HomeCost To CustomerM12744Evidence
Topic/Matter Intersection

Topic:"Cost To Customer" in M12744

Matter: Nova Scotia Power Inc. - CI C0080102 – 92H-331 Double Circuit Peggy’s Cove Rd - $4,303,210
2 passages 2 documents

Cost To Customer across all matters →

101247Letter enclosing work order / request for confidentiality 1 passage
Commercial Information p. p. 0
Commercial Information Items 1-2: Partial confidentiality was applied to costs associated with materials, contracts, consulting, First Nations Commitment, software, and licensing details provided in the capital work order(s). To protect va...

AI summary NS Power argues that maintaining confidentiality for specific costs (materials, contracts, etc.) protects customer interests by preserving competitive bidding and preventing suppliers from gaining unfair advantages. Transparent disclosure could lead to higher prices and reduced competition, ultimately increasing costs for customers.

101403NSEB (NSPI) IR-1 to IR-15 1 passage
Request IR-5:
Request IR-5: - Please provide a table outlining NS Power's cost per meter to construct three-phase feeders over each of the past five years. - a. Please identify the estimated cost per meter to construct the proposed C0080102 92H-331 Doub...

AI summary Request IR-5 seeks NS Power's historical cost-per-meter data for constructing three-phase feeders over five years, the estimated cost for a specific new feeder (C0080102 92H-331), and explanations for discrepancies between historical and projected costs.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →