixed Cost Adder from Energy Balancing Service Tariff 2.1552.253 Annually Adjusted Energy Savings Credit 0.000 Annual Energy Cost Adjustment 2...

AI summary The text defines the components and applicability of the Energy Charge. The charge consists of a Fixed Cost Adder from the Energy Balancing Service Tariff and an Annually Adjusted Energy Savings Credit, totaling approximately 4.33 cents per kWh. This charge applies to the monthly displaced energy of a Load Resource Supplier (LRS) on Nova Scotia Power's generation system, calculated as the total monthly LRS load (including distribution losses) minus the top-up quantity determined under the Energy Balancing Service Tariff.

The Demand Charge is made up of two components: p. p. 37
The Demand Charge is made up of two components: Demand Charge Components dollars per kW Demand Charge from Standby Service Tariff $5.6016.200 Annually Adjusted Demand Savings Credit $0.000 Total $5.6016.200 The Demand Charge is applicable...

AI summary The text defines the composition of the Demand Charge, which consists of the Demand Charge from the Standby Service Tariff and an Annually Adjusted Demand Savings Credit. It specifies that the Demand Charge applies to the monthly displaced demand on Nova Scotia Power's system for a Load Resource Supplier (LRS). This displaced demand is calculated as the difference between the LRS's Winter Peak Firm Demand and their Monthly Standby Contract Demand, as defined in the Standby Service Tariff.

ADMINISTRATION CHARGE p. p. 37
ADMINISTRATION CHARGE As a new service offering, the cost of providing this service is uncertain and the applicable regulatory practice remains to be determined. Until reviewed and, if necessary, revised at some point in the future, it is...

AI summary The document outlines the establishment of a new Administration Charge for the Distribution-connected Aggregation Service (DAS). Because the cost of this new service is currently uncertain, the DAS Tariff charge is initially limited to a monthly administration charge based on NS Power's forecast incremental costs. The charge is calculated by dividing forecast annual administration costs by the number of subscribed Load Resource Suppliers (LRS) and will be submitted to the Nova Scotia Energy Board for review and approval as part of the 2027 Annually Adjusted Rates Application.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →